Tugas — Engineering

Engineering · 80 job · 1418 telat

Engineering ENG

Done On progress Overdue Outstanding
80 job · 1730 aktivitas · 1418 telat
Nama ProjectAktivitas 1Aktivitas 2Aktivitas 3Aktivitas 4Aktivitas 5Aktivitas 6Aktivitas 7Aktivitas 8Aktivitas 9Aktivitas 10Aktivitas 11Aktivitas 12Aktivitas 13Aktivitas 14Aktivitas 15Aktivitas 16Aktivitas 17Aktivitas 18Aktivitas 19Aktivitas 20Aktivitas 21Aktivitas 22Aktivitas 23Aktivitas 24Aktivitas 25Aktivitas 26Aktivitas 27Aktivitas 28Highest Delay
MECHANICAL PROSESProduct OnlyDeadline: Oct 12, 20220/28 aktivitas selesaiCustomer VisitOverdue0/2244moPlan: Oct 19–Dec 2Draft Cutout ViewOverdue0/1744moPlan: Nov 17–Nov 18Meet / Cust VisitOverdue1/2144moPlan: Oct 19–Nov 25Actual: Oct 25Approval CutoutOverdue0/1744moPlan: Nov 18–Nov 21Aproval DrawOverdue18/4544moPlan: Oct 12–Dec 2Actual: Nov 11BOQOverdue10/4544moPlan: Oct 13–Dec 6Actual: Nov 11GAOverdue1/2844moPlan: Oct 12–Nov 28Actual: Oct 26BOM HVOverdue0/1744moPlan: Nov 21–Nov 22FEPOverdue10/4544moPlan: Oct 13–Dec 5Actual: Nov 11SLDOverdue0/2844moPlan: Oct 13–Nov 28TD PKBOverdue16/4744moPlan: Oct 14–Dec 6Actual: Nov 10Cutout listOverdue0/1744moPlan: Nov 23–Nov 24PROGRAMOverdue5/4544moPlan: Oct 13–Dec 5Actual: Oct 24SchematicsOverdue0/2844moPlan: Oct 13–Nov 29TD WeldOverdue13/4544moPlan: Oct 14–Dec 6Actual: Nov 10Wiring ListOverdue0/1744moPlan: Nov 22–Nov 22BOQ LIst Elec_LVOverdue0/2844moPlan: Oct 14–Nov 29Printout SchematicOverdue0/1744moPlan: Nov 24–Nov 24TD AssyOverdue17/4644moPlan: Oct 14–Dec 7Actual: Nov 10Tubing ListOverdue0/1744moPlan: Nov 22–Nov 23(aktivitas)Overdue0/2844moPlan: Oct 14–Nov 303D BusbarOverdue5/4244moPlan: Oct 17–Dec 8Actual: Oct 27Bom List ElectricalOverdue0/2844moPlan: Oct 14–Nov 303D AssyOverdue10/4344moPlan: Oct 17–Dec 8Actual: Nov 11Preare DOc Operation (ATP,MOP,EOP;etc)Overdue0/2844moPlan: Oct 17–Dec 1Design ReviewOverdue0/2844moPlan: Oct 17–Dec 1TD VLispOverdue3/4044moPlan: Oct 17–Dec 8Actual: Oct 19OthersOverdue16/4744moPlan: Oct 14–Dec 7Actual: Nov 1044mo
PRODUCT & DEVELOPMENTProduct OnlyDeadline: Oct 12, 20220/28 aktivitas selesaiCustomer VisitOverdue0/644moPlan: Oct 13–Nov 17Draft Cutout ViewOverdue0/245moPlan: Nov 2–Nov 3Meet / Cust VisitOverdue0/345moPlan: Oct 13–Nov 10Approval CutoutOverdue0/245moPlan: Nov 3–Nov 4Aproval DrawOverdue2/944moPlan: Oct 12–Nov 17Actual: Oct 19BOQOverdue3/1044moPlan: Oct 13–Nov 21Actual: Oct 24GAOverdue0/345moPlan: Oct 14–Nov 11BOM HVOverdue0/245moPlan: Nov 4–Nov 7FEPOverdue2/944moPlan: Oct 13–Nov 18Actual: Oct 19SLDOverdue0/345moPlan: Oct 17–Nov 11TD PKBOverdue3/1044moPlan: Oct 14–Nov 21Actual: Oct 24Cutout listOverdue0/245moPlan: Nov 8–Nov 9PROGRAMOverdue2/944moPlan: Oct 13–Nov 18Actual: Oct 19SchematicsOverdue0/344moPlan: Oct 17–Nov 14TD WeldOverdue2/944moPlan: Oct 14–Nov 21Actual: Oct 20Wiring ListOverdue0/245moPlan: Nov 7–Nov 7BOQ LIst Elec_LVOverdue0/344moPlan: Oct 18–Nov 14Printout SchematicOverdue0/245moPlan: Nov 9–Nov 9TD AssyOverdue3/1044moPlan: Oct 14–Nov 22Actual: Oct 24Tubing ListOverdue0/245moPlan: Nov 7–Nov 8(aktivitas)Overdue0/244moPlan: Nov 14–Nov 153D BusbarOverdue1/844moPlan: Oct 17–Nov 23Actual: Oct 19Bom List ElectricalOverdue0/344moPlan: Oct 19–Nov 153D AssyOverdue1/844moPlan: Oct 17–Nov 23Actual: Oct 19Preare DOc Operation (ATP,MOP,EOP;etc)Overdue0/344moPlan: Oct 20–Nov 16Design ReviewOverdue0/344moPlan: Oct 19–Nov 16TD VLispOverdue2/944moPlan: Oct 17–Nov 23Actual: Oct 21OthersOverdue3/1044moPlan: Oct 14–Nov 22Actual: Oct 2445mo
ELEC_ LV_SYSTEMProduct OnlyDeadline: Oct 27, 20220/28 aktivitas selesaiCustomer VisitOverdue0/244moPlan: Oct 19–Nov 22Draft Cutout ViewOverdue0/145moPlan: Nov 7–Nov 8Meet / Cust VisitOverdue0/4544moPlan: Oct 12–Nov 15Approval CutoutOverdue0/145moPlan: Nov 8–Nov 9Aproval DrawOverdue0/244moPlan: Oct 20–Nov 22BOQOverdue0/244moPlan: Oct 21–Nov 24GAOverdue8/12044moPlan: Oct 12–Nov 16Actual: Oct 20BOM HVOverdue0/145moPlan: Nov 9–Nov 10FEPOverdue0/244moPlan: Oct 20–Nov 23SLDOverdue4/11844moPlan: Oct 13–Nov 16Actual: Oct 20TD PKBOverdue0/244moPlan: Oct 24–Nov 24Cutout listOverdue0/144moPlan: Nov 11–Nov 14PROGRAMOverdue0/244moPlan: Oct 21–Nov 23SchematicsOverdue9/11344moPlan: Oct 13–Nov 17Actual: Oct 26TD WeldOverdue0/244moPlan: Oct 24–Nov 24Wiring ListOverdue0/145moPlan: Nov 10–Nov 10BOQ LIst Elec_LVOverdue5/11244moPlan: Oct 14–Nov 17Actual: Oct 20Printout SchematicOverdue0/144moPlan: Nov 14–Nov 14TD AssyOverdue0/244moPlan: Oct 24–Nov 25Tubing ListOverdue0/145moPlan: Nov 10–Nov 11(aktivitas)Overdue1/11244moPlan: Oct 14–Nov 18Actual: Oct 143D BusbarOverdue0/244moPlan: Oct 25–Nov 28Bom List ElectricalOverdue5/11244moPlan: Oct 14–Nov 18Actual: Oct 193D AssyOverdue0/244moPlan: Oct 26–Nov 28Preare DOc Operation (ATP,MOP,EOP;etc)Overdue1/11444moPlan: Oct 17–Nov 21Actual: Oct 20Design ReviewOverdue3/11244moPlan: Oct 17–Nov 21Actual: Oct 19TD VLispOverdue0/244moPlan: Oct 26–Nov 28OthersOverdue0/244moPlan: Oct 25–Nov 2545mo
Internal - Stock Rack Server Moratel & DCPDUProduct + InstalasiDeadline: Jan 30, 20261/28 aktivitas selesaiMembuat Approval Drawing GAOverdue0/28moPlan: Nov 7–Nov 7Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 17–Nov 17Membuat Approval Drawing GA-SLD/cutoutOverdue0/18moPlan: Nov 12–Nov 12Membuat BomlistOverdue0/18moPlan: Nov 12–Nov 13Membuat BomlistDone1/1Plan: Nov 10–Nov 10Actual: Nov 10Membuat Timeline instalasiOverdue0/18moPlan: Nov 17–Nov 18Membuat BomlistOverdue0/18moPlan: Nov 18–Nov 18Membuat SchematicOverdue0/28moPlan: Nov 13–Nov 13Technical DrawingOverdue0/18moPlan: Nov 10–Nov 10Vlisp Technical Drawing Overdue0/18moPlan: Nov 10–Nov 10Melakukan Design ReviewOverdue0/18moPlan: Nov 11–Nov 11Membuat Dxf Cutout / nameplateOverdue0/18moPlan: Nov 13–Nov 14Membuat MOP/WIOverdue0/18moPlan: Nov 18–Nov 19TD BusbarOverdue0/18moPlan: Nov 10–Nov 113D design Overdue0/18moPlan: Nov 11–Nov 11Membuat MOP/WIOverdue0/18moPlan: Nov 14–Nov 14Membuat SOPOverdue0/18moPlan: Nov 19–Nov 19Permintaan Customer VisitOverdue0/18moPlan: Nov 12–Nov 12Membuat Form FAT, ATP, SATOverdue0/18moPlan: Nov 19–Nov 20Membuat Form FAT, Onsite, SATOverdue0/18moPlan: Nov 14–Nov 14Membuat MOP/WIOverdue0/48moPlan: Nov 12–Nov 12Melakukan Design ReviewOverdue0/18moPlan: Nov 14–Nov 17Membuat Materi TrainingOverdue0/38moPlan: Nov 12–Nov 12Membuat Materi TrainingOverdue0/18moPlan: Nov 20–Nov 20TD BusbarOverdue0/18moPlan: Nov 11–Nov 12Membuat Materi TrainingOverdue0/18moPlan: Nov 17–Nov 17Permintaan Customer VisitOverdue0/38moPlan: Nov 20–Nov 20Permintaan Customer VisitOverdue0/38moPlan: Nov 17–Nov 178mo
Kelinci Mas - DSS TallolamaProduct OnlyDeadline: Aug 7, 20260/27 aktivitas selesaiMembuat Approval Drawing GAOverdue1/249moPlan: Oct 1–Oct 11Actual: Oct 2Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 6–Nov 7Membuat Approval Drawing GA-SLD/cutoutOverdue1/248moPlan: Oct 14–Nov 2Actual: Oct 3Membuat BomlistOverdue1/248moPlan: Oct 10–Oct 30Actual: Oct 31Membuat BomlistOverdue1/248moPlan: Oct 15–Nov 2Actual: Oct 13Membuat Timeline instalasiOverdue0/18moPlan: Nov 7–Nov 7Membuat BomlistOverdue0/18moPlan: Nov 7–Nov 8Membuat SchematicOverdue1/248moPlan: Oct 15–Nov 5Actual: Nov 5Technical DrawingOverdue1/248moPlan: Oct 13–Oct 31Actual: Oct 31Vlisp Technical Drawing Overdue1/248moPlan: Oct 10–Oct 30Actual: Oct 31Melakukan Design ReviewOverdue1/248moPlan: Oct 14–Nov 1Actual: Nov 10Membuat Dxf Cutout / nameplateOverdue1/248moPlan: Oct 16–Nov 5Actual: Oct 3Membuat MOP/WIOverdue0/18moPlan: Nov 8–Nov 8TD BusbarOverdue1/248moPlan: Oct 10–Oct 31Actual: Oct 313D design Overdue1/248moPlan: Oct 13–Oct 31Actual: Oct 31Membuat MOP/WIOverdue1/248moPlan: Oct 16–Nov 5Actual: Nov 5Membuat SOPOverdue0/18moPlan: Nov 8–Nov 9Permintaan Customer VisitOverdue0/248moPlan: Oct 14–Nov 1Membuat Form FAT, ATP, SATOverdue0/18moPlan: Nov 9–Nov 9Membuat Form FAT, Onsite, SATOverdue1/248moPlan: Oct 16–Nov 6Actual: Nov 5Membuat MOP/WIOverdue0/18moPlan: Nov 1–Nov 1Melakukan Design ReviewOverdue1/248moPlan: Oct 17–Nov 6Actual: Nov 11Membuat Materi TrainingOverdue0/18moPlan: Nov 1–Nov 1Membuat Materi TrainingOverdue0/18moPlan: Nov 9–Nov 9TD BusbarOverdue1/248moPlan: Oct 13–Nov 1Actual: Oct 31Membuat Materi TrainingOverdue0/248moPlan: Oct 17–Nov 6Permintaan Customer VisitOverdue0/18moPlan: Nov 6–Nov 6-9mo
GSPE_STOK BOX PANEL MORATELProduct + InstalasiDeadline: Aug 13, 20250/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/311moPlan: Aug 22–Aug 25Membuat Approval Drawing GA-SLDOverdue0/310moPlan: Sep 1–Sep 2Membuat Approval Drawing GA-SLD/cutoutOverdue0/310moPlan: Aug 27–Aug 28Membuat BomlistOverdue0/311moPlan: Aug 25–Aug 25Membuat BomlistOverdue0/310moPlan: Aug 28–Aug 28Membuat Timeline instalasiOverdue0/310moPlan: Sep 2–Sep 2Membuat BomlistOverdue0/310moPlan: Sep 2–Sep 3Membuat SchematicOverdue0/310moPlan: Aug 28–Aug 28Technical DrawingOverdue0/311moPlan: Aug 25–Aug 26Melakukan Design ReviewOverdue0/311moPlan: Aug 26–Aug 26Membuat Dxf Cutout / nameplateOverdue0/310moPlan: Aug 28–Aug 29Membuat MOP/WIOverdue0/310moPlan: Sep 3–Sep 3Membuat MOP/WIOverdue0/310moPlan: Aug 29–Aug 29Membuat SOPOverdue0/310moPlan: Sep 3–Sep 3Permintaan Customer VisitOverdue0/311moPlan: Aug 26–Aug 27Membuat Form FAT, ATP, SATOverdue0/310moPlan: Sep 3–Sep 4Membuat Form FAT, Onsite, SATOverdue0/310moPlan: Aug 29–Aug 29Membuat MOP/WIOverdue0/311moPlan: Aug 27–Aug 27Melakukan Design ReviewOverdue0/310moPlan: Aug 29–Sep 1Membuat Materi TrainingOverdue0/311moPlan: Aug 27–Aug 27Membuat Materi TrainingOverdue0/310moPlan: Sep 4–Sep 4Membuat Materi TrainingOverdue0/310moPlan: Sep 1–Sep 1Permintaan Customer VisitOverdue0/310moPlan: Sep 4–Sep 4Permintaan Customer VisitOverdue0/310moPlan: Sep 1–Sep 1----11mo
Forecast_Stock Panel Hitachi IP42 & IP54Product + InstalasiDeadline: Oct 10, 20250/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/310moPlan: Sep 24–Sep 25Membuat Approval Drawing GA-SLDOverdue0/39moPlan: Oct 2–Oct 3Membuat Approval Drawing GA-SLD/cutoutOverdue0/39moPlan: Sep 29–Sep 30Membuat BomlistOverdue0/310moPlan: Sep 25–Sep 25Membuat BomlistOverdue0/39moPlan: Sep 30–Sep 30Membuat Timeline instalasiOverdue0/39moPlan: Oct 3–Oct 3Membuat BomlistOverdue0/39moPlan: Oct 3–Oct 6Membuat SchematicOverdue0/39moPlan: Sep 30–Sep 30Technical DrawingOverdue0/310moPlan: Sep 25–Sep 26Melakukan Design ReviewOverdue0/310moPlan: Sep 26–Sep 26Membuat Dxf Cutout / nameplateOverdue0/39moPlan: Sep 30–Oct 1Membuat MOP/WIOverdue0/39moPlan: Oct 6–Oct 6Membuat MOP/WIOverdue0/39moPlan: Oct 1–Oct 1Membuat SOPOverdue0/39moPlan: Oct 6–Oct 6Permintaan Customer VisitOverdue0/39moPlan: Sep 26–Sep 29Membuat Form FAT, ATP, SATOverdue0/39moPlan: Oct 6–Oct 7Membuat Form FAT, Onsite, SATOverdue0/39moPlan: Oct 1–Oct 1Membuat MOP/WIOverdue0/39moPlan: Sep 29–Sep 29Melakukan Design ReviewOverdue0/39moPlan: Oct 1–Oct 2Membuat Materi TrainingOverdue0/39moPlan: Sep 29–Sep 29Membuat Materi TrainingOverdue0/39moPlan: Oct 7–Oct 7Membuat Materi TrainingOverdue0/39moPlan: Oct 2–Oct 2Permintaan Customer VisitOverdue0/39moPlan: Oct 7–Oct 7Permintaan Customer VisitOverdue0/39moPlan: Oct 2–Oct 2----10mo
PTT - Module MPTT DPC 3000 HE (25 unit)Product + InstalasiDeadline: Dec 19, 20250/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/17moPlan: Dec 18–Dec 18Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Dec 26–Dec 26Membuat Approval Drawing GA-SLD/cutoutOverdue0/27moPlan: Dec 23–Dec 23Membuat BomlistOverdue0/17moPlan: Dec 18–Dec 19Membuat BomlistOverdue0/17moPlan: Dec 23–Dec 24Membuat Timeline instalasiOverdue0/16moPlan: Dec 26–Dec 29Membuat BomlistOverdue0/16moPlan: Dec 29–Dec 29Membuat SchematicOverdue0/17moPlan: Dec 24–Dec 24Technical DrawingOverdue0/17moPlan: Dec 19–Dec 19Melakukan Design ReviewOverdue0/17moPlan: Dec 19–Dec 22Membuat Dxf Cutout / nameplateOverdue0/27moPlan: Dec 24–Dec 24Membuat MOP/WIOverdue0/26moPlan: Dec 29–Dec 30Membuat MOP/WIOverdue0/17moPlan: Dec 24–Dec 25Membuat SOPOverdue0/16moPlan: Dec 30–Dec 30Permintaan Customer VisitOverdue0/17moPlan: Dec 22–Dec 22Membuat Form FAT, ATP, SATOverdue0/16moPlan: Dec 30–Dec 30Membuat Form FAT, Onsite, SATOverdue0/27moPlan: Dec 25–Dec 25Membuat MOP/WIOverdue0/27moPlan: Dec 22–Dec 23Melakukan Design ReviewOverdue0/17moPlan: Dec 25–Dec 25Membuat Materi TrainingOverdue0/17moPlan: Dec 23–Dec 23Membuat Materi TrainingOverdue0/26moPlan: Dec 30–Dec 31Membuat Materi TrainingOverdue0/16moPlan: Dec 25–Dec 26Permintaan Customer VisitOverdue0/16moPlan: Dec 31–Dec 31Permintaan Customer VisitOverdue0/16moPlan: Dec 26–Dec 26----7mo
BDX - CGK1_RACK SERVER & rPDUProduct + InstalasiDeadline: Feb 6, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue2/36moPlan: Dec 17–Dec 31Actual: Dec 17Membuat Approval Drawing GA-SLDOverdue1/46moPlan: Dec 17–Jan 8Actual: Dec 17Membuat Approval Drawing GA-SLD/cutoutOverdue1/26moPlan: Dec 17–Jan 5Actual: Dec 17Membuat BomlistOverdue2/36moPlan: Dec 18–Dec 31Actual: Dec 18Membuat BomlistOverdue1/26moPlan: Dec 17–Jan 5Actual: Dec 17Membuat Timeline instalasiOverdue1/46moPlan: Nov 18–Jan 8Actual: Dec 18Membuat BomlistOverdue1/46moPlan: Nov 19–Jan 9Actual: Dec 18Membuat SchematicOverdue1/26moPlan: Dec 16–Jan 5Actual: Dec 17Technical DrawingOverdue2/36moPlan: Dec 18–Jan 1Actual: Dec 18Melakukan Design ReviewOverdue2/36moPlan: Dec 18–Jan 1Actual: Dec 18Membuat Dxf Cutout / nameplateOverdue1/26moPlan: Dec 16–Jan 6Actual: Dec 17Membuat MOP/WIOverdue0/46moPlan: Nov 19–Jan 19Membuat MOP/WIOverdue0/26moPlan: Jan 6–Jan 19Membuat SOPOverdue0/46moPlan: Jan 9–Jan 19Permintaan Customer VisitOverdue2/36moPlan: Dec 18–Jan 2Actual: Dec 31Membuat Form FAT, ATP, SATOverdue0/56moPlan: Jan 9–Jan 19Membuat Form FAT, Onsite, SATOverdue0/86moPlan: Jan 6–Jan 19Membuat MOP/WIOverdue1/36moPlan: Jan 2–Jan 19Actual: Jan 19Melakukan Design ReviewOverdue1/26moPlan: Dec 24–Jan 7Actual: Dec 19Membuat Materi TrainingOverdue0/36moPlan: Jan 2–Jan 19Membuat Materi TrainingOverdue0/36moPlan: Jan 12–Jan 22Membuat Materi TrainingOverdue0/36moPlan: Dec 24–Jan 7Permintaan Customer VisitOverdue0/25moPlan: Jan 12–Jan 30Permintaan Customer VisitOverdue1/26moPlan: Dec 25–Jan 7Actual: Dec 22----6mo
Internal - Layout Penambahan Unit Mesin HSGProduct + InstalasiDeadline: Feb 6, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/35moPlan: Feb 2–Feb 2Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 10–Feb 10Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 5–Feb 5Membuat BomlistOverdue0/15moPlan: Feb 2–Feb 3Membuat BomlistOverdue0/15moPlan: Feb 5–Feb 6Membuat Timeline instalasiOverdue0/15moPlan: Feb 10–Feb 11Membuat BomlistOverdue0/15moPlan: Feb 11–Feb 11Membuat SchematicOverdue0/25moPlan: Feb 6–Feb 6Technical DrawingOverdue0/15moPlan: Feb 3–Feb 3Melakukan Design ReviewOverdue0/15moPlan: Feb 3–Feb 4Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 6–Feb 6Membuat MOP/WIOverdue0/15moPlan: Feb 11–Feb 12Membuat MOP/WIOverdue0/15moPlan: Feb 6–Feb 9Membuat SOPOverdue0/15moPlan: Feb 12–Feb 12Permintaan Customer VisitOverdue0/15moPlan: Feb 4–Feb 4Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 12–Feb 12Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 9–Feb 9Membuat MOP/WIOverdue0/15moPlan: Feb 4–Feb 5Melakukan Design ReviewOverdue0/15moPlan: Feb 9–Feb 9Membuat Materi TrainingOverdue0/15moPlan: Feb 5–Feb 5Membuat Materi TrainingOverdue0/15moPlan: Feb 12–Feb 13Membuat Materi TrainingOverdue0/15moPlan: Feb 9–Feb 10Permintaan Customer VisitOverdue0/15moPlan: Feb 13–Feb 13Permintaan Customer VisitOverdue0/15moPlan: Feb 10–Feb 10----5mo
Job LeaderProduct + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/18moPlan: Nov 19–Nov 20Membuat Approval Drawing GA-SLDOverdue0/17moPlan: Nov 27–Nov 28Membuat Approval Drawing GA-SLD/cutoutOverdue0/18moPlan: Nov 24–Nov 25Membuat BomlistOverdue0/26moPlan: Nov 25–Dec 31Membuat BomlistOverdue1/26moPlan: Nov 20–Jan 13Actual: Jan 13Membuat Timeline instalasiOverdue0/17moPlan: Nov 28–Nov 28Membuat BomlistOverdue0/17moPlan: Nov 28–Dec 1Membuat SchematicOverdue0/26moPlan: Nov 25–Jan 9Technical DrawingOverdue0/18moPlan: Nov 20–Nov 21Melakukan Design ReviewOverdue0/26moPlan: Nov 19–Jan 12Membuat Dxf Cutout / nameplateOverdue0/17moPlan: Nov 25–Nov 26Membuat MOP/WIOverdue0/17moPlan: Dec 1–Dec 1Membuat MOP/WIOverdue0/17moPlan: Nov 26–Nov 26Membuat SOPOverdue0/17moPlan: Dec 1–Dec 1Permintaan Customer VisitOverdue0/18moPlan: Nov 21–Nov 24Membuat Form FAT, ATP, SATOverdue0/17moPlan: Dec 1–Dec 2Membuat Form FAT, Onsite, SATOverdue0/17moPlan: Nov 26–Nov 26Membuat MOP/WIOverdue0/18moPlan: Nov 24–Nov 24Melakukan Design ReviewOverdue0/26moPlan: Nov 26–Jan 12Membuat Materi TrainingOverdue0/18moPlan: Nov 24–Nov 24Membuat Materi TrainingOverdue0/17moPlan: Dec 2–Dec 2Membuat Materi TrainingOverdue0/17moPlan: Nov 27–Nov 27Permintaan Customer VisitOverdue0/17moPlan: Dec 2–Dec 2Permintaan Customer VisitOverdue0/17moPlan: Nov 27–Nov 27----8mo
Internal - Project ISO_27001Product + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/35moPlan: Jan 30–Jan 30Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 9Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 4Membuat BomlistOverdue0/15moPlan: Jan 30–Feb 2Membuat BomlistOverdue0/25moPlan: Feb 4–Feb 5Membuat Timeline instalasiOverdue0/15moPlan: Feb 9–Feb 10Membuat BomlistOverdue0/25moPlan: Feb 10–Feb 10Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5Technical DrawingOverdue0/15moPlan: Feb 2–Feb 2Melakukan Design ReviewOverdue0/15moPlan: Feb 2–Feb 3Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 5Membuat MOP/WIOverdue0/15moPlan: Feb 10–Feb 11Membuat MOP/WIOverdue0/15moPlan: Feb 5–Feb 6Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11Permintaan Customer VisitOverdue0/25moPlan: Feb 3–Feb 3Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 11Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6Membuat MOP/WIOverdue0/15moPlan: Feb 3–Feb 4Melakukan Design ReviewOverdue0/35moPlan: Feb 6–Feb 6Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4Membuat Materi TrainingOverdue0/15moPlan: Feb 11–Feb 12Membuat Materi TrainingOverdue0/15moPlan: Feb 6–Feb 9Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12Permintaan Customer VisitOverdue0/15moPlan: Feb 9–Feb 9----5mo
Internal - Program Estimator (Containment, Container, Smart Rack)Product + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Jan 30–Feb 2Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 10Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 5Membuat BomlistOverdue0/15moPlan: Feb 2–Feb 2Membuat BomlistOverdue0/15moPlan: Feb 5–Feb 5Membuat Timeline instalasiOverdue0/15moPlan: Feb 10–Feb 10Membuat BomlistOverdue0/15moPlan: Feb 10–Feb 11Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5Technical DrawingOverdue0/15moPlan: Feb 2–Feb 3Melakukan Design ReviewOverdue0/15moPlan: Feb 3–Feb 3Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 6Membuat MOP/WIOverdue0/15moPlan: Feb 11–Feb 11Membuat MOP/WIOverdue0/15moPlan: Feb 6–Feb 6Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 4Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 12Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6Membuat MOP/WIOverdue0/15moPlan: Feb 4–Feb 4Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 9Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4Membuat Materi TrainingOverdue0/15moPlan: Feb 12–Feb 12Membuat Materi TrainingOverdue0/15moPlan: Feb 9–Feb 9Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12Permintaan Customer VisitOverdue0/15moPlan: Feb 9–Feb 9----5mo
Internal - Automation Program CRM Section 1-4Product + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Jan 30–Feb 2Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 10Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 5Membuat BomlistOverdue0/15moPlan: Feb 2–Feb 2Membuat BomlistOverdue0/15moPlan: Feb 5–Feb 5Membuat Timeline instalasiOverdue0/15moPlan: Feb 10–Feb 10Membuat BomlistOverdue0/15moPlan: Feb 10–Feb 11Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5Technical DrawingOverdue0/15moPlan: Feb 2–Feb 3Melakukan Design ReviewOverdue0/15moPlan: Feb 3–Feb 3Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 6Membuat MOP/WIOverdue0/15moPlan: Feb 11–Feb 11Membuat MOP/WIOverdue0/15moPlan: Feb 6–Feb 6Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 4Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 12Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6Membuat MOP/WIOverdue0/15moPlan: Feb 4–Feb 4Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 9Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4Membuat Materi TrainingOverdue0/15moPlan: Feb 12–Feb 12Membuat Materi TrainingOverdue0/15moPlan: Feb 9–Feb 9Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12Permintaan Customer VisitOverdue0/15moPlan: Feb 9–Feb 9----5mo
Internal - Perbaikan Loading/Unloading Area Pintu BelakangProduct + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/25moPlan: Jan 30–Jan 30Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 9Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 4Membuat BomlistOverdue0/15moPlan: Jan 30–Feb 2Membuat BomlistOverdue0/25moPlan: Feb 4–Feb 5Membuat Timeline instalasiOverdue0/15moPlan: Feb 9–Feb 10Membuat BomlistOverdue0/15moPlan: Feb 10–Feb 10Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5Technical DrawingOverdue0/25moPlan: Feb 2–Feb 2Melakukan Design ReviewOverdue0/25moPlan: Feb 2–Feb 3Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 5Membuat MOP/WIOverdue0/15moPlan: Feb 10–Feb 11Membuat MOP/WIOverdue0/25moPlan: Feb 5–Feb 6Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 3Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 11Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6Membuat MOP/WIOverdue0/15moPlan: Feb 3–Feb 4Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 6Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4Membuat Materi TrainingOverdue0/15moPlan: Feb 11–Feb 12Membuat Materi TrainingOverdue0/25moPlan: Feb 6–Feb 9Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12Permintaan Customer VisitOverdue0/25moPlan: Feb 9–Feb 9----5mo
Review Product Presentation - Marketing UpdateProduct + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Jan 30–Jan 30Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 9Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 4Membuat BomlistOverdue0/15moPlan: Jan 30–Feb 2Membuat BomlistOverdue0/15moPlan: Feb 4–Feb 5Membuat Timeline instalasiOverdue0/15moPlan: Feb 9–Feb 10Membuat BomlistOverdue0/15moPlan: Feb 10–Feb 10Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5Technical DrawingOverdue0/15moPlan: Feb 2–Feb 2Melakukan Design ReviewOverdue0/15moPlan: Feb 2–Feb 3Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 5Membuat MOP/WIOverdue0/15moPlan: Feb 10–Feb 11Membuat MOP/WIOverdue0/15moPlan: Feb 5–Feb 6Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 3Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 11Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6Membuat MOP/WIOverdue0/15moPlan: Feb 3–Feb 4Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 6Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4Membuat Materi TrainingOverdue0/15moPlan: Feb 11–Feb 12Membuat Materi TrainingOverdue0/15moPlan: Feb 6–Feb 9Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12Permintaan Customer VisitOverdue0/15moPlan: Feb 9–Feb 9----5mo
Mega Akses - POP Tegal Cangkring-Bali (Add Battery)Product + InstalasiDeadline: Mar 13, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Jan 26–Jan 27Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 3–Feb 4Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Jan 29–Jan 30Membuat BomlistOverdue0/15moPlan: Jan 27–Jan 27Membuat BomlistOverdue0/15moPlan: Jan 30–Jan 30Membuat Timeline instalasiOverdue0/15moPlan: Feb 4–Feb 4Membuat BomlistOverdue0/15moPlan: Feb 4–Feb 5Membuat SchematicOverdue0/15moPlan: Jan 30–Jan 30Technical DrawingOverdue0/15moPlan: Jan 27–Jan 28Melakukan Design ReviewOverdue0/15moPlan: Jan 28–Jan 28Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Jan 30–Feb 2Membuat MOP/WIOverdue0/15moPlan: Feb 5–Feb 5Membuat MOP/WIOverdue0/15moPlan: Feb 2–Feb 2Membuat SOPOverdue0/15moPlan: Feb 5–Feb 5Permintaan Customer VisitOverdue0/15moPlan: Jan 28–Jan 29Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 5–Feb 6Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 2–Feb 2Membuat MOP/WIOverdue0/15moPlan: Jan 29–Jan 29Melakukan Design ReviewOverdue0/15moPlan: Feb 2–Feb 3Membuat Materi TrainingOverdue0/15moPlan: Jan 29–Jan 29Membuat Materi TrainingOverdue0/15moPlan: Feb 6–Feb 6Membuat Materi TrainingOverdue0/15moPlan: Feb 3–Feb 3Permintaan Customer VisitOverdue0/15moPlan: Feb 6–Feb 6Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 3----5mo
Mega Akses - Req.Battery - JABODETABEKProduct + InstalasiDeadline: Apr 10, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Feb 10–Feb 11Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 18–Feb 19Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 13–Feb 16Membuat BomlistOverdue0/15moPlan: Feb 11–Feb 11Membuat BomlistOverdue0/15moPlan: Feb 16–Feb 16Membuat Timeline instalasiOverdue0/15moPlan: Feb 19–Feb 19Membuat BomlistOverdue0/15moPlan: Feb 19–Feb 20Membuat SchematicOverdue0/15moPlan: Feb 16–Feb 16Technical DrawingOverdue0/15moPlan: Feb 11–Feb 12Melakukan Design ReviewOverdue0/15moPlan: Feb 12–Feb 12Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 16–Feb 17Membuat MOP/WIOverdue0/15moPlan: Feb 20–Feb 20Membuat MOP/WIOverdue0/15moPlan: Feb 17–Feb 17Membuat SOPOverdue0/15moPlan: Feb 20–Feb 20Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 13Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 20–Feb 23Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 17–Feb 17Membuat MOP/WIOverdue0/15moPlan: Feb 13–Feb 13Melakukan Design ReviewOverdue0/15moPlan: Feb 17–Feb 18Membuat Materi TrainingOverdue0/15moPlan: Feb 13–Feb 13Membuat Materi TrainingOverdue0/15moPlan: Feb 23–Feb 23Membuat Materi TrainingOverdue0/15moPlan: Feb 18–Feb 18Permintaan Customer VisitOverdue0/15moPlan: Feb 23–Feb 23Permintaan Customer VisitOverdue0/15moPlan: Feb 18–Feb 18----5mo
INTERNAL | - MDCC Trial Full Schneider Device - ContainerProduct + InstalasiDeadline: Apr 20, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/96moPlan: Dec 22–Jan 1Membuat Approval Drawing GA-SLDOverdue0/95moPlan: Dec 30–Feb 5Membuat Approval Drawing GA-SLD/cutoutOverdue0/96moPlan: Nov 20–Dec 26Membuat BomlistOverdue1/97moPlan: Nov 11–Dec 23Actual: Jan 12Membuat BomlistOverdue1/96moPlan: Nov 21–Dec 26Actual: Mar 2Membuat Timeline instalasiOverdue0/115moPlan: Dec 31–Feb 6Membuat BomlistOverdue0/95moPlan: Dec 31–Feb 6Membuat SchematicOverdue0/126moPlan: Nov 21–Dec 26Technical DrawingOverdue0/107moPlan: Nov 11–Dec 24Melakukan Design ReviewOverdue1/197moPlan: Nov 11–Dec 24Actual: Feb 4Membuat Dxf Cutout / nameplateOverdue0/105moPlan: Dec 26–Feb 1Membuat MOP/WIOverdue0/115moPlan: Jan 1–Feb 7Membuat MOP/WIOverdue0/95moPlan: Dec 29–Feb 4Membuat SOPOverdue0/115moPlan: Jan 1–Feb 7Permintaan Customer VisitOverdue0/107moPlan: Nov 19–Dec 25Membuat Form FAT, ATP, SATOverdue0/95moPlan: Jan 1–Feb 7Membuat Form FAT, Onsite, SATOverdue0/95moPlan: Dec 29–Feb 4Membuat MOP/WIOverdue0/97moPlan: Nov 19–Dec 25Melakukan Design ReviewOverdue0/95moPlan: Dec 29–Feb 4Membuat Materi TrainingOverdue0/97moPlan: Nov 20–Dec 25Membuat Materi TrainingOverdue0/115moPlan: Jan 2–Feb 8Membuat Materi TrainingOverdue0/95moPlan: Dec 30–Feb 5Permintaan Customer VisitOverdue0/95moPlan: Jan 2–Feb 8Permintaan Customer VisitOverdue0/95moPlan: Dec 30–Feb 5----7mo
Mega Akses - BDF Power Tanah Merah (Add Battery)Product + InstalasiDeadline: Apr 30, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/14moPlan: Feb 23–Feb 24Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Mar 3–Mar 4Membuat Approval Drawing GA-SLD/cutoutOverdue0/14moPlan: Feb 26–Feb 27Membuat BomlistOverdue0/14moPlan: Feb 24–Feb 24Membuat BomlistOverdue0/14moPlan: Feb 27–Feb 27Membuat Timeline instalasiOverdue0/14moPlan: Mar 4–Mar 4Membuat BomlistOverdue0/14moPlan: Mar 4–Mar 5Membuat SchematicOverdue0/14moPlan: Feb 27–Feb 27Technical DrawingOverdue0/14moPlan: Feb 24–Feb 25Melakukan Design ReviewOverdue0/14moPlan: Feb 25–Feb 25Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Feb 27–Mar 2Membuat MOP/WIOverdue0/14moPlan: Mar 5–Mar 5Membuat MOP/WIOverdue0/14moPlan: Mar 2–Mar 2Membuat SOPOverdue0/14moPlan: Mar 5–Mar 5Permintaan Customer VisitOverdue0/14moPlan: Feb 25–Feb 26Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 5–Mar 6Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Mar 2–Mar 2Membuat MOP/WIOverdue0/14moPlan: Feb 26–Feb 26Melakukan Design ReviewOverdue0/14moPlan: Mar 2–Mar 3Membuat Materi TrainingOverdue0/14moPlan: Feb 26–Feb 26Membuat Materi TrainingOverdue0/14moPlan: Mar 6–Mar 6Membuat Materi TrainingOverdue0/14moPlan: Mar 3–Mar 3Permintaan Customer VisitOverdue0/14moPlan: Mar 6–Mar 6Permintaan Customer VisitOverdue0/14moPlan: Mar 3–Mar 3----4mo
BDX - CGK1_Panel PDUProduct + InstalasiDeadline: May 21, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue1/26moPlan: Oct 30–Jan 1Actual: Dec 17Membuat Approval Drawing GA-SLDOverdue0/17moPlan: Nov 4–Dec 14Membuat Approval Drawing GA-SLD/cutoutOverdue1/26moPlan: Oct 30–Jan 6Actual: Dec 17Membuat BomlistOverdue1/26moPlan: Oct 31–Jan 2Actual: Dec 19Membuat BomlistOverdue1/26moPlan: Oct 30–Jan 7Actual: Jan 9Membuat Timeline instalasiOverdue0/18moPlan: Oct 30–Nov 2Membuat BomlistOverdue0/17moPlan: Dec 2–Dec 2Membuat SchematicOverdue1/26moPlan: Oct 30–Jan 7Actual: Dec 17Technical DrawingOverdue1/26moPlan: Oct 31–Jan 2Actual: Dec 19Melakukan Design ReviewOverdue1/26moPlan: Nov 3–Jan 5Actual: Dec 19Membuat Dxf Cutout / nameplateOverdue1/26moPlan: Oct 30–Jan 7Actual: Dec 17Membuat MOP/WIOverdue0/17moPlan: Dec 2–Dec 3Membuat MOP/WIOverdue1/25moPlan: Jan 7–Jan 28Actual: Jan 28Membuat SOPOverdue0/17moPlan: Dec 2–Dec 5Permintaan Customer VisitOverdue1/26moPlan: Nov 3–Jan 5Actual: Jan 2Membuat Form FAT, ATP, SATOverdue0/17moPlan: Dec 4–Dec 4Membuat Form FAT, Onsite, SATOverdue1/26moPlan: Dec 2–Jan 8Actual: Jan 23Membuat MOP/WIOverdue1/25moPlan: Jan 5–Jan 28Actual: Jan 28Melakukan Design ReviewOverdue1/26moPlan: Dec 2–Jan 8Actual: Dec 19Membuat Materi TrainingOverdue0/17moPlan: Dec 4–Dec 5Membuat Materi TrainingOverdue0/26moPlan: Dec 2–Jan 6Membuat Materi TrainingOverdue0/26moPlan: Dec 2–Jan 9Permintaan Customer VisitOverdue0/17moPlan: Dec 5–Dec 5Permintaan Customer VisitOverdue1/26moPlan: Nov 4–Jan 9Actual: Jan 22----8mo
Internal - Forecast Rack Server : (42U, 45U, 52U)Product + InstalasiDeadline: May 29, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/36moPlan: Dec 22–Dec 31Membuat Approval Drawing GA-SLDOverdue0/34moPlan: Dec 30–Mar 21Membuat Approval Drawing GA-SLD/cutoutOverdue0/35moPlan: Dec 25–Feb 1Membuat BomlistOverdue0/55moPlan: Dec 22–Jan 30Membuat BomlistOverdue0/55moPlan: Dec 25–Feb 2Membuat Timeline instalasiOverdue0/34moPlan: Dec 30–Mar 22Membuat BomlistOverdue0/44moPlan: Dec 31–Mar 22Membuat SchematicOverdue0/35moPlan: Dec 26–Feb 2Technical DrawingOverdue0/35moPlan: Dec 23–Jan 30Melakukan Design ReviewOverdue0/85moPlan: Dec 23–Jan 31Membuat Dxf Cutout / nameplateOverdue0/35moPlan: Dec 26–Feb 2Membuat MOP/WIOverdue0/44moPlan: Dec 31–Mar 23Membuat MOP/WIOverdue0/45moPlan: Dec 26–Feb 5Membuat SOPOverdue0/34moPlan: Jan 1–Mar 23Permintaan Customer VisitOverdue0/35moPlan: Dec 24–Jan 31Membuat Form FAT, ATP, SATOverdue0/44moPlan: Jan 1–Mar 23Membuat Form FAT, Onsite, SATOverdue0/35moPlan: Dec 29–Feb 5Membuat MOP/WIOverdue0/35moPlan: Dec 24–Feb 1Melakukan Design ReviewOverdue0/34moPlan: Dec 29–Mar 21Membuat Materi TrainingOverdue0/35moPlan: Dec 25–Feb 1Membuat Materi TrainingOverdue0/34moPlan: Jan 1–Mar 24Membuat Materi TrainingOverdue0/34moPlan: Dec 29–Mar 21Permintaan Customer VisitOverdue0/44moPlan: Jan 2–Mar 24Permintaan Customer VisitOverdue0/44moPlan: Dec 30–Mar 21----6mo
Intan Mufakat Raya - GIS 150 KV Gandul II/PamulangProduct + InstalasiDeadline: Jun 10, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/14moPlan: Mar 4–Mar 5Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Mar 12–Mar 13Membuat Approval Drawing GA-SLD/cutoutOverdue0/14moPlan: Mar 9–Mar 10Membuat BomlistOverdue0/14moPlan: Mar 5–Mar 5Membuat BomlistOverdue0/14moPlan: Mar 10–Mar 10Membuat Timeline instalasiOverdue0/14moPlan: Mar 13–Mar 13Membuat BomlistOverdue0/14moPlan: Mar 13–Mar 16Membuat SchematicOverdue0/14moPlan: Mar 10–Mar 10Technical DrawingOverdue0/14moPlan: Mar 5–Mar 6Melakukan Design ReviewOverdue0/14moPlan: Mar 6–Mar 6Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Mar 10–Mar 11Membuat MOP/WIOverdue0/14moPlan: Mar 16–Mar 16Membuat MOP/WIOverdue0/14moPlan: Mar 11–Mar 11Membuat SOPOverdue0/14moPlan: Mar 16–Mar 16Permintaan Customer VisitOverdue0/14moPlan: Mar 6–Mar 9Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 16–Mar 17Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Mar 11–Mar 11Membuat MOP/WIOverdue0/14moPlan: Mar 9–Mar 9Melakukan Design ReviewOverdue0/14moPlan: Mar 11–Mar 12Membuat Materi TrainingOverdue0/14moPlan: Mar 9–Mar 9Membuat Materi TrainingOverdue0/14moPlan: Mar 17–Mar 17Membuat Materi TrainingOverdue0/14moPlan: Mar 12–Mar 12Permintaan Customer VisitOverdue0/14moPlan: Mar 17–Mar 17Permintaan Customer VisitOverdue0/14moPlan: Mar 12–Mar 12----4mo
Internal - Pembuatan Bak Treatment, Hoist, Oven dan TrolleyProduct + InstalasiDeadline: Jun 30, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/76moPlan: Nov 24–Jan 5Membuat Approval Drawing GA-SLDOverdue0/46moPlan: Dec 2–Jan 13Membuat Approval Drawing GA-SLD/cutoutOverdue0/66moPlan: Nov 27–Jan 8Membuat BomlistOverdue0/56moPlan: Nov 24–Jan 14Membuat BomlistOverdue1/55moPlan: Nov 27–Jan 26Actual: Jan 26Membuat Timeline instalasiOverdue0/46moPlan: Dec 2–Jan 14Membuat BomlistOverdue0/46moPlan: Dec 3–Jan 14Membuat SchematicOverdue0/55moPlan: Nov 28–Jan 30Technical DrawingOverdue0/66moPlan: Nov 25–Jan 6Melakukan Design ReviewOverdue1/56moPlan: Nov 25–Jan 15Actual: Jan 15Membuat Dxf Cutout / nameplateOverdue0/46moPlan: Nov 28–Jan 9Membuat MOP/WIOverdue0/56moPlan: Dec 3–Jan 15Membuat MOP/WIOverdue0/56moPlan: Nov 28–Jan 12Membuat SOPOverdue0/66moPlan: Dec 4–Jan 15Permintaan Customer VisitOverdue0/56moPlan: Nov 26–Jan 7Membuat Form FAT, ATP, SATOverdue0/46moPlan: Dec 4–Jan 15Membuat Form FAT, Onsite, SATOverdue0/56moPlan: Dec 1–Jan 12Membuat MOP/WIOverdue0/56moPlan: Nov 26–Jan 8Melakukan Design ReviewOverdue0/86moPlan: Dec 1–Jan 13Membuat Materi TrainingOverdue0/46moPlan: Nov 27–Jan 8Membuat Materi TrainingOverdue0/56moPlan: Dec 4–Jan 16Membuat Materi TrainingOverdue0/56moPlan: Dec 1–Jan 13Permintaan Customer VisitOverdue0/46moPlan: Dec 5–Jan 16Permintaan Customer VisitOverdue0/56moPlan: Dec 2–Jan 13----6mo
ATOZ - Dakota Electrical Fitout (Batam)Product + InstalasiDeadline: Jul 24, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/14wPlan: Jun 9–Jun 10Membuat Approval Drawing GA-SLDOverdue0/13wPlan: Jun 17–Jun 18Membuat Approval Drawing GA-SLD/cutoutOverdue0/13wPlan: Jun 12–Jun 15Membuat BomlistOverdue0/14wPlan: Jun 10–Jun 10Membuat BomlistOverdue0/13wPlan: Jun 15–Jun 15Membuat Timeline instalasiOverdue0/13wPlan: Jun 18–Jun 18Membuat BomlistOverdue0/13wPlan: Jun 18–Jun 19Membuat SchematicOverdue0/13wPlan: Jun 15–Jun 15Technical DrawingOverdue0/14wPlan: Jun 10–Jun 11Melakukan Design ReviewOverdue0/14wPlan: Jun 11–Jun 11Membuat Dxf Cutout / nameplateOverdue0/13wPlan: Jun 15–Jun 16Membuat MOP/WIOverdue0/13wPlan: Jun 19–Jun 19Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16Membuat SOPOverdue0/13wPlan: Jun 19–Jun 19Permintaan Customer VisitOverdue0/14wPlan: Jun 11–Jun 12Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 19–Jun 22Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 16–Jun 16Membuat MOP/WIOverdue0/14wPlan: Jun 12–Jun 12Melakukan Design ReviewOverdue0/13wPlan: Jun 16–Jun 17Membuat Materi TrainingOverdue0/14wPlan: Jun 12–Jun 12Membuat Materi TrainingOverdue0/12wPlan: Jun 22–Jun 22Membuat Materi TrainingOverdue0/13wPlan: Jun 17–Jun 17Permintaan Customer VisitOverdue0/12wPlan: Jun 22–Jun 22Permintaan Customer VisitOverdue0/13wPlan: Jun 17–Jun 17----4w
BDX CGK3 - Electrical MaterialProduct + InstalasiDeadline: Jul 24, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/14wPlan: Jun 11–Jun 12Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22Membuat Approval Drawing GA-SLD/cutoutOverdue0/13wPlan: Jun 16–Jun 17Membuat BomlistOverdue0/14wPlan: Jun 12–Jun 12Membuat BomlistOverdue0/13wPlan: Jun 17–Jun 17Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23Membuat SchematicOverdue0/13wPlan: Jun 17–Jun 17Technical DrawingOverdue0/13wPlan: Jun 12–Jun 15Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15Membuat Dxf Cutout / nameplateOverdue0/13wPlan: Jun 17–Jun 18Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19----4w
Mega Akes - HUB Majalengka (Add Battery)Product + InstalasiDeadline: Jul 31, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Feb 20–Feb 23Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Mar 2–Mar 3Membuat Approval Drawing GA-SLD/cutoutOverdue0/14moPlan: Feb 25–Feb 26Membuat BomlistOverdue0/15moPlan: Feb 23–Feb 23Membuat BomlistOverdue0/14moPlan: Feb 26–Feb 26Membuat Timeline instalasiOverdue0/14moPlan: Mar 3–Mar 3Membuat BomlistOverdue0/14moPlan: Mar 3–Mar 4Membuat SchematicOverdue0/14moPlan: Feb 26–Feb 26Technical DrawingOverdue0/14moPlan: Feb 23–Feb 24Melakukan Design ReviewOverdue0/14moPlan: Feb 24–Feb 24Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Feb 26–Feb 27Membuat MOP/WIOverdue0/14moPlan: Mar 4–Mar 4Membuat MOP/WIOverdue0/14moPlan: Feb 27–Feb 27Membuat SOPOverdue0/14moPlan: Mar 4–Mar 4Permintaan Customer VisitOverdue0/14moPlan: Feb 24–Feb 25Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 4–Mar 5Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Feb 27–Feb 27Membuat MOP/WIOverdue0/14moPlan: Feb 25–Feb 25Melakukan Design ReviewOverdue0/14moPlan: Feb 27–Mar 2Membuat Materi TrainingOverdue0/14moPlan: Feb 25–Feb 25Membuat Materi TrainingOverdue0/14moPlan: Mar 5–Mar 5Membuat Materi TrainingOverdue0/14moPlan: Mar 2–Mar 2Permintaan Customer VisitOverdue0/14moPlan: Mar 5–Mar 5Permintaan Customer VisitOverdue0/14moPlan: Mar 2–Mar 2----5mo
Hitachi - ACP25105 - Seko IndokomasProduct + InstalasiDeadline: Aug 12, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/14wPlan: Jun 11–Jun 12Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22Membuat Approval Drawing GA-SLD/cutoutOverdue0/13wPlan: Jun 16–Jun 17Membuat BomlistOverdue0/14wPlan: Jun 12–Jun 12Membuat BomlistOverdue0/13wPlan: Jun 17–Jun 17Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23Membuat SchematicOverdue0/13wPlan: Jun 17–Jun 17Technical DrawingOverdue0/13wPlan: Jun 12–Jun 15Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15Membuat Dxf Cutout / nameplateOverdue0/13wPlan: Jun 17–Jun 18Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19----4w
Demo/Mockup Panel Typetest Cubic, Eaton MV, Eaton LVProduct + InstalasiDeadline: Aug 31, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/45moPlan: Jan 30–Feb 2Membuat Approval Drawing GA-SLDOverdue0/55moPlan: Feb 9–Feb 10Membuat Approval Drawing GA-SLD/cutoutOverdue0/54moPlan: Feb 4–Feb 25Membuat BomlistOverdue0/75moPlan: Jan 30–Feb 2Membuat BomlistOverdue1/74moPlan: Feb 4–Mar 2Actual: Feb 5Membuat Timeline instalasiOverdue0/35moPlan: Feb 9–Feb 10Membuat BomlistOverdue0/55moPlan: Feb 10–Feb 11Membuat SchematicOverdue0/64moPlan: Feb 5–Feb 26Technical DrawingOverdue0/44moPlan: Jan 19–Feb 25Melakukan Design ReviewOverdue0/55moPlan: Feb 2–Feb 3Membuat Dxf Cutout / nameplateOverdue0/25moPlan: Feb 5–Feb 5Membuat MOP/WIOverdue0/35moPlan: Feb 10–Feb 11Membuat MOP/WIOverdue0/35moPlan: Feb 5–Feb 6Membuat SOPOverdue0/45moPlan: Feb 11–Feb 11Permintaan Customer VisitOverdue0/25moPlan: Feb 3–Feb 3Membuat Form FAT, ATP, SATOverdue0/35moPlan: Feb 11–Feb 11Membuat Form FAT, Onsite, SATOverdue0/25moPlan: Feb 6–Feb 6Membuat MOP/WIOverdue0/25moPlan: Feb 3–Feb 4Melakukan Design ReviewOverdue0/25moPlan: Feb 6–Feb 9Membuat Materi TrainingOverdue0/25moPlan: Feb 4–Feb 4Membuat Materi TrainingOverdue0/45moPlan: Feb 11–Feb 12Membuat Materi TrainingOverdue0/25moPlan: Feb 6–Feb 9Permintaan Customer VisitOverdue0/35moPlan: Feb 12–Feb 12Permintaan Customer VisitOverdue0/25moPlan: Feb 9–Feb 9----5mo
PANEL MCC FIXEDProduct OnlyDeadline: Sep 13, 20220/23 aktivitas selesaiAproval DrawOverdue0/846moPlan: Sep 16–Sep 21BOQOverdue0/846moPlan: Sep 14–Sep 20GAOverdue0/546moPlan: Sep 13–Sep 15FEPOverdue0/846moPlan: Sep 14–Sep 19SLDOverdue0/246moPlan: Sep 13–Sep 14TD PKBOverdue0/846moPlan: Sep 14–Sep 20PROGRAMOverdue2/846moPlan: Sep 14–Sep 19Actual: Sep 19SchematicsOverdue1/546moPlan: Sep 14–Sep 15Actual: Oct 13TD WeldOverdue0/846moPlan: Sep 15–Sep 20BOQ LIst Elec_LVOverdue1/546moPlan: Sep 14–Sep 15Actual: Oct 13TD AssyOverdue0/846moPlan: Sep 15–Sep 20WiringList x TubingOverdue0/346moPlan: Sep 15–Sep 15(aktivitas)Overdue0/146moPlan: Sep 15–Sep 153D BusbarOverdue0/846moPlan: Sep 15–Sep 21Bom List ElectricalOverdue1/546moPlan: Sep 15–Sep 16Actual: Oct 17CUT OUTOverdue0/346moPlan: Sep 15–Sep 153D AssyOverdue0/846moPlan: Sep 16–Sep 21Preare DOc Operation (ATP,MOP,EOP;etc)Overdue1/546moPlan: Sep 13–Sep 16Actual: Oct 19Design ReviewOverdue1/546moPlan: Sep 15–Sep 16Actual: Oct 17OthersOverdue0/346moPlan: Sep 16–Sep 16TD VLispOverdue0/846moPlan: Sep 13–Sep 21OthersOverdue0/846moPlan: Sep 15–Sep 21(aktivitas)Overdue0/646moPlan: Sep 16–Sep 21-----46mo
Shimizu - Loadbank IRISProduct + InstalasiDeadline: Feb 22, 20261/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Feb 22–Feb 22Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 20–Nov 20Membuat Approval Drawing GA-SLD/cutoutOverdue0/18moPlan: Nov 17–Nov 17Membuat BomlistOverdue0/18moPlan: Nov 12–Nov 13Membuat BomlistOverdue0/18moPlan: Nov 17–Nov 18Membuat Timeline instalasiOverdue0/38moPlan: Nov 13–Nov 16Membuat BomlistDone1/1Plan: Nov 16–Nov 17Actual: Nov 13Membuat SchematicOverdue0/18moPlan: Nov 18–Nov 18Technical DrawingOverdue0/18moPlan: Nov 16–Nov 16Vlisp Technical Drawing Overdue0/18moPlan: Nov 13–Nov 13Melakukan Design ReviewOverdue0/18moPlan: Nov 16–Nov 17Membuat Dxf Cutout / nameplateOverdue0/18moPlan: Nov 18–Nov 19Membuat MOP/WIOverdue0/18moPlan: Nov 17–Nov 17TD BusbarOverdue0/18moPlan: Nov 13–Nov 133D design Overdue0/18moPlan: Nov 13–Nov 16Membuat MOP/WIOverdue0/18moPlan: Nov 19–Nov 19Membuat SOPOverdue0/18moPlan: Nov 17–Nov 18Permintaan Customer VisitOverdue0/18moPlan: Nov 17–Nov 17Membuat Form FAT, ATP, SATOverdue0/18moPlan: Nov 18–Nov 18Membuat Form FAT, Onsite, SATOverdue0/38moPlan: Nov 19–Nov 19Melakukan Design ReviewOverdue0/18moPlan: Nov 19–Nov 20Membuat Materi TrainingOverdue0/18moPlan: Nov 18–Nov 18TD BusbarOverdue0/18moPlan: Nov 16–Nov 16Membuat Materi TrainingOverdue0/18moPlan: Nov 20–Nov 20----8mo
PT Telin - Instalasi CLS PluitProduct + InstalasiDeadline: Feb 26, 20261/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Feb 16–Feb 17Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Feb 24–Feb 25Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 19–Feb 20Membuat BomlistOverdue0/15moPlan: Feb 20–Feb 20Membuat BomlistDone1/1Plan: Feb 17–Feb 17Actual: Feb 11Membuat Timeline instalasiOverdue0/14moPlan: Feb 25–Feb 25Membuat BomlistOverdue0/14moPlan: Feb 25–Feb 26Membuat SchematicOverdue0/15moPlan: Feb 20–Feb 20Technical DrawingOverdue0/15moPlan: Feb 17–Feb 18Melakukan Design ReviewOverdue0/15moPlan: Feb 18–Feb 18Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 20–Feb 23Membuat MOP/WIOverdue0/14moPlan: Feb 26–Feb 26Membuat MOP/WIOverdue0/15moPlan: Feb 23–Feb 23Membuat SOPOverdue0/14moPlan: Feb 26–Feb 26Permintaan Customer VisitOverdue0/15moPlan: Feb 18–Feb 19Membuat Form FAT, ATP, SATOverdue0/14moPlan: Feb 26–Feb 27Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 23–Feb 23Membuat MOP/WIOverdue0/15moPlan: Feb 19–Feb 19Melakukan Design ReviewOverdue0/14moPlan: Feb 23–Feb 24Membuat Materi TrainingOverdue0/15moPlan: Feb 19–Feb 19Membuat Materi TrainingOverdue0/14moPlan: Feb 27–Feb 27Membuat Materi TrainingOverdue0/14moPlan: Feb 24–Feb 24Permintaan Customer VisitOverdue0/14moPlan: Feb 27–Feb 27Permintaan Customer VisitOverdue0/14moPlan: Feb 24–Feb 24----5mo
Internal - Micro Data Centre EatonProduct + InstalasiDeadline: Jan 23, 20262/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/16moPlan: Dec 29–Dec 29Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Jan 8–Jan 8Membuat Approval Drawing GA-SLD/cutoutOverdue0/16moPlan: Jan 3–Jan 3Membuat BomlistOverdue0/16moPlan: Dec 29–Jan 1Membuat BomlistDone1/11dPlan: Jan 4–Jan 4Actual: Jan 5Membuat Timeline instalasiOverdue0/16moPlan: Jan 8–Jan 9Membuat BomlistOverdue0/26moPlan: Jan 9–Jan 9Membuat SchematicDone1/11dPlan: Jan 4–Jan 4Actual: Jan 5Technical DrawingOverdue0/26moPlan: Jan 1–Jan 1Melakukan Design ReviewOverdue0/16moPlan: Jan 1–Jan 2Membuat Dxf Cutout / nameplateOverdue0/16moPlan: Jan 4–Jan 4Membuat MOP/WIOverdue0/16moPlan: Jan 9–Jan 10Membuat MOP/WIOverdue0/16moPlan: Jan 4–Jan 5Membuat SOPOverdue0/16moPlan: Jan 10–Jan 10Permintaan Customer VisitOverdue0/16moPlan: Jan 2–Jan 2Membuat Form FAT, ATP, SATOverdue0/16moPlan: Jan 10–Jan 10Membuat Form FAT, Onsite, SATOverdue0/16moPlan: Jan 5–Jan 5Membuat MOP/WIOverdue0/16moPlan: Jan 2–Jan 3Melakukan Design ReviewOverdue0/16moPlan: Jan 5–Jan 5Membuat Materi TrainingOverdue0/16moPlan: Jan 3–Jan 3Membuat Materi TrainingOverdue0/26moPlan: Jan 10–Jan 11Membuat Materi TrainingOverdue0/16moPlan: Jan 5–Jan 8Permintaan Customer VisitOverdue0/16moPlan: Jan 11–Jan 11Permintaan Customer VisitOverdue0/16moPlan: Jan 8–Jan 8----6mo
Internal - Mini Data Center Rack (MDCR) from ScheneiderProduct + InstalasiDeadline: Mar 27, 20262/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/15moPlan: Feb 2–Feb 5Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 12–Feb 12Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 7–Feb 8Membuat BomlistDone1/12moPlan: Feb 5–Feb 5Actual: Apr 17Membuat BomlistDone1/11moPlan: Feb 8–Feb 8Actual: Mar 16Membuat Timeline instalasiOverdue0/15moPlan: Feb 12–Feb 13Membuat BomlistOverdue0/15moPlan: Feb 13–Feb 13Membuat SchematicOverdue0/15moPlan: Feb 8–Feb 8Technical DrawingOverdue0/15moPlan: Feb 5–Feb 6Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 6Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 8–Feb 8Membuat MOP/WIOverdue0/15moPlan: Feb 13–Feb 14Membuat MOP/WIOverdue0/15moPlan: Feb 8–Feb 9Membuat SOPOverdue0/15moPlan: Feb 14–Feb 14Permintaan Customer VisitOverdue0/15moPlan: Feb 6–Feb 6Membuat Form FAT, ATP, SATOverdue0/25moPlan: Feb 14–Feb 14Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 9–Feb 9Membuat MOP/WIOverdue0/15moPlan: Feb 6–Feb 7Melakukan Design ReviewOverdue0/15moPlan: Feb 9–Feb 12Membuat Materi TrainingOverdue0/15moPlan: Feb 7–Feb 7Membuat Materi TrainingOverdue0/15moPlan: Feb 14–Feb 15Membuat Materi TrainingOverdue0/15moPlan: Feb 9–Feb 12Permintaan Customer VisitOverdue0/15moPlan: Feb 15–Feb 15Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12----5mo
Mock Up - PT. Enerkomp Persada Raya Panel Soft Starter 250KWProduct + InstalasiDeadline: Mar 31, 20262/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/17moPlan: Dec 16–Dec 16Membuat Approval Drawing GA-SLDOverdue0/27moPlan: Dec 24–Dec 24Membuat Approval Drawing GA-SLD/cutoutOverdue0/17moPlan: Dec 19–Dec 19Membuat BomlistDone1/1Plan: Dec 17–Dec 17Actual: Dec 4Membuat BomlistDone1/1Plan: Dec 22–Dec 22Actual: Dec 4Membuat Timeline instalasiOverdue0/17moPlan: Dec 24–Dec 25Membuat BomlistOverdue0/27moPlan: Dec 25–Dec 25Membuat SchematicOverdue1/37moPlan: Dec 22–Dec 23Actual: Dec 4Technical DrawingOverdue0/17moPlan: Dec 17–Dec 17Melakukan Design ReviewOverdue1/37moPlan: Dec 17–Dec 18Actual: Dec 16Membuat Dxf Cutout / nameplateOverdue0/17moPlan: Dec 22–Dec 23Membuat MOP/WIOverdue0/16moPlan: Dec 25–Dec 26Membuat MOP/WIOverdue0/17moPlan: Dec 23–Dec 23Membuat SOPOverdue0/16moPlan: Dec 26–Dec 26Permintaan Customer VisitOverdue0/17moPlan: Dec 18–Dec 18Membuat Form FAT, ATP, SATOverdue0/26moPlan: Dec 26–Dec 29Membuat Form FAT, Onsite, SATOverdue0/17moPlan: Dec 23–Dec 23Membuat MOP/WIOverdue0/17moPlan: Dec 18–Dec 19Melakukan Design ReviewOverdue0/27moPlan: Dec 23–Dec 24Membuat Materi TrainingOverdue0/17moPlan: Dec 19–Dec 19Membuat Materi TrainingOverdue0/16moPlan: Dec 29–Dec 29Membuat Materi TrainingOverdue0/17moPlan: Dec 24–Dec 24Permintaan Customer VisitOverdue0/16moPlan: Dec 29–Dec 29Permintaan Customer VisitOverdue0/27moPlan: Dec 24–Dec 24----7mo
Internal - Smart rPDUProduct + InstalasiDeadline: Apr 30, 20262/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/25moPlan: Jan 16–Jan 26Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Jan 23–Jan 23Membuat Approval Drawing GA-SLD/cutoutOverdue0/16moPlan: Jan 21–Jan 21Membuat BomlistOverdue0/25moPlan: Jan 16–Jan 28Membuat BomlistDone1/1Plan: Jan 28–Jan 29Actual: Jan 29Membuat Timeline instalasiOverdue0/16moPlan: Jan 23–Jan 24Membuat BomlistOverdue0/16moPlan: Jan 24–Jan 24Membuat SchematicDone1/1Plan: Jan 26–Jan 28Actual: Jan 28Technical DrawingOverdue0/16moPlan: Jan 19–Jan 19Melakukan Design ReviewOverdue0/25moPlan: Jan 19–Jan 26Membuat Dxf Cutout / nameplateOverdue0/16moPlan: Jan 19–Jan 19Membuat MOP/WIOverdue0/15moPlan: Jan 24–Jan 25Membuat MOP/WIOverdue0/16moPlan: Jan 19–Jan 20Membuat SOPOverdue0/15moPlan: Jan 25–Jan 25Permintaan Customer VisitOverdue0/16moPlan: Jan 20–Jan 20Membuat Form FAT, ATP, SATOverdue0/15moPlan: Jan 25–Jan 25Membuat Form FAT, Onsite, SATOverdue0/26moPlan: Jan 20–Jan 20Membuat MOP/WIOverdue0/36moPlan: Jan 20–Jan 21Melakukan Design ReviewOverdue0/26moPlan: Jan 20–Jan 20Membuat Materi TrainingOverdue0/16moPlan: Jan 21–Jan 21Membuat Materi TrainingOverdue0/15moPlan: Jan 25–Jan 26Membuat Materi TrainingOverdue0/16moPlan: Jan 20–Jan 23Permintaan Customer VisitOverdue0/15moPlan: Jan 26–Jan 26Permintaan Customer VisitOverdue0/16moPlan: Jan 23–Jan 23----6mo
Pembuatan Robot AGVProduct + InstalasiDeadline: Jul 24, 20262/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/16moPlan: Jan 20–Jan 20Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Jan 28–Jan 28Membuat Approval Drawing GA-SLD/cutoutOverdue0/16moPlan: Jan 23–Jan 23Membuat BomlistDone1/1Plan: Jan 21–Jan 21Actual: Jan 21Membuat BomlistDone1/12wPlan: Jan 26–Jan 26Actual: Feb 12Membuat Timeline instalasiOverdue0/15moPlan: Jan 28–Jan 29Membuat BomlistOverdue0/15moPlan: Jan 29–Jan 29Membuat SchematicOverdue0/15moPlan: Jan 26–Jan 26Technical DrawingOverdue0/16moPlan: Jan 21–Jan 21Melakukan Design ReviewOverdue0/16moPlan: Jan 21–Jan 22Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Jan 26–Jan 26Membuat MOP/WIOverdue0/15moPlan: Jan 29–Jan 30Membuat MOP/WIOverdue0/15moPlan: Jan 26–Jan 27Membuat SOPOverdue0/15moPlan: Jan 30–Jan 30Permintaan Customer VisitOverdue0/16moPlan: Jan 22–Jan 22Membuat Form FAT, ATP, SATOverdue0/15moPlan: Jan 30–Jan 30Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Jan 27–Jan 27Membuat MOP/WIOverdue0/16moPlan: Jan 22–Jan 23Melakukan Design ReviewOverdue0/15moPlan: Jan 27–Jan 27Membuat Materi TrainingOverdue0/16moPlan: Jan 23–Jan 23Membuat Materi TrainingOverdue0/15moPlan: Jan 30–Feb 2Membuat Materi TrainingOverdue0/15moPlan: Jan 27–Jan 28Permintaan Customer VisitOverdue0/25moPlan: Feb 2–Feb 2Permintaan Customer VisitOverdue0/25moPlan: Jan 28–Jan 28----6mo
DNA Teknologi Indonesia - Caging System DHIProduct + InstalasiDeadline: Jul 28, 20262/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/13wPlan: Jun 16–Jun 17Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 24–Jun 25Membuat Approval Drawing GA-SLD/cutoutOverdue0/12wPlan: Jun 19–Jun 22Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 22Membuat BomlistDone1/16dPlan: Jun 17–Jun 17Actual: Jun 23Membuat Timeline instalasiOverdue0/12wPlan: Jun 25–Jun 25Membuat BomlistOverdue0/12wPlan: Jun 25–Jun 26Membuat SchematicOverdue0/12wPlan: Jun 22–Jun 22Technical DrawingDone1/15dPlan: Jun 17–Jun 18Actual: Jun 23Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 18Membuat Dxf Cutout / nameplateOverdue0/12wPlan: Jun 22–Jun 23Membuat MOP/WIOverdue0/12wPlan: Jun 26–Jun 26Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23Membuat SOPOverdue0/12wPlan: Jun 26–Jun 26Permintaan Customer VisitOverdue0/13wPlan: Jun 18–Jun 19Membuat Form FAT, ATP, SATOverdue0/11wPlan: Jun 26–Jun 29Membuat Form FAT, Onsite, SATOverdue0/12wPlan: Jun 23–Jun 23Membuat MOP/WIOverdue0/13wPlan: Jun 19–Jun 19Melakukan Design ReviewOverdue0/12wPlan: Jun 23–Jun 24Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19Membuat Materi TrainingOverdue0/11wPlan: Jun 29–Jun 29Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24Permintaan Customer VisitOverdue0/11wPlan: Jun 29–Jun 29Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24----3w
ENGINEERING OPRASIONAL 2022Product OnlyDeadline: Jun 9, 20220/21 aktivitas selesaiAproval DrawOverdue0/749moPlan: Jun 17–Jun 17BOQOverdue0/749moPlan: Jun 15–Jun 15GAOverdue1/750moPlan: Jun 10–Jun 10Actual: Jun 13FEPOverdue0/749moPlan: Jun 15–Jun 15TD PKBOverdue0/749moPlan: Jun 15–Jun 16PROGRAMOverdue0/749moPlan: Jun 15–Jun 15SchematicsOverdue0/650moPlan: Jun 10–Jun 10TD WeldOverdue0/749moPlan: Jun 16–Jun 16BOQ LIst Elec_LVOverdue2/850moPlan: Jun 9–Jun 10Actual: Jun 13TD AssyOverdue0/749moPlan: Jun 16–Jun 16WiringList x TubingOverdue0/650moPlan: Jun 13–Jun 133D BusbarOverdue0/749moPlan: Jun 16–Jun 17Bom List ElectricalOverdue0/650moPlan: Jun 10–Jun 13CUT OUTOverdue0/650moPlan: Jun 13–Jun 133D AssyOverdue0/749moPlan: Jun 17–Jun 17Preare DOc Operation (ATP,MOP,EOP;etc)Overdue1/750moPlan: Jun 14–Jun 14Actual: Jun 13Design ReviewOverdue1/750moPlan: Jun 13–Jun 14Actual: Jun 13OthersOverdue1/750moPlan: Jun 14–Jun 14Actual: Jun 13TD VLispOverdue0/749moPlan: Jun 14–Jun 15OthersOverdue0/749moPlan: Jun 16–Jun 16(aktivitas)Overdue0/749moPlan: Jun 17–Jun 17-------50mo
Siemens - UCC BP TangguhProduct + InstalasiDeadline: May 29, 20263/24 aktivitas selesaiMembuat Approval Drawing GADone1/11moPlan: Feb 17–Feb 18Actual: Apr 3Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Feb 25–Feb 26Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 20–Feb 23Membuat BomlistOverdue0/15moPlan: Feb 23–Feb 23Membuat BomlistDone1/12moPlan: Feb 18–Feb 18Actual: Apr 8Membuat Timeline instalasiOverdue0/14moPlan: Feb 26–Feb 26Membuat BomlistOverdue0/14moPlan: Feb 26–Feb 27Membuat SchematicOverdue0/15moPlan: Feb 23–Feb 23Technical DrawingDone1/13wPlan: Feb 18–Feb 19Actual: Mar 9Melakukan Design ReviewOverdue0/15moPlan: Feb 19–Feb 19Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Feb 23–Feb 24Membuat MOP/WIOverdue0/14moPlan: Feb 27–Feb 27Membuat MOP/WIOverdue0/14moPlan: Feb 24–Feb 24Membuat SOPOverdue0/14moPlan: Feb 27–Feb 27Permintaan Customer VisitOverdue0/15moPlan: Feb 19–Feb 20Membuat Form FAT, ATP, SATOverdue0/14moPlan: Feb 27–Mar 2Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Feb 24–Feb 24Membuat MOP/WIOverdue0/15moPlan: Feb 20–Feb 20Melakukan Design ReviewOverdue0/14moPlan: Feb 24–Feb 25Membuat Materi TrainingOverdue0/15moPlan: Feb 20–Feb 20Membuat Materi TrainingOverdue0/14moPlan: Mar 2–Mar 2Membuat Materi TrainingOverdue0/14moPlan: Feb 25–Feb 25Permintaan Customer VisitOverdue0/14moPlan: Mar 2–Mar 2Permintaan Customer VisitOverdue0/14moPlan: Feb 25–Feb 25----5mo
Hitachi - ACP25035 - GI Satui 150kVProduct + InstalasiDeadline: Jun 19, 20267/28 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Dec 23–Dec 24Actual: Nov 18Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Dec 31–Dec 31Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Dec 26–Dec 29Actual: Nov 17Membuat BomlistDone1/1Plan: Dec 24–Dec 24Actual: Dec 3Membuat BomlistDone1/1Plan: Dec 29–Dec 29Actual: Dec 4Membuat Timeline instalasiOverdue0/16moPlan: Dec 31–Jan 1Membuat BomlistOverdue0/16moPlan: Jan 1–Jan 1Membuat SchematicDone1/1Plan: Dec 29–Dec 30Actual: Dec 11Technical DrawingDone1/1Plan: Dec 25–Dec 25Actual: Dec 3Vlisp Technical Drawing Overdue0/17moPlan: Nov 26–Nov 26Melakukan Design ReviewOverdue0/17moPlan: Dec 25–Dec 25Membuat Dxf Cutout / nameplateDone1/1Plan: Dec 30–Dec 30Actual: Nov 17Membuat MOP/WIOverdue0/16moPlan: Jan 1–Jan 2TD BusbarOverdue0/17moPlan: Nov 26–Nov 273D design Overdue0/17moPlan: Nov 27–Nov 27Membuat MOP/WIOverdue0/16moPlan: Dec 30–Dec 30Membuat SOPOverdue0/16moPlan: Jan 2–Jan 2Permintaan Customer VisitOverdue0/26moPlan: Dec 26–Dec 26Membuat Form FAT, ATP, SATOverdue0/16moPlan: Jan 2–Jan 5Membuat Form FAT, Onsite, SATOverdue0/16moPlan: Dec 30–Dec 30Membuat MOP/WIOverdue0/16moPlan: Dec 26–Dec 26Melakukan Design ReviewOverdue0/26moPlan: Dec 30–Dec 31Membuat Materi TrainingOverdue0/16moPlan: Dec 26–Dec 26Membuat Materi TrainingOverdue0/16moPlan: Jan 5–Jan 5TD BusbarOverdue0/17moPlan: Nov 27–Nov 27Membuat Materi TrainingOverdue0/16moPlan: Dec 31–Dec 31Permintaan Customer VisitOverdue0/16moPlan: Jan 5–Jan 5Permintaan Customer VisitOverdue0/26moPlan: Dec 31–Dec 317mo
Hitachi - ACP25026 - BalonganProduct + InstalasiDeadline: Jul 20, 20267/28 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Nov 17–Nov 18Actual: Oct 23Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 25–Nov 25Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Nov 20–Nov 21Actual: Oct 15Membuat BomlistDone1/12moPlan: Nov 18–Nov 18Actual: Jan 20Membuat BomlistDone1/1Plan: Nov 21–Nov 21Actual: Oct 15Membuat Timeline instalasiOverdue0/17moPlan: Nov 25–Nov 26Membuat BomlistOverdue0/17moPlan: Nov 26–Nov 26Membuat SchematicDone1/12moPlan: Nov 21–Nov 24Actual: Jan 19Technical DrawingDone1/12moPlan: Nov 19–Nov 19Actual: Jan 20Vlisp Technical Drawing Overdue0/19moPlan: Oct 21–Oct 21Melakukan Design ReviewOverdue0/18moPlan: Nov 19–Nov 19Membuat Dxf Cutout / nameplateDone1/1Plan: Nov 24–Nov 24Actual: Oct 15Membuat MOP/WIOverdue0/17moPlan: Nov 26–Nov 27TD BusbarOverdue0/19moPlan: Oct 21–Oct 223D design Overdue0/19moPlan: Oct 22–Oct 22Membuat MOP/WIOverdue0/38moPlan: Nov 24–Nov 24Membuat SOPOverdue0/27moPlan: Nov 27–Nov 27Permintaan Customer VisitOverdue0/18moPlan: Nov 20–Nov 20Membuat Form FAT, ATP, SATOverdue0/27moPlan: Nov 27–Nov 28Membuat Form FAT, Onsite, SATOverdue0/28moPlan: Nov 24–Nov 24Membuat MOP/WIOverdue0/18moPlan: Nov 20–Nov 20Melakukan Design ReviewOverdue0/18moPlan: Nov 24–Nov 25Membuat Materi TrainingOverdue0/28moPlan: Nov 20–Nov 20Membuat Materi TrainingOverdue0/17moPlan: Nov 28–Nov 28TD BusbarOverdue0/19moPlan: Oct 22–Oct 23Membuat Materi TrainingOverdue0/18moPlan: Nov 25–Nov 25Permintaan Customer VisitOverdue0/27moPlan: Nov 28–Nov 28Permintaan Customer VisitOverdue0/18moPlan: Nov 25–Nov 259mo
Ekamas Mora Republik - Open Rack 42U & Rack DCPDU 3U_PO# 174372Product + InstalasiDeadline: Aug 7, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/12wPlan: Jun 25–Jun 26Membuat Approval Drawing GA-SLDOverdue0/12dPlan: Jul 3–Jul 6Membuat Approval Drawing GA-SLD/cutoutOverdue0/11wPlan: Jun 30–Jul 1Membuat BomlistOverdue0/12wPlan: Jun 26–Jun 26Membuat BomlistOverdue0/11wPlan: Jul 1–Jul 1Membuat Timeline instalasiOverdue0/12dPlan: Jul 6–Jul 6Membuat BomlistOverdue0/11dPlan: Jul 6–Jul 7Membuat SchematicOverdue0/11wPlan: Jul 1–Jul 1Technical DrawingOverdue0/11wPlan: Jun 26–Jun 29Melakukan Design ReviewOverdue0/11wPlan: Jun 29–Jun 29Membuat Dxf Cutout / nameplateOverdue0/16dPlan: Jul 1–Jul 2Membuat MOP/WIOverdue0/11dPlan: Jul 7–Jul 7Membuat MOP/WIOverdue0/16dPlan: Jul 2–Jul 2Membuat SOPOverdue0/11dPlan: Jul 7–Jul 7Permintaan Customer VisitOverdue0/11wPlan: Jun 29–Jun 30Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 7–Jul 8Membuat Form FAT, Onsite, SATOverdue0/16dPlan: Jul 2–Jul 2Membuat MOP/WIOverdue0/11wPlan: Jun 30–Jun 30Melakukan Design ReviewOverdue0/15dPlan: Jul 2–Jul 3Membuat Materi TrainingOverdue0/11wPlan: Jun 30–Jun 30Membuat Materi TrainingOn Progress0/1Plan: Jul 8–Jul 8Membuat Materi TrainingOverdue0/15dPlan: Jul 3–Jul 3Permintaan Customer VisitOn Progress0/1Plan: Jul 8–Jul 8Permintaan Customer VisitOverdue0/15dPlan: Jul 3–Jul 3----2w
Internal - MDCC 20 Feet POD Phase 2/IP65Product + InstalasiDeadline: Jun 30, 20264/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/17moPlan: Dec 23–Dec 23Membuat Approval Drawing GA-SLDOverdue0/13moPlan: Apr 3–Apr 3Membuat Approval Drawing GA-SLD/cutoutOverdue0/13moPlan: Mar 31–Mar 31Membuat BomlistDone1/1Plan: Nov 11–Nov 11Actual: Nov 11Membuat BomlistDone1/1Plan: Apr 1–Apr 1Actual: Mar 9Membuat Timeline instalasiOverdue0/13moPlan: Apr 3–Apr 6Membuat BomlistOverdue0/13moPlan: Apr 6–Apr 6Membuat SchematicDone1/1Plan: Apr 1–Apr 1Actual: Mar 9Technical DrawingOverdue0/28moPlan: Nov 11–Nov 11Melakukan Design ReviewDone1/1Plan: Mar 30–Mar 30Actual: Mar 2Membuat Dxf Cutout / nameplateOverdue0/13moPlan: Apr 1–Apr 1Membuat MOP/WIOverdue0/13moPlan: Apr 6–Apr 7Membuat MOP/WIOverdue0/13moPlan: Apr 1–Apr 2Membuat SOPOverdue0/13moPlan: Apr 7–Apr 7Permintaan Customer VisitOverdue0/23moPlan: Mar 30–Mar 30Membuat Form FAT, ATP, SATOverdue0/13moPlan: Apr 7–Apr 7Membuat Form FAT, Onsite, SATOverdue0/13moPlan: Apr 2–Apr 2Membuat MOP/WIOverdue0/13moPlan: Mar 30–Mar 31Melakukan Design ReviewOverdue1/33moPlan: Apr 2–Apr 3Actual: Mar 2Membuat Materi TrainingOverdue0/13moPlan: Mar 31–Mar 31Membuat Materi TrainingOverdue0/13moPlan: Apr 7–Apr 8Membuat Materi TrainingOverdue0/13moPlan: Apr 2–Apr 3Permintaan Customer VisitOverdue0/13moPlan: Apr 8–Apr 8Permintaan Customer VisitOverdue0/13moPlan: Apr 3–Apr 3----8mo
Wholesale - Panel DB - Dermaga BiakProduct + InstalasiDeadline: Jun 30, 20264/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/11moPlan: May 22–May 25Membuat Approval Drawing GA-SLDOverdue0/11moPlan: Jun 1–Jun 2Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: May 27–May 28Actual: May 13Membuat BomlistOverdue0/11moPlan: May 25–May 25Membuat BomlistDone1/11moPlan: May 28–May 28Actual: Jul 2Membuat Timeline instalasiOverdue0/11moPlan: Jun 2–Jun 2Membuat BomlistOverdue0/11moPlan: Jun 2–Jun 3Membuat SchematicDone1/11moPlan: May 28–May 28Actual: Jul 2Technical DrawingOverdue0/11moPlan: May 25–May 26Melakukan Design ReviewOverdue0/11moPlan: May 26–May 26Membuat Dxf Cutout / nameplateOverdue0/11moPlan: May 28–May 29Membuat MOP/WIOverdue0/11moPlan: Jun 3–Jun 3Membuat MOP/WIOverdue0/11moPlan: May 29–May 29Membuat SOPOverdue0/11moPlan: Jun 3–Jun 3Permintaan Customer VisitOverdue0/11moPlan: May 26–May 27Membuat Form FAT, ATP, SATOverdue0/11moPlan: Jun 3–Jun 4Membuat Form FAT, Onsite, SATDone1/11moPlan: May 29–May 29Actual: Jul 7Membuat MOP/WIOverdue0/11moPlan: May 27–May 27Melakukan Design ReviewOverdue0/11moPlan: May 29–Jun 1Membuat Materi TrainingOverdue0/11moPlan: May 27–May 27Membuat Materi TrainingOverdue0/11moPlan: Jun 4–Jun 4Membuat Materi TrainingOverdue0/11moPlan: Jun 1–Jun 1Permintaan Customer VisitOverdue0/11moPlan: Jun 4–Jun 4Permintaan Customer VisitOverdue0/11moPlan: Jun 1–Jun 1----1mo
PT. NexWave_Panel TXDP & SDP AC_PO25090188Product + InstalasiDeadline: Jul 3, 20264/24 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Mar 30–Mar 31Actual: Mar 31Membuat Approval Drawing GA-SLDOverdue0/13moPlan: Apr 3–Apr 3Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Mar 31–Apr 1Actual: Mar 31Membuat BomlistDone1/1Plan: Apr 1–Apr 1Actual: Apr 1Membuat BomlistDone1/1Plan: Apr 1–Apr 1Actual: Apr 1Membuat Timeline instalasiOverdue0/13moPlan: Apr 3–Apr 6Membuat BomlistOverdue0/23moPlan: Apr 6–Apr 6Membuat SchematicOverdue0/23moPlan: Apr 1–Apr 1Technical DrawingOverdue0/13moPlan: Apr 1–Apr 1Melakukan Design ReviewOverdue1/63moPlan: Apr 1–Apr 9Actual: Apr 9Membuat Dxf Cutout / nameplateOverdue0/13moPlan: Apr 1–Apr 1Membuat MOP/WIOverdue0/13moPlan: Apr 6–Apr 7Membuat MOP/WIOverdue0/13moPlan: Apr 1–Apr 2Membuat SOPOverdue0/23moPlan: Apr 7–Apr 7Permintaan Customer VisitOverdue0/13moPlan: Apr 9–Apr 9Membuat Form FAT, ATP, SATOverdue0/13moPlan: Apr 7–Apr 7Membuat Form FAT, Onsite, SATOverdue0/23moPlan: Apr 2–Apr 2Membuat MOP/WIOverdue0/13moPlan: Apr 9–Apr 10Melakukan Design ReviewOverdue0/13moPlan: Apr 2–Apr 2Membuat Materi TrainingOverdue0/13moPlan: Apr 7–Apr 8Membuat Materi TrainingOverdue0/13moPlan: Apr 10–Apr 10Membuat Materi TrainingOverdue0/13moPlan: Apr 2–Apr 3Permintaan Customer VisitOverdue0/23moPlan: Apr 8–Apr 8Permintaan Customer VisitOverdue0/63moPlan: Apr 3–Apr 3----3mo
Inti Bumi Mas - Panel FeederProduct + InstalasiDeadline: Jul 22, 20264/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/14moPlan: Mar 4–Mar 4Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Mar 13–Mar 16Membuat Approval Drawing GA-SLD/cutoutOverdue0/14moPlan: Mar 4–Mar 4Membuat BomlistDone1/11moPlan: Mar 6–Mar 6Actual: Apr 7Membuat BomlistDone1/12wPlan: Mar 11–Mar 11Actual: Mar 27Membuat Timeline instalasiOverdue0/14moPlan: Mar 16–Mar 16Membuat BomlistOverdue0/14moPlan: Mar 16–Mar 17Membuat SchematicDone1/1Plan: Mar 11–Mar 11Actual: Mar 27Technical DrawingDone1/14wPlan: Mar 6–Mar 9Actual: Apr 7Melakukan Design ReviewOverdue0/14moPlan: Mar 9–Mar 9Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Mar 11–Mar 12Membuat MOP/WIOverdue0/14moPlan: Mar 17–Mar 17Membuat MOP/WIOverdue0/14moPlan: Mar 12–Mar 12Membuat SOPOverdue0/14moPlan: Mar 17–Mar 17Permintaan Customer VisitOverdue0/14moPlan: Mar 9–Mar 10Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 17–Mar 18Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Mar 12–Mar 12Membuat MOP/WIOverdue0/14moPlan: Mar 10–Mar 10Melakukan Design ReviewOverdue0/14moPlan: Mar 12–Mar 13Membuat Materi TrainingOverdue0/14moPlan: Mar 10–Mar 10Membuat Materi TrainingOverdue0/14moPlan: Mar 18–Mar 18Membuat Materi TrainingOverdue0/14moPlan: Mar 13–Mar 13Permintaan Customer VisitOverdue0/14moPlan: Mar 18–Mar 18Permintaan Customer VisitOverdue0/14moPlan: Mar 13–Mar 13----4mo
PROGRAM CNC, LASER & LVDProduct OnlyDeadline: Sep 7, 20220/19 aktivitas selesaiAproval DrawOverdue0/3846moPlan: Sep 7–Sep 15BOQOverdue0/3846moPlan: Sep 8–Sep 14GAOverdue0/147moPlan: Sep 8–Sep 8FEPOverdue0/3846moPlan: Sep 8–Sep 13SLDOverdue0/147moPlan: Sep 7–Sep 8TD PKBOverdue0/3846moPlan: Sep 8–Sep 14PROGRAMOverdue1/3846moPlan: Sep 8–Sep 13Actual: Sep 20SchematicsOverdue0/147moPlan: Sep 8–Sep 9TD WeldOverdue0/3846moPlan: Sep 9–Sep 14BOQ LIst Elec_LVOverdue0/147moPlan: Sep 9–Sep 9TD AssyOverdue0/3846moPlan: Sep 9–Sep 143D BusbarOverdue0/3846moPlan: Sep 9–Sep 15Bom List ElectricalOverdue0/147moPlan: Sep 12–Sep 123D AssyOverdue0/3846moPlan: Sep 12–Sep 15Preare DOc Operation (ATP,MOP,EOP;etc)Overdue0/147moPlan: Sep 9–Sep 12Design ReviewOverdue0/147moPlan: Sep 12–Sep 12TD VLispOverdue0/3846moPlan: Sep 7–Sep 13OthersOverdue0/3846moPlan: Sep 9–Sep 15(aktivitas)Overdue0/147moPlan: Sep 12–Sep 12---------47mo
GSPE_Smart Rack (Micro Data Center)Product + InstalasiDeadline: Apr 6, 20265/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/28moPlan: Nov 24–Nov 24Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Jan 20–Jan 20Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jan 17–Jan 18Actual: Dec 11Membuat BomlistDone1/1Plan: Jan 13–Jan 13Actual: Sep 22Membuat BomlistDone1/1Plan: Jan 18–Jan 18Actual: Dec 11Membuat Timeline instalasiOverdue0/26moPlan: Jan 20–Jan 21Membuat BomlistOverdue0/16moPlan: Jan 21–Jan 21Membuat SchematicDone1/1Plan: Jan 18–Jan 18Actual: Dec 11Technical DrawingOverdue0/16moPlan: Jan 13–Jan 13Melakukan Design ReviewDone1/13wPlan: Jan 14–Jan 14Actual: Feb 4Membuat Dxf Cutout / nameplateOverdue0/16moPlan: Jan 18–Jan 18Membuat MOP/WIOverdue0/16moPlan: Jan 21–Jan 24Membuat MOP/WIOverdue0/16moPlan: Jan 18–Jan 19Membuat SOPOverdue0/16moPlan: Jan 24–Jan 24Permintaan Customer VisitOverdue0/16moPlan: Jan 14–Jan 14Membuat Form FAT, ATP, SATOverdue0/16moPlan: Jan 24–Jan 24Membuat Form FAT, Onsite, SATOverdue0/16moPlan: Jan 19–Jan 19Membuat MOP/WIOverdue0/16moPlan: Jan 14–Jan 17Melakukan Design ReviewOverdue0/16moPlan: Jan 19–Jan 19Membuat Materi TrainingOverdue0/16moPlan: Jan 17–Jan 17Membuat Materi TrainingOverdue0/15moPlan: Jan 24–Jan 25Membuat Materi TrainingOverdue0/16moPlan: Jan 19–Jan 20Permintaan Customer VisitOverdue0/15moPlan: Jan 25–Jan 25Permintaan Customer VisitOverdue0/16moPlan: Jan 20–Jan 20----8mo
Mega Akses - Omadata SurabayaProduct + InstalasiDeadline: Jul 31, 20265/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/12moPlan: May 4–May 4Membuat Approval Drawing GA-SLDDone1/1Plan: May 12–May 13Actual: Apr 23Membuat Approval Drawing GA-SLD/cutoutOverdue0/12moPlan: May 7–May 7Membuat BomlistOverdue0/12moPlan: May 4–May 5Membuat BomlistOverdue0/12moPlan: May 7–May 8Membuat Timeline instalasiDone1/1Plan: May 13–May 13Actual: Apr 23Membuat BomlistDone1/1Plan: May 13–May 14Actual: Apr 23Membuat SchematicOverdue0/12moPlan: May 8–May 8Technical DrawingOverdue0/12moPlan: May 5–May 5Melakukan Design ReviewOverdue0/12moPlan: May 5–May 6Membuat Dxf Cutout / nameplateOverdue0/12moPlan: May 8–May 8Membuat MOP/WIDone1/1Plan: May 14–May 14Actual: Apr 23Membuat MOP/WIOverdue0/12moPlan: May 8–May 11Membuat SOPDone1/1Plan: May 14–May 14Actual: Apr 23Permintaan Customer VisitOverdue0/12moPlan: May 6–May 6Membuat Form FAT, ATP, SATOverdue0/12moPlan: May 14–May 14Membuat Form FAT, Onsite, SATOverdue0/12moPlan: May 11–May 11Membuat MOP/WIOverdue0/12moPlan: May 6–May 7Melakukan Design ReviewOverdue0/12moPlan: May 11–May 11Membuat Materi TrainingOverdue0/12moPlan: May 7–May 7Membuat Materi TrainingOverdue0/12moPlan: May 14–May 15Membuat Materi TrainingOverdue0/12moPlan: May 11–May 12Permintaan Customer VisitOverdue0/12moPlan: May 15–May 15Permintaan Customer VisitOverdue0/12moPlan: May 12–May 12----2mo
Mega Akses Persada - BDF Power Papahan KaranganyarProduct + InstalasiDeadline: Aug 28, 20265/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/46dPlan: Jul 2–Jul 2Membuat Approval Drawing GA-SLDDone1/1Plan: Jun 27–Jun 30Actual: Jun 24Membuat Approval Drawing GA-SLD/cutoutOverdue0/12wPlan: Jun 25–Jun 26Membuat BomlistOverdue0/12wPlan: Jun 25–Jun 25Membuat BomlistOverdue0/35dPlan: Jul 2–Jul 3Membuat Timeline instalasiDone1/1Plan: Jun 30–Jun 30Actual: Jun 24Membuat BomlistDone1/1Plan: Jun 30–Jul 1Actual: Jun 24Membuat SchematicOverdue0/12wPlan: Jun 25–Jun 25Technical DrawingOverdue0/15dPlan: Jul 3–Jul 3Melakukan Design ReviewOverdue0/12dPlan: Jul 3–Jul 6Membuat Dxf Cutout / nameplateOverdue0/12wPlan: Jun 25–Jun 25Membuat MOP/WIDone1/1Plan: Jul 1–Jul 1Actual: Jun 24Membuat MOP/WIOverdue0/12wPlan: Jun 26–Jun 26Membuat SOPDone1/1Plan: Jul 1–Jul 1Actual: Jun 24Permintaan Customer VisitOverdue0/12dPlan: Jul 6–Jul 6Membuat Form FAT, ATP, SATOverdue0/16dPlan: Jul 1–Jul 2Membuat Form FAT, Onsite, SATOverdue0/12wPlan: Jun 26–Jun 26Membuat MOP/WIOverdue0/21dPlan: Jul 6–Jul 7Melakukan Design ReviewOverdue0/12wPlan: Jun 26–Jun 26Membuat Materi TrainingOverdue0/16dPlan: Jul 2–Jul 2Membuat Materi TrainingOverdue0/21dPlan: Jul 7–Jul 7Membuat Materi TrainingOverdue0/22wPlan: Jun 26–Jun 27Permintaan Customer VisitOverdue0/16dPlan: Jul 2–Jul 2Permintaan Customer VisitOverdue0/12wPlan: Jun 27–Jun 27----2w
INQUIRY ESTIMATORProduct OnlyDeadline: Oct 12, 20220/18 aktivitas selesaiDraft Cutout ViewOverdue0/145moPlan: Oct 31–Nov 1Approval CutoutOverdue0/145moPlan: Nov 1–Nov 2Aproval DrawOverdue0/145moPlan: Oct 12–Oct 13BOQOverdue0/145moPlan: Oct 13–Oct 14BOM HVOverdue0/145moPlan: Nov 2–Nov 3FEPOverdue0/145moPlan: Oct 13–Oct 13TD PKBOverdue0/145moPlan: Oct 14–Oct 14Cutout listOverdue0/145moPlan: Nov 4–Nov 7PROGRAMOverdue0/145moPlan: Oct 13–Oct 13TD WeldOverdue0/145moPlan: Oct 14–Oct 14Wiring ListOverdue0/145moPlan: Nov 3–Nov 3Printout SchematicOverdue0/145moPlan: Nov 7–Nov 7TD AssyOverdue0/145moPlan: Oct 14–Oct 14Tubing ListOverdue0/145moPlan: Nov 3–Nov 43D BusbarOverdue0/145moPlan: Oct 17–Oct 173D AssyOverdue0/145moPlan: Oct 17–Oct 17TD VLispOverdue0/145moPlan: Oct 17–Oct 17OthersOverdue0/145moPlan: Oct 14–Oct 17----------45mo
Internal - Contaiment 50 UnitProduct + InstalasiDeadline: Jun 30, 20264/22 aktivitas selesaiMembuat Approval Drawing GA-SLDOverdue0/27moPlan: Dec 1–Dec 1Membuat BomlistDone1/1Plan: Nov 11–Dec 30Actual: Dec 30Membuat BomlistDone1/1Plan: Jan 5–Jan 5Actual: Jan 5Membuat Timeline instalasiOverdue0/17moPlan: Dec 1–Dec 2Membuat BomlistOverdue0/17moPlan: Dec 2–Dec 2Membuat SchematicDone1/1Plan: Dec 30–Jan 5Actual: Jan 5Technical DrawingOverdue0/18moPlan: Nov 24–Nov 24Melakukan Design ReviewDone1/1Plan: Dec 29–Dec 29Actual: Dec 29Membuat Dxf Cutout / nameplateOverdue0/17moPlan: Nov 27–Nov 27Membuat MOP/WIOverdue0/17moPlan: Dec 2–Dec 3Membuat MOP/WIOverdue0/17moPlan: Nov 27–Nov 28Membuat SOPOverdue0/17moPlan: Dec 3–Dec 3Permintaan Customer VisitOverdue0/68moPlan: Nov 25–Nov 25Membuat Form FAT, ATP, SATOverdue0/17moPlan: Dec 3–Dec 3Membuat Form FAT, Onsite, SATOverdue0/17moPlan: Nov 28–Nov 28Membuat MOP/WIOverdue0/17moPlan: Nov 25–Nov 26Melakukan Design ReviewOverdue0/17moPlan: Nov 28–Nov 28Membuat Materi TrainingOverdue0/27moPlan: Nov 26–Nov 26Membuat Materi TrainingOverdue0/27moPlan: Dec 3–Dec 4Membuat Materi TrainingOverdue0/17moPlan: Nov 28–Dec 1Permintaan Customer VisitOverdue0/17moPlan: Dec 4–Dec 4Permintaan Customer VisitOverdue0/17moPlan: Dec 1–Dec 1------8mo
Hitachi - GI 150kV kruengProduct + InstalasiDeadline: Jul 22, 20267/24 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Jun 11–Jun 12Actual: Jun 10Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 16–Jun 17Actual: Jun 10Membuat BomlistDone1/1Plan: Jun 12–Jun 12Actual: Jun 12Membuat BomlistDone1/1Plan: Jun 17–Jun 17Actual: Jun 10Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23Membuat SchematicDone1/1Plan: Jun 17–Jun 17Actual: Jun 15Technical DrawingDone1/1Plan: Jun 12–Jun 15Actual: Jun 12Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15Membuat Dxf Cutout / nameplateDone1/1Plan: Jun 17–Jun 18Actual: Jun 15Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19----3w
Hitachi - ACP25099 - GI 150kV TakengonProduct + InstalasiDeadline: Jul 31, 20267/24 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Jun 11–Jun 12Actual: Jun 10Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 16–Jun 17Actual: Jun 10Membuat BomlistDone1/1Plan: Jun 12–Jun 12Actual: Jun 12Membuat BomlistDone1/1Plan: Jun 17–Jun 17Actual: Jun 12Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23Membuat SchematicDone1/1Plan: Jun 17–Jun 17Actual: Jun 15Technical DrawingDone1/1Plan: Jun 12–Jun 15Actual: Jun 12Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15Membuat Dxf Cutout / nameplateDone1/1Plan: Jun 17–Jun 18Actual: Jun 15Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19----3w
Hitachi - GI 150kV SribawonoProduct + InstalasiDeadline: Aug 25, 20267/24 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Jun 11–Jun 12Actual: Jun 10Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 16–Jun 17Actual: Jun 10Membuat BomlistDone1/1Plan: Jun 12–Jun 12Actual: Jun 12Membuat BomlistDone1/11dPlan: Jun 17–Jun 17Actual: Jun 18Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23Membuat SchematicDone1/11dPlan: Jun 17–Jun 17Actual: Jun 18Technical DrawingDone1/1Plan: Jun 12–Jun 15Actual: Jun 12Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15Membuat Dxf Cutout / nameplateDone1/1Plan: Jun 17–Jun 18Actual: Jun 18Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19----3w
Hitachi - GI 150kV KolakaProduct + InstalasiDeadline: Aug 28, 20267/24 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Jun 11–Jun 12Actual: Jun 10Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 16–Jun 17Actual: Jun 10Membuat BomlistDone1/13wPlan: Jun 12–Jun 12Actual: Jul 3Membuat BomlistDone1/11dPlan: Jun 17–Jun 17Actual: Jun 18Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23Membuat SchematicDone1/11dPlan: Jun 17–Jun 17Actual: Jun 18Technical DrawingDone1/13wPlan: Jun 12–Jun 15Actual: Jul 3Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15Membuat Dxf Cutout / nameplateDone1/1Plan: Jun 17–Jun 18Actual: Jun 18Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19----3w
Schneider - Panel for PUSRI IIIB Project // E2010-96440Product + InstalasiDeadline: May 26, 202612/28 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Nov 9–Nov 10Actual: Sep 10Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 17–Nov 17Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Nov 14–Nov 15Actual: Sep 10Membuat BomlistDone1/1Plan: Nov 10–Nov 10Actual: Sep 17Membuat BomlistDone1/1Plan: Nov 15–Nov 15Actual: Sep 19Membuat Timeline instalasiOverdue0/18moPlan: Nov 17–Nov 20Membuat BomlistOverdue0/18moPlan: Nov 20–Nov 20Membuat SchematicDone1/1Plan: Nov 15–Nov 16Actual: Oct 10Technical DrawingDone1/1Plan: Nov 13–Nov 13Actual: Sep 17Vlisp Technical Drawing Done1/1Plan: Oct 10–Oct 10Actual: Sep 17Melakukan Design ReviewDone1/1Plan: Nov 14–Nov 14Actual: Sep 22Membuat Dxf Cutout / nameplateDone1/1Plan: Nov 16–Nov 16Actual: Sep 11Membuat MOP/WIOverdue0/18moPlan: Nov 20–Nov 21TD BusbarDone1/1Plan: Oct 10–Oct 13Actual: Sep 173D design Done1/1Plan: Oct 13–Oct 13Actual: Sep 17Membuat MOP/WIOverdue0/18moPlan: Nov 16–Nov 16Membuat SOPOverdue0/18moPlan: Nov 21–Nov 21Permintaan Customer VisitOverdue0/18moPlan: Nov 14–Nov 14Membuat Form FAT, ATP, SATOverdue0/18moPlan: Nov 21–Nov 22Membuat Form FAT, Onsite, SATOverdue0/18moPlan: Nov 16–Nov 16Membuat MOP/WIOverdue0/18moPlan: Nov 14–Nov 14Melakukan Design ReviewOverdue0/18moPlan: Nov 16–Nov 17Membuat Materi TrainingOverdue0/18moPlan: Nov 14–Nov 14Membuat Materi TrainingOverdue0/18moPlan: Nov 22–Nov 22TD BusbarDone1/1Plan: Oct 13–Oct 14Actual: Sep 17Membuat Materi TrainingOverdue0/28moPlan: Nov 17–Nov 17Permintaan Customer VisitOverdue0/18moPlan: Nov 22–Nov 22Permintaan Customer VisitOverdue0/18moPlan: Nov 17–Nov 178mo
Kelinci Mas Unggul - Panel MK Single PhiProduct + InstalasiDeadline: Jun 10, 20268/24 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Apr 30–May 1Actual: Mar 2Membuat Approval Drawing GA-SLDOverdue0/12moPlan: May 8–May 11Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: May 5–May 6Actual: Mar 2Membuat BomlistDone1/1Plan: May 1–May 1Actual: Mar 4Membuat BomlistDone1/1Plan: May 6–May 6Actual: Mar 10Membuat Timeline instalasiOverdue0/12moPlan: May 11–May 11Membuat BomlistOverdue0/12moPlan: May 11–May 12Membuat SchematicDone1/1Plan: May 6–May 6Actual: Mar 9Technical DrawingDone1/1Plan: May 1–May 4Actual: Mar 4Melakukan Design ReviewDone1/1Plan: May 4–May 4Actual: Mar 2Membuat Dxf Cutout / nameplateDone1/1Plan: May 6–May 7Actual: Mar 10Membuat MOP/WIOverdue0/12moPlan: May 12–May 12Membuat MOP/WIOverdue0/12moPlan: May 7–May 7Membuat SOPOverdue0/12moPlan: May 12–May 12Permintaan Customer VisitOverdue0/12moPlan: May 4–May 5Membuat Form FAT, ATP, SATOverdue0/12moPlan: May 12–May 13Membuat Form FAT, Onsite, SATOverdue0/12moPlan: May 7–May 7Membuat MOP/WIOverdue0/12moPlan: May 5–May 5Melakukan Design ReviewOverdue0/12moPlan: May 7–May 8Membuat Materi TrainingOverdue0/12moPlan: May 5–May 5Membuat Materi TrainingOverdue0/12moPlan: May 13–May 13Membuat Materi TrainingOverdue0/12moPlan: May 8–May 8Permintaan Customer VisitOverdue0/12moPlan: May 13–May 13Permintaan Customer VisitOverdue0/12moPlan: May 8–May 8----2mo
Hitachi - ACP25085 - Sebuku PLN NPCProduct + InstalasiDeadline: Jul 6, 20268/24 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: May 12–May 12Actual: May 12Membuat Approval Drawing GA-SLDOverdue0/11moPlan: May 27–May 27Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: May 6–May 6Actual: May 6Membuat BomlistDone1/1Plan: May 18–May 18Actual: May 15Membuat BomlistDone1/14dPlan: May 18–May 18Actual: May 22Membuat Timeline instalasiOverdue0/11moPlan: May 27–May 28Membuat BomlistOverdue0/31moPlan: May 28–May 28Membuat SchematicDone1/15dPlan: May 20–May 20Actual: May 25Technical DrawingDone1/1Plan: May 18–May 18Actual: May 15Melakukan Design ReviewDone1/1Plan: May 18–May 18Actual: May 12Membuat Dxf Cutout / nameplateDone1/1Plan: May 18–May 18Actual: May 6Membuat MOP/WIOverdue0/11moPlan: May 28–May 29Membuat MOP/WIOverdue0/11moPlan: May 25–May 26Membuat SOPOverdue0/11moPlan: May 29–May 29Permintaan Customer VisitOverdue0/12moPlan: May 21–May 21Membuat Form FAT, ATP, SATOverdue0/11moPlan: May 29–May 29Membuat Form FAT, Onsite, SATOverdue0/11moPlan: May 26–May 26Membuat MOP/WIOverdue0/12moPlan: May 21–May 22Melakukan Design ReviewOverdue0/11moPlan: May 26–May 26Membuat Materi TrainingOverdue0/12moPlan: May 22–May 22Membuat Materi TrainingOverdue0/11moPlan: May 29–Jun 1Membuat Materi TrainingOverdue0/11moPlan: May 26–May 27Permintaan Customer VisitOverdue0/21moPlan: Jun 1–Jun 1Permintaan Customer VisitOverdue0/11moPlan: May 27–May 27----2mo
PT. LTI_PO 26060314_ODC With Aircond 300W (1 Unit)Product + InstalasiDeadline: Jul 22, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/11wPlan: Jun 30–Jul 1Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 8–Jul 9Membuat Approval Drawing GA-SLD/cutoutOverdue0/12dPlan: Jul 3–Jul 6Membuat BomlistOverdue0/11wPlan: Jul 1–Jul 1Membuat BomlistOverdue0/12dPlan: Jul 6–Jul 6Membuat Timeline instalasiOn Progress0/1Plan: Jul 9–Jul 9Membuat BomlistOn Progress0/1Plan: Jul 9–Jul 10Membuat SchematicOverdue0/12dPlan: Jul 6–Jul 6Technical DrawingOverdue0/16dPlan: Jul 1–Jul 2Melakukan Design ReviewOverdue0/16dPlan: Jul 2–Jul 2Membuat Dxf Cutout / nameplateOverdue0/11dPlan: Jul 6–Jul 7Membuat MOP/WIOn Progress0/1Plan: Jul 10–Jul 10Membuat MOP/WIOverdue0/11dPlan: Jul 7–Jul 7Membuat SOPOn Progress0/1Plan: Jul 10–Jul 10Permintaan Customer VisitOverdue0/15dPlan: Jul 2–Jul 3Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 10–Jul 13Membuat Form FAT, Onsite, SATOverdue0/11dPlan: Jul 7–Jul 7Membuat MOP/WIOverdue0/15dPlan: Jul 3–Jul 3Melakukan Design ReviewOn Progress0/1Plan: Jul 7–Jul 8Membuat Materi TrainingOverdue0/15dPlan: Jul 3–Jul 3Membuat Materi TrainingOn Progress0/1Plan: Jul 13–Jul 13Membuat Materi TrainingOn Progress0/1Plan: Jul 8–Jul 8Permintaan Customer VisitOn Progress0/1Plan: Jul 13–Jul 13Permintaan Customer VisitOn Progress0/1Plan: Jul 8–Jul 8----1w
PROGRAM PUNCHING, LVD, LASERProduct OnlyDeadline: Oct 11, 20220/12 aktivitas selesaiCustomer VisitOverdue0/345moPlan: Oct 24–Oct 25Aproval DrawOverdue0/1545moPlan: Oct 11–Oct 25BOQOverdue0/1545moPlan: Oct 12–Oct 26FEPOverdue0/1545moPlan: Oct 12–Oct 25TD PKBOverdue0/1545moPlan: Oct 13–Oct 26PROGRAMOverdue3/1645moPlan: Oct 12–Oct 26Actual: Oct 24TD WeldOverdue0/1545moPlan: Oct 13–Oct 26TD AssyOverdue0/1545moPlan: Oct 13–Oct 263D BusbarOverdue0/1545moPlan: Oct 14–Oct 273D AssyOverdue0/1545moPlan: Oct 14–Oct 27TD VLispOverdue0/1545moPlan: Oct 14–Oct 27OthersOverdue0/1545moPlan: Oct 13–Oct 27----------------45mo
INTERNAL_DUMMYLOAD BANK 10KVAProduct OnlyDeadline: Oct 14, 20220/12 aktivitas selesaiAproval DrawOverdue0/246moPlan: Oct 11–Oct 11BOQOverdue0/246moPlan: Oct 7–Oct 7FEPOverdue0/246moPlan: Oct 7–Oct 7TD PKBOverdue0/246moPlan: Oct 7–Oct 10PROGRAMOverdue0/246moPlan: Oct 7–Oct 7TD WeldOverdue0/246moPlan: Oct 10–Oct 10TD AssyOverdue0/246moPlan: Oct 10–Oct 103D BusbarOverdue0/246moPlan: Oct 10–Oct 113D AssyOverdue0/246moPlan: Oct 11–Oct 11TD VLispOverdue0/246moPlan: Oct 6–Oct 7OthersOverdue0/246moPlan: Oct 10–Oct 10(aktivitas)Overdue0/246moPlan: Oct 11–Oct 11----------------46mo
Forecast - Open Rack, Subrack, BB45UProduct OnlyDeadline: Sep 20, 20240/10 aktivitas selesaiCustomer VisitOverdue0/123moPlan: Aug 23–Aug 26Aproval DrawOverdue0/123moPlan: Aug 26–Aug 26BOQOverdue0/123moPlan: Aug 27–Aug 27FEPOverdue0/123moPlan: Aug 26–Aug 27TD PKBOverdue0/123moPlan: Aug 27–Aug 28TD WeldOverdue0/123moPlan: Aug 28–Aug 28TD AssyOverdue0/123moPlan: Aug 28–Aug 293D BusbarOverdue0/123moPlan: Aug 29–Aug 293D AssyOverdue0/123moPlan: Aug 29–Aug 30TD VLispOverdue0/123moPlan: Aug 30–Aug 30------------------23mo
PT Roka Lane Asia - Rack Server 52U DWDM MMRProduct + InstalasiDeadline: Aug 21, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/16dPlan: Jul 1–Jul 2Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 9–Jul 10Membuat Approval Drawing GA-SLD/cutoutOverdue0/11dPlan: Jul 6–Jul 7Membuat BomlistOverdue0/16dPlan: Jul 2–Jul 2Membuat BomlistOverdue0/11dPlan: Jul 7–Jul 7Membuat Timeline instalasiOn Progress0/1Plan: Jul 10–Jul 10Membuat BomlistOn Progress0/1Plan: Jul 10–Jul 13Membuat SchematicOverdue0/11dPlan: Jul 7–Jul 7Technical DrawingOverdue0/15dPlan: Jul 2–Jul 3Melakukan Design ReviewOverdue0/15dPlan: Jul 3–Jul 3Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 7–Jul 8Membuat MOP/WIOn Progress0/1Plan: Jul 13–Jul 13Membuat MOP/WIOn Progress0/1Plan: Jul 8–Jul 8Membuat SOPOn Progress0/1Plan: Jul 13–Jul 13Permintaan Customer VisitOverdue0/12dPlan: Jul 3–Jul 6Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 13–Jul 14Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 8–Jul 8Membuat MOP/WIOverdue0/12dPlan: Jul 6–Jul 6Melakukan Design ReviewOn Progress0/1Plan: Jul 8–Jul 9Membuat Materi TrainingOverdue0/12dPlan: Jul 6–Jul 6Membuat Materi TrainingOn Progress0/1Plan: Jul 14–Jul 14Membuat Materi TrainingOn Progress0/1Plan: Jul 9–Jul 9Permintaan Customer VisitOn Progress0/1Plan: Jul 14–Jul 14Permintaan Customer VisitOn Progress0/1Plan: Jul 9–Jul 9----6d
ELEC_ HV_SYSTEMProduct OnlyDeadline: Oct 12, 20220/7 aktivitas selesaiDraft Cutout ViewOverdue0/3045moPlan: Oct 12–Oct 19Approval CutoutOverdue0/3045moPlan: Oct 13–Oct 20BOM HVOverdue0/3045moPlan: Oct 14–Oct 21Cutout listOverdue0/3045moPlan: Oct 18–Oct 25Wiring ListOverdue0/3045moPlan: Oct 17–Oct 21Printout SchematicOverdue0/3045moPlan: Oct 19–Oct 25Tubing ListOverdue0/3045moPlan: Oct 17–Oct 24---------------------45mo
Review Drawing RDMPProduct OnlyDeadline: Oct 13, 20221/8 aktivitas selesaiGADone1/1Plan: Oct 13–Oct 14Actual: Oct 13SLDOverdue0/145moPlan: Oct 14–Oct 14SchematicsOverdue0/145moPlan: Oct 14–Oct 17BOQ LIst Elec_LVOverdue0/145moPlan: Oct 17–Oct 17(aktivitas)Overdue0/145moPlan: Oct 17–Oct 17Bom List ElectricalOverdue0/145moPlan: Oct 17–Oct 18Preare DOc Operation (ATP,MOP,EOP;etc)Overdue0/145moPlan: Oct 18–Oct 18Design ReviewOverdue0/145moPlan: Oct 18–Oct 18--------------------45mo
Schneider Electric - LNGPPProduct + InstalasiDeadline: Apr 30, 20260/7 aktivitas selesaiMembuat Timeline instalasiOverdue0/14moPlan: Mar 19–Mar 20Membuat BomlistOverdue0/14moPlan: Mar 20–Mar 20Membuat MOP/WIOverdue0/14moPlan: Mar 20–Mar 23Membuat SOPOverdue0/14moPlan: Mar 23–Mar 23Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 23–Mar 23Membuat Materi TrainingOverdue0/14moPlan: Mar 23–Mar 24Permintaan Customer VisitOverdue0/14moPlan: Mar 24–Mar 24---------------------4mo
ERCS DCAM - Loadbank PanelProduct + InstalasiDeadline: Aug 24, 20267/17 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Jun 1–Jun 2Actual: May 8Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 4–Jun 5Actual: May 5Membuat BomlistDone1/16dPlan: Jun 2–Jun 2Actual: Jun 8Membuat BomlistDone1/1Plan: Jun 5–Jun 5Actual: May 25Membuat Timeline instalasiOn Progress0/1Plan: Jul 1–Jul 17Membuat BomlistOn Progress0/1Plan: Jul 1–Jul 17Membuat SchematicDone1/1Plan: Jun 5–Jun 5Actual: May 29Melakukan Design ReviewDone1/1Plan: Jun 3–Jun 3Actual: Jun 3Membuat MOP/WIOn Progress0/1Plan: Jul 1–Jul 10Membuat MOP/WIOverdue0/12wPlan: Jun 19–Jun 26Membuat SOPOn Progress0/1Plan: Jul 1–Jul 10Membuat Form FAT, Onsite, SATDone1/1Plan: Jun 8–Jun 12Actual: Jun 8Membuat MOP/WIOverdue0/11moPlan: Jun 4–Jun 4Melakukan Design ReviewOverdue0/14wPlan: Jun 8–Jun 9Membuat Materi TrainingOn Progress0/1Plan: Jul 27–Jul 31Permintaan Customer VisitOverdue0/11wPlan: Jun 30–Jun 30Permintaan Customer VisitOverdue0/11wPlan: Jun 30–Jun 30-----------1mo
PT. Vivandiere Technology Indonesia - Renovasi Gedung Data Center BNPT - SentulProduct + InstalasiDeadline: Jun 1, 202611/15 aktivitas selesaiMembuat Approval Drawing GA-SLDDone1/14wPlan: Mar 18–Mar 19Actual: Apr 13Membuat Approval Drawing GA-SLD/cutoutDone1/14wPlan: Mar 5–Mar 10Actual: Apr 6Membuat BomlistDone1/12moPlan: Mar 13–Mar 18Actual: May 4Membuat BomlistDone1/1Plan: Mar 13–Mar 18Actual: Apr 17Membuat BomlistDone1/1Plan: Mar 19–Mar 20Actual: Mar 20Membuat SchematicDone1/11moPlan: Mar 13–Mar 18Actual: Apr 28Technical DrawingDone1/12moPlan: Mar 13–Mar 18Actual: May 4Melakukan Design ReviewDone1/12moPlan: Mar 25–Mar 25Actual: May 15Membuat MOP/WIOverdue0/14moPlan: Mar 16–Mar 18Membuat MOP/WIDone1/13moPlan: Mar 9–Mar 18Actual: Jun 10Membuat SOPOverdue0/14moPlan: Mar 16–Mar 18Membuat Form FAT, Onsite, SATDone1/13moPlan: Mar 5–Mar 18Actual: Jun 10Melakukan Design ReviewDone1/12moPlan: Mar 5–Mar 18Actual: May 15Membuat Materi TrainingOverdue0/13moPlan: Mar 11–Mar 27Membuat Materi TrainingOverdue0/13moPlan: Mar 5–Mar 27-------------4mo
Ekamas Mora Republik - POP Villa Beji Bali_ACPDB & DCPDBProduct + InstalasiDeadline: Jul 10, 20265/24 aktivitas selesaiMembuat Approval Drawing GAOverdue0/12dPlan: Jul 3–Jul 6Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 13–Jul 14Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jul 8–Jul 9Actual: Jun 29Membuat BomlistDone1/1Plan: Jul 6–Jul 6Actual: Jun 30Membuat BomlistDone1/1Plan: Jul 9–Jul 9Actual: Jun 29Membuat Timeline instalasiOn Progress0/1Plan: Jul 14–Jul 14Membuat BomlistOn Progress0/1Plan: Jul 14–Jul 15Membuat SchematicDone1/1Plan: Jul 9–Jul 9Actual: Jun 29Technical DrawingDone1/1Plan: Jul 6–Jul 7Actual: Jun 30Melakukan Design ReviewOverdue0/11dPlan: Jul 7–Jul 7Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 9–Jul 10Membuat MOP/WIOn Progress0/1Plan: Jul 15–Jul 15Membuat MOP/WIOn Progress0/1Plan: Jul 10–Jul 10Membuat SOPOn Progress0/1Plan: Jul 15–Jul 15Permintaan Customer VisitOn Progress0/1Plan: Jul 7–Jul 8Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 15–Jul 16Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 10–Jul 10Membuat MOP/WIOn Progress0/1Plan: Jul 8–Jul 8Melakukan Design ReviewOn Progress0/1Plan: Jul 10–Jul 13Membuat Materi TrainingOn Progress0/1Plan: Jul 8–Jul 8Membuat Materi TrainingOn Progress0/1Plan: Jul 16–Jul 16Membuat Materi TrainingOn Progress0/1Plan: Jul 13–Jul 13Permintaan Customer VisitOn Progress0/1Plan: Jul 16–Jul 16Permintaan Customer VisitOn Progress0/1Plan: Jul 13–Jul 13----2d
Hitachi - ACP25053 - DSS Maumere 150kVProduct + InstalasiDeadline: Jul 6, 20267/8 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Feb 27–Feb 27Actual: Feb 25Membuat Approval Drawing GA-SLD/cutoutDone1/13dPlan: Feb 27–Feb 27Actual: Mar 2Membuat BomlistDone1/13wPlan: Mar 3–Mar 3Actual: Mar 25Membuat BomlistDone1/12wPlan: Mar 4–Mar 4Actual: Mar 18Membuat SchematicOverdue0/14moPlan: Mar 3–Mar 3Technical DrawingDone1/12wPlan: Mar 9–Mar 11Actual: Mar 25Melakukan Design ReviewDone1/11wPlan: Mar 12–Mar 12Actual: Mar 20Membuat Dxf Cutout / nameplateDone1/12wPlan: Mar 5–Mar 5Actual: Mar 17--------------------4mo
Hitachi - ACP25076 - Single Phi BarruProduct + InstalasiDeadline: Jun 16, 20269/9 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Mar 2–Mar 2Actual: Mar 2Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Mar 2–Mar 2Actual: Mar 2Membuat BomlistDone1/16dPlan: Mar 4–Mar 4Actual: Mar 10Membuat BomlistDone1/1Plan: Mar 10–Mar 10Actual: Mar 4Membuat SchematicDone1/1Plan: Mar 9–Mar 9Actual: Mar 9Technical DrawingDone1/1Plan: Mar 9–Mar 10Actual: Mar 4Melakukan Design ReviewDone1/1Plan: Mar 9–Mar 9Actual: Mar 4Membuat Dxf Cutout / nameplateDone1/1Plan: Mar 10–Mar 10Actual: Mar 9Melakukan Design ReviewDone1/1Plan: Mar 9–Mar 9Actual: Mar 4-------------------6d
MIG - PO-26-0171 - Project Alladin Panel S110 & S510 - Panel DistributionProduct + InstalasiDeadline: Jul 8, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOn Progress0/1Plan: Jul 17–Jul 20Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 27–Jul 28Membuat Approval Drawing GA-SLD/cutoutOn Progress0/1Plan: Jul 22–Jul 23Membuat BomlistOn Progress0/1Plan: Jul 20–Jul 20Membuat BomlistOn Progress0/1Plan: Jul 23–Jul 23Membuat Timeline instalasiOn Progress0/1Plan: Jul 28–Jul 28Membuat BomlistOn Progress0/1Plan: Jul 28–Jul 29Membuat SchematicOn Progress0/1Plan: Jul 23–Jul 23Technical DrawingOn Progress0/1Plan: Jul 20–Jul 21Melakukan Design ReviewOn Progress0/1Plan: Jul 21–Jul 21Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 23–Jul 24Membuat MOP/WIOn Progress0/1Plan: Jul 29–Jul 29Membuat MOP/WIOn Progress0/1Plan: Jul 24–Jul 24Membuat SOPOn Progress0/1Plan: Jul 29–Jul 29Permintaan Customer VisitOn Progress0/1Plan: Jul 21–Jul 22Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 29–Jul 30Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 24–Jul 24Membuat MOP/WIOn Progress0/1Plan: Jul 22–Jul 22Melakukan Design ReviewOn Progress0/1Plan: Jul 24–Jul 27Membuat Materi TrainingOn Progress0/1Plan: Jul 22–Jul 22Membuat Materi TrainingOn Progress0/1Plan: Jul 30–Jul 30Membuat Materi TrainingOn Progress0/1Plan: Jul 27–Jul 27Permintaan Customer VisitOn Progress0/1Plan: Jul 30–Jul 30Permintaan Customer VisitOn Progress0/1Plan: Jul 27–Jul 27----
Hitachi - ACP25029 - GI Tolinggula 150kVProduct + InstalasiDeadline: Jul 13, 20267/7 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Mar 27–Mar 27Actual: Mar 27Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Mar 18–Mar 18Actual: Mar 18Membuat BomlistDone1/11dPlan: Apr 1–Apr 1Actual: Apr 2Membuat BomlistDone1/11wPlan: Apr 2–Apr 2Actual: Apr 10Membuat SchematicDone1/11wPlan: Apr 2–Apr 2Actual: Apr 10Technical DrawingDone1/11dPlan: Apr 1–Apr 1Actual: Apr 2Membuat Dxf Cutout / nameplateDone1/11wPlan: Apr 3–Apr 3Actual: Apr 10---------------------1w
Inti Bumi Mas - Panel VFD 132KWProduct + InstalasiDeadline: Jul 22, 202610/10 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: Jan 5–Jan 5Actual: Jan 5Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jan 5–Jan 5Actual: Jan 5Membuat BomlistDone1/12moPlan: Jan 7–Jan 7Actual: Mar 4Membuat BomlistDone1/12moPlan: Jan 7–Jan 7Actual: Feb 24Membuat SchematicDone1/12moPlan: Jan 5–Jan 5Actual: Feb 24Technical DrawingDone1/12moPlan: Jan 7–Jan 8Actual: Mar 4Melakukan Design ReviewDone1/1Plan: Jan 12–Jan 8Actual: Jan 8Membuat Dxf Cutout / nameplateDone1/11moPlan: Jan 12–Jan 13Actual: Feb 24Membuat Form FAT, Onsite, SATDone1/13moPlan: Mar 13–Mar 13Actual: Jun 19Melakukan Design ReviewDone1/1Plan: Jan 9–Jan 9Actual: Jan 8------------------3mo
Hitachi - ACP26018 - GI KM17 Borneo IndobaraProduct + InstalasiDeadline: Jul 30, 20268/8 aktivitas selesaiMembuat Approval Drawing GADone1/1Plan: May 12–May 12Actual: May 12Membuat Approval Drawing GA-SLD/cutoutDone1/11wPlan: May 15–May 15Actual: May 25Membuat BomlistDone1/1Plan: May 15–May 15Actual: May 12Membuat BomlistDone1/16dPlan: May 19–May 19Actual: May 25Membuat SchematicDone1/1Plan: May 19–May 19Actual: May 18Technical DrawingDone1/1Plan: May 12–May 15Actual: May 12Melakukan Design ReviewDone1/1Plan: May 12–May 12Actual: May 11Membuat Dxf Cutout / nameplateDone1/1Plan: May 19–May 19Actual: May 15--------------------1w
Rumah Data Kita CGK11 - Rack Server 45UProduct + InstalasiDeadline: Sep 11, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOn Progress0/1Plan: Jul 14–Jul 15Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 22–Jul 23Membuat Approval Drawing GA-SLD/cutoutOn Progress0/1Plan: Jul 17–Jul 20Membuat BomlistOn Progress0/1Plan: Jul 15–Jul 15Membuat BomlistOn Progress0/1Plan: Jul 20–Jul 20Membuat Timeline instalasiOn Progress0/1Plan: Jul 23–Jul 23Membuat BomlistOn Progress0/1Plan: Jul 23–Jul 24Membuat SchematicOn Progress0/1Plan: Jul 20–Jul 20Technical DrawingOn Progress0/1Plan: Jul 15–Jul 16Melakukan Design ReviewOn Progress0/1Plan: Jul 16–Jul 16Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 20–Jul 21Membuat MOP/WIOn Progress0/1Plan: Jul 24–Jul 24Membuat MOP/WIOn Progress0/1Plan: Jul 21–Jul 21Membuat SOPOn Progress0/1Plan: Jul 24–Jul 24Permintaan Customer VisitOn Progress0/1Plan: Jul 16–Jul 17Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 24–Jul 27Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 21–Jul 21Membuat MOP/WIOn Progress0/1Plan: Jul 17–Jul 17Melakukan Design ReviewOn Progress0/1Plan: Jul 21–Jul 22Membuat Materi TrainingOn Progress0/1Plan: Jul 17–Jul 17Membuat Materi TrainingOn Progress0/1Plan: Jul 27–Jul 27Membuat Materi TrainingOn Progress0/1Plan: Jul 22–Jul 22Permintaan Customer VisitOn Progress0/1Plan: Jul 27–Jul 27Permintaan Customer VisitOn Progress0/1Plan: Jul 22–Jul 22----
Internal - Stock Box Container 40 Feet ( 10 Unit)Product + InstalasiDeadline: Sep 21, 20262/2 aktivitas selesaiMembuat BomlistDone1/1Plan: Nov 10–Nov 13Actual: Nov 13Melakukan Design ReviewDone1/1Plan: Dec 19–Dec 31Actual: Jan 13--------------------------
Hitachi - ACP25111 - Muara Laboh Stage 2Product + InstalasiDeadline: Oct 23, 20260/24 aktivitas selesaiMembuat Approval Drawing GAOn Progress0/1Plan: Jul 15–Jul 16Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 23–Jul 24Membuat Approval Drawing GA-SLD/cutoutOn Progress0/1Plan: Jul 20–Jul 21Membuat BomlistOn Progress0/1Plan: Jul 16–Jul 16Membuat BomlistOn Progress0/1Plan: Jul 21–Jul 21Membuat Timeline instalasiOn Progress0/1Plan: Jul 24–Jul 24Membuat BomlistOn Progress0/1Plan: Jul 24–Jul 27Membuat SchematicOn Progress0/1Plan: Jul 21–Jul 21Technical DrawingOn Progress0/1Plan: Jul 16–Jul 17Melakukan Design ReviewOn Progress0/1Plan: Jul 17–Jul 17Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 21–Jul 22Membuat MOP/WIOn Progress0/1Plan: Jul 27–Jul 27Membuat MOP/WIOn Progress0/1Plan: Jul 22–Jul 22Membuat SOPOn Progress0/1Plan: Jul 27–Jul 27Permintaan Customer VisitOn Progress0/1Plan: Jul 17–Jul 20Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 27–Jul 28Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 22–Jul 22Membuat MOP/WIOn Progress0/1Plan: Jul 20–Jul 20Melakukan Design ReviewOn Progress0/1Plan: Jul 22–Jul 23Membuat Materi TrainingOn Progress0/1Plan: Jul 20–Jul 20Membuat Materi TrainingOn Progress0/1Plan: Jul 28–Jul 28Membuat Materi TrainingOn Progress0/1Plan: Jul 23–Jul 23Permintaan Customer VisitOn Progress0/1Plan: Jul 28–Jul 28Permintaan Customer VisitOn Progress0/1Plan: Jul 23–Jul 23----