| MECHANICAL PROSESProduct OnlyDeadline: Oct 12, 20220/28 aktivitas selesai | Customer VisitOverdue0/2244moPlan: Oct 19–Dec 2 | Draft Cutout ViewOverdue0/1744moPlan: Nov 17–Nov 18 | Meet / Cust VisitOverdue1/2144moPlan: Oct 19–Nov 25Actual: Oct 25 | Approval CutoutOverdue0/1744moPlan: Nov 18–Nov 21 | Aproval DrawOverdue18/4544moPlan: Oct 12–Dec 2Actual: Nov 11 | BOQOverdue10/4544moPlan: Oct 13–Dec 6Actual: Nov 11 | GAOverdue1/2844moPlan: Oct 12–Nov 28Actual: Oct 26 | BOM HVOverdue0/1744moPlan: Nov 21–Nov 22 | FEPOverdue10/4544moPlan: Oct 13–Dec 5Actual: Nov 11 | SLDOverdue0/2844moPlan: Oct 13–Nov 28 | TD PKBOverdue16/4744moPlan: Oct 14–Dec 6Actual: Nov 10 | Cutout listOverdue0/1744moPlan: Nov 23–Nov 24 | PROGRAMOverdue5/4544moPlan: Oct 13–Dec 5Actual: Oct 24 | SchematicsOverdue0/2844moPlan: Oct 13–Nov 29 | TD WeldOverdue13/4544moPlan: Oct 14–Dec 6Actual: Nov 10 | Wiring ListOverdue0/1744moPlan: Nov 22–Nov 22 | BOQ LIst Elec_LVOverdue0/2844moPlan: Oct 14–Nov 29 | Printout SchematicOverdue0/1744moPlan: Nov 24–Nov 24 | TD AssyOverdue17/4644moPlan: Oct 14–Dec 7Actual: Nov 10 | Tubing ListOverdue0/1744moPlan: Nov 22–Nov 23 | (aktivitas)Overdue0/2844moPlan: Oct 14–Nov 30 | 3D BusbarOverdue5/4244moPlan: Oct 17–Dec 8Actual: Oct 27 | Bom List ElectricalOverdue0/2844moPlan: Oct 14–Nov 30 | 3D AssyOverdue10/4344moPlan: Oct 17–Dec 8Actual: Nov 11 | Preare DOc Operation (ATP,MOP,EOP;etc)Overdue0/2844moPlan: Oct 17–Dec 1 | Design ReviewOverdue0/2844moPlan: Oct 17–Dec 1 | TD VLispOverdue3/4044moPlan: Oct 17–Dec 8Actual: Oct 19 | OthersOverdue16/4744moPlan: Oct 14–Dec 7Actual: Nov 10 | 44mo |
| PRODUCT & DEVELOPMENTProduct OnlyDeadline: Oct 12, 20220/28 aktivitas selesai | Customer VisitOverdue0/644moPlan: Oct 13–Nov 17 | Draft Cutout ViewOverdue0/245moPlan: Nov 2–Nov 3 | Meet / Cust VisitOverdue0/345moPlan: Oct 13–Nov 10 | Approval CutoutOverdue0/245moPlan: Nov 3–Nov 4 | Aproval DrawOverdue2/944moPlan: Oct 12–Nov 17Actual: Oct 19 | BOQOverdue3/1044moPlan: Oct 13–Nov 21Actual: Oct 24 | GAOverdue0/345moPlan: Oct 14–Nov 11 | BOM HVOverdue0/245moPlan: Nov 4–Nov 7 | FEPOverdue2/944moPlan: Oct 13–Nov 18Actual: Oct 19 | SLDOverdue0/345moPlan: Oct 17–Nov 11 | TD PKBOverdue3/1044moPlan: Oct 14–Nov 21Actual: Oct 24 | Cutout listOverdue0/245moPlan: Nov 8–Nov 9 | PROGRAMOverdue2/944moPlan: Oct 13–Nov 18Actual: Oct 19 | SchematicsOverdue0/344moPlan: Oct 17–Nov 14 | TD WeldOverdue2/944moPlan: Oct 14–Nov 21Actual: Oct 20 | Wiring ListOverdue0/245moPlan: Nov 7–Nov 7 | BOQ LIst Elec_LVOverdue0/344moPlan: Oct 18–Nov 14 | Printout SchematicOverdue0/245moPlan: Nov 9–Nov 9 | TD AssyOverdue3/1044moPlan: Oct 14–Nov 22Actual: Oct 24 | Tubing ListOverdue0/245moPlan: Nov 7–Nov 8 | (aktivitas)Overdue0/244moPlan: Nov 14–Nov 15 | 3D BusbarOverdue1/844moPlan: Oct 17–Nov 23Actual: Oct 19 | Bom List ElectricalOverdue0/344moPlan: Oct 19–Nov 15 | 3D AssyOverdue1/844moPlan: Oct 17–Nov 23Actual: Oct 19 | Preare DOc Operation (ATP,MOP,EOP;etc)Overdue0/344moPlan: Oct 20–Nov 16 | Design ReviewOverdue0/344moPlan: Oct 19–Nov 16 | TD VLispOverdue2/944moPlan: Oct 17–Nov 23Actual: Oct 21 | OthersOverdue3/1044moPlan: Oct 14–Nov 22Actual: Oct 24 | 45mo |
| ELEC_ LV_SYSTEMProduct OnlyDeadline: Oct 27, 20220/28 aktivitas selesai | Customer VisitOverdue0/244moPlan: Oct 19–Nov 22 | Draft Cutout ViewOverdue0/145moPlan: Nov 7–Nov 8 | Meet / Cust VisitOverdue0/4544moPlan: Oct 12–Nov 15 | Approval CutoutOverdue0/145moPlan: Nov 8–Nov 9 | Aproval DrawOverdue0/244moPlan: Oct 20–Nov 22 | BOQOverdue0/244moPlan: Oct 21–Nov 24 | GAOverdue8/12044moPlan: Oct 12–Nov 16Actual: Oct 20 | BOM HVOverdue0/145moPlan: Nov 9–Nov 10 | FEPOverdue0/244moPlan: Oct 20–Nov 23 | SLDOverdue4/11844moPlan: Oct 13–Nov 16Actual: Oct 20 | TD PKBOverdue0/244moPlan: Oct 24–Nov 24 | Cutout listOverdue0/144moPlan: Nov 11–Nov 14 | PROGRAMOverdue0/244moPlan: Oct 21–Nov 23 | SchematicsOverdue9/11344moPlan: Oct 13–Nov 17Actual: Oct 26 | TD WeldOverdue0/244moPlan: Oct 24–Nov 24 | Wiring ListOverdue0/145moPlan: Nov 10–Nov 10 | BOQ LIst Elec_LVOverdue5/11244moPlan: Oct 14–Nov 17Actual: Oct 20 | Printout SchematicOverdue0/144moPlan: Nov 14–Nov 14 | TD AssyOverdue0/244moPlan: Oct 24–Nov 25 | Tubing ListOverdue0/145moPlan: Nov 10–Nov 11 | (aktivitas)Overdue1/11244moPlan: Oct 14–Nov 18Actual: Oct 14 | 3D BusbarOverdue0/244moPlan: Oct 25–Nov 28 | Bom List ElectricalOverdue5/11244moPlan: Oct 14–Nov 18Actual: Oct 19 | 3D AssyOverdue0/244moPlan: Oct 26–Nov 28 | Preare DOc Operation (ATP,MOP,EOP;etc)Overdue1/11444moPlan: Oct 17–Nov 21Actual: Oct 20 | Design ReviewOverdue3/11244moPlan: Oct 17–Nov 21Actual: Oct 19 | TD VLispOverdue0/244moPlan: Oct 26–Nov 28 | OthersOverdue0/244moPlan: Oct 25–Nov 25 | 45mo |
| Internal - Stock Rack Server Moratel & DCPDUProduct + InstalasiDeadline: Jan 30, 20261/28 aktivitas selesai | Membuat Approval Drawing GAOverdue0/28moPlan: Nov 7–Nov 7 | Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 17–Nov 17 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/18moPlan: Nov 12–Nov 12 | Membuat BomlistOverdue0/18moPlan: Nov 12–Nov 13 | Membuat BomlistDone1/1Plan: Nov 10–Nov 10Actual: Nov 10 | Membuat Timeline instalasiOverdue0/18moPlan: Nov 17–Nov 18 | Membuat BomlistOverdue0/18moPlan: Nov 18–Nov 18 | Membuat SchematicOverdue0/28moPlan: Nov 13–Nov 13 | Technical DrawingOverdue0/18moPlan: Nov 10–Nov 10 | Vlisp Technical Drawing Overdue0/18moPlan: Nov 10–Nov 10 | Melakukan Design ReviewOverdue0/18moPlan: Nov 11–Nov 11 | Membuat Dxf Cutout / nameplateOverdue0/18moPlan: Nov 13–Nov 14 | Membuat MOP/WIOverdue0/18moPlan: Nov 18–Nov 19 | TD BusbarOverdue0/18moPlan: Nov 10–Nov 11 | 3D design Overdue0/18moPlan: Nov 11–Nov 11 | Membuat MOP/WIOverdue0/18moPlan: Nov 14–Nov 14 | Membuat SOPOverdue0/18moPlan: Nov 19–Nov 19 | Permintaan Customer VisitOverdue0/18moPlan: Nov 12–Nov 12 | Membuat Form FAT, ATP, SATOverdue0/18moPlan: Nov 19–Nov 20 | Membuat Form FAT, Onsite, SATOverdue0/18moPlan: Nov 14–Nov 14 | Membuat MOP/WIOverdue0/48moPlan: Nov 12–Nov 12 | Melakukan Design ReviewOverdue0/18moPlan: Nov 14–Nov 17 | Membuat Materi TrainingOverdue0/38moPlan: Nov 12–Nov 12 | Membuat Materi TrainingOverdue0/18moPlan: Nov 20–Nov 20 | TD BusbarOverdue0/18moPlan: Nov 11–Nov 12 | Membuat Materi TrainingOverdue0/18moPlan: Nov 17–Nov 17 | Permintaan Customer VisitOverdue0/38moPlan: Nov 20–Nov 20 | Permintaan Customer VisitOverdue0/38moPlan: Nov 17–Nov 17 | 8mo |
| Kelinci Mas - DSS TallolamaProduct OnlyDeadline: Aug 7, 20260/27 aktivitas selesai | Membuat Approval Drawing GAOverdue1/249moPlan: Oct 1–Oct 11Actual: Oct 2 | Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 6–Nov 7 | Membuat Approval Drawing GA-SLD/cutoutOverdue1/248moPlan: Oct 14–Nov 2Actual: Oct 3 | Membuat BomlistOverdue1/248moPlan: Oct 10–Oct 30Actual: Oct 31 | Membuat BomlistOverdue1/248moPlan: Oct 15–Nov 2Actual: Oct 13 | Membuat Timeline instalasiOverdue0/18moPlan: Nov 7–Nov 7 | Membuat BomlistOverdue0/18moPlan: Nov 7–Nov 8 | Membuat SchematicOverdue1/248moPlan: Oct 15–Nov 5Actual: Nov 5 | Technical DrawingOverdue1/248moPlan: Oct 13–Oct 31Actual: Oct 31 | Vlisp Technical Drawing Overdue1/248moPlan: Oct 10–Oct 30Actual: Oct 31 | Melakukan Design ReviewOverdue1/248moPlan: Oct 14–Nov 1Actual: Nov 10 | Membuat Dxf Cutout / nameplateOverdue1/248moPlan: Oct 16–Nov 5Actual: Oct 3 | Membuat MOP/WIOverdue0/18moPlan: Nov 8–Nov 8 | TD BusbarOverdue1/248moPlan: Oct 10–Oct 31Actual: Oct 31 | 3D design Overdue1/248moPlan: Oct 13–Oct 31Actual: Oct 31 | Membuat MOP/WIOverdue1/248moPlan: Oct 16–Nov 5Actual: Nov 5 | Membuat SOPOverdue0/18moPlan: Nov 8–Nov 9 | Permintaan Customer VisitOverdue0/248moPlan: Oct 14–Nov 1 | Membuat Form FAT, ATP, SATOverdue0/18moPlan: Nov 9–Nov 9 | Membuat Form FAT, Onsite, SATOverdue1/248moPlan: Oct 16–Nov 6Actual: Nov 5 | Membuat MOP/WIOverdue0/18moPlan: Nov 1–Nov 1 | Melakukan Design ReviewOverdue1/248moPlan: Oct 17–Nov 6Actual: Nov 11 | Membuat Materi TrainingOverdue0/18moPlan: Nov 1–Nov 1 | Membuat Materi TrainingOverdue0/18moPlan: Nov 9–Nov 9 | TD BusbarOverdue1/248moPlan: Oct 13–Nov 1Actual: Oct 31 | Membuat Materi TrainingOverdue0/248moPlan: Oct 17–Nov 6 | Permintaan Customer VisitOverdue0/18moPlan: Nov 6–Nov 6 | - | 9mo |
| GSPE_STOK BOX PANEL MORATELProduct + InstalasiDeadline: Aug 13, 20250/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/311moPlan: Aug 22–Aug 25 | Membuat Approval Drawing GA-SLDOverdue0/310moPlan: Sep 1–Sep 2 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/310moPlan: Aug 27–Aug 28 | Membuat BomlistOverdue0/311moPlan: Aug 25–Aug 25 | Membuat BomlistOverdue0/310moPlan: Aug 28–Aug 28 | Membuat Timeline instalasiOverdue0/310moPlan: Sep 2–Sep 2 | Membuat BomlistOverdue0/310moPlan: Sep 2–Sep 3 | Membuat SchematicOverdue0/310moPlan: Aug 28–Aug 28 | Technical DrawingOverdue0/311moPlan: Aug 25–Aug 26 | Melakukan Design ReviewOverdue0/311moPlan: Aug 26–Aug 26 | Membuat Dxf Cutout / nameplateOverdue0/310moPlan: Aug 28–Aug 29 | Membuat MOP/WIOverdue0/310moPlan: Sep 3–Sep 3 | Membuat MOP/WIOverdue0/310moPlan: Aug 29–Aug 29 | Membuat SOPOverdue0/310moPlan: Sep 3–Sep 3 | Permintaan Customer VisitOverdue0/311moPlan: Aug 26–Aug 27 | Membuat Form FAT, ATP, SATOverdue0/310moPlan: Sep 3–Sep 4 | Membuat Form FAT, Onsite, SATOverdue0/310moPlan: Aug 29–Aug 29 | Membuat MOP/WIOverdue0/311moPlan: Aug 27–Aug 27 | Melakukan Design ReviewOverdue0/310moPlan: Aug 29–Sep 1 | Membuat Materi TrainingOverdue0/311moPlan: Aug 27–Aug 27 | Membuat Materi TrainingOverdue0/310moPlan: Sep 4–Sep 4 | Membuat Materi TrainingOverdue0/310moPlan: Sep 1–Sep 1 | Permintaan Customer VisitOverdue0/310moPlan: Sep 4–Sep 4 | Permintaan Customer VisitOverdue0/310moPlan: Sep 1–Sep 1 | - | - | - | - | 11mo |
| Forecast_Stock Panel Hitachi IP42 & IP54Product + InstalasiDeadline: Oct 10, 20250/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/310moPlan: Sep 24–Sep 25 | Membuat Approval Drawing GA-SLDOverdue0/39moPlan: Oct 2–Oct 3 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/39moPlan: Sep 29–Sep 30 | Membuat BomlistOverdue0/310moPlan: Sep 25–Sep 25 | Membuat BomlistOverdue0/39moPlan: Sep 30–Sep 30 | Membuat Timeline instalasiOverdue0/39moPlan: Oct 3–Oct 3 | Membuat BomlistOverdue0/39moPlan: Oct 3–Oct 6 | Membuat SchematicOverdue0/39moPlan: Sep 30–Sep 30 | Technical DrawingOverdue0/310moPlan: Sep 25–Sep 26 | Melakukan Design ReviewOverdue0/310moPlan: Sep 26–Sep 26 | Membuat Dxf Cutout / nameplateOverdue0/39moPlan: Sep 30–Oct 1 | Membuat MOP/WIOverdue0/39moPlan: Oct 6–Oct 6 | Membuat MOP/WIOverdue0/39moPlan: Oct 1–Oct 1 | Membuat SOPOverdue0/39moPlan: Oct 6–Oct 6 | Permintaan Customer VisitOverdue0/39moPlan: Sep 26–Sep 29 | Membuat Form FAT, ATP, SATOverdue0/39moPlan: Oct 6–Oct 7 | Membuat Form FAT, Onsite, SATOverdue0/39moPlan: Oct 1–Oct 1 | Membuat MOP/WIOverdue0/39moPlan: Sep 29–Sep 29 | Melakukan Design ReviewOverdue0/39moPlan: Oct 1–Oct 2 | Membuat Materi TrainingOverdue0/39moPlan: Sep 29–Sep 29 | Membuat Materi TrainingOverdue0/39moPlan: Oct 7–Oct 7 | Membuat Materi TrainingOverdue0/39moPlan: Oct 2–Oct 2 | Permintaan Customer VisitOverdue0/39moPlan: Oct 7–Oct 7 | Permintaan Customer VisitOverdue0/39moPlan: Oct 2–Oct 2 | - | - | - | - | 10mo |
| PTT - Module MPTT DPC 3000 HE (25 unit)Product + InstalasiDeadline: Dec 19, 20250/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/17moPlan: Dec 18–Dec 18 | Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Dec 26–Dec 26 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/27moPlan: Dec 23–Dec 23 | Membuat BomlistOverdue0/17moPlan: Dec 18–Dec 19 | Membuat BomlistOverdue0/17moPlan: Dec 23–Dec 24 | Membuat Timeline instalasiOverdue0/16moPlan: Dec 26–Dec 29 | Membuat BomlistOverdue0/16moPlan: Dec 29–Dec 29 | Membuat SchematicOverdue0/17moPlan: Dec 24–Dec 24 | Technical DrawingOverdue0/17moPlan: Dec 19–Dec 19 | Melakukan Design ReviewOverdue0/17moPlan: Dec 19–Dec 22 | Membuat Dxf Cutout / nameplateOverdue0/27moPlan: Dec 24–Dec 24 | Membuat MOP/WIOverdue0/26moPlan: Dec 29–Dec 30 | Membuat MOP/WIOverdue0/17moPlan: Dec 24–Dec 25 | Membuat SOPOverdue0/16moPlan: Dec 30–Dec 30 | Permintaan Customer VisitOverdue0/17moPlan: Dec 22–Dec 22 | Membuat Form FAT, ATP, SATOverdue0/16moPlan: Dec 30–Dec 30 | Membuat Form FAT, Onsite, SATOverdue0/27moPlan: Dec 25–Dec 25 | Membuat MOP/WIOverdue0/27moPlan: Dec 22–Dec 23 | Melakukan Design ReviewOverdue0/17moPlan: Dec 25–Dec 25 | Membuat Materi TrainingOverdue0/17moPlan: Dec 23–Dec 23 | Membuat Materi TrainingOverdue0/26moPlan: Dec 30–Dec 31 | Membuat Materi TrainingOverdue0/16moPlan: Dec 25–Dec 26 | Permintaan Customer VisitOverdue0/16moPlan: Dec 31–Dec 31 | Permintaan Customer VisitOverdue0/16moPlan: Dec 26–Dec 26 | - | - | - | - | 7mo |
| BDX - CGK1_RACK SERVER & rPDUProduct + InstalasiDeadline: Feb 6, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue2/36moPlan: Dec 17–Dec 31Actual: Dec 17 | Membuat Approval Drawing GA-SLDOverdue1/46moPlan: Dec 17–Jan 8Actual: Dec 17 | Membuat Approval Drawing GA-SLD/cutoutOverdue1/26moPlan: Dec 17–Jan 5Actual: Dec 17 | Membuat BomlistOverdue2/36moPlan: Dec 18–Dec 31Actual: Dec 18 | Membuat BomlistOverdue1/26moPlan: Dec 17–Jan 5Actual: Dec 17 | Membuat Timeline instalasiOverdue1/46moPlan: Nov 18–Jan 8Actual: Dec 18 | Membuat BomlistOverdue1/46moPlan: Nov 19–Jan 9Actual: Dec 18 | Membuat SchematicOverdue1/26moPlan: Dec 16–Jan 5Actual: Dec 17 | Technical DrawingOverdue2/36moPlan: Dec 18–Jan 1Actual: Dec 18 | Melakukan Design ReviewOverdue2/36moPlan: Dec 18–Jan 1Actual: Dec 18 | Membuat Dxf Cutout / nameplateOverdue1/26moPlan: Dec 16–Jan 6Actual: Dec 17 | Membuat MOP/WIOverdue0/46moPlan: Nov 19–Jan 19 | Membuat MOP/WIOverdue0/26moPlan: Jan 6–Jan 19 | Membuat SOPOverdue0/46moPlan: Jan 9–Jan 19 | Permintaan Customer VisitOverdue2/36moPlan: Dec 18–Jan 2Actual: Dec 31 | Membuat Form FAT, ATP, SATOverdue0/56moPlan: Jan 9–Jan 19 | Membuat Form FAT, Onsite, SATOverdue0/86moPlan: Jan 6–Jan 19 | Membuat MOP/WIOverdue1/36moPlan: Jan 2–Jan 19Actual: Jan 19 | Melakukan Design ReviewOverdue1/26moPlan: Dec 24–Jan 7Actual: Dec 19 | Membuat Materi TrainingOverdue0/36moPlan: Jan 2–Jan 19 | Membuat Materi TrainingOverdue0/36moPlan: Jan 12–Jan 22 | Membuat Materi TrainingOverdue0/36moPlan: Dec 24–Jan 7 | Permintaan Customer VisitOverdue0/25moPlan: Jan 12–Jan 30 | Permintaan Customer VisitOverdue1/26moPlan: Dec 25–Jan 7Actual: Dec 22 | - | - | - | - | 6mo |
| Internal - Layout Penambahan Unit Mesin HSGProduct + InstalasiDeadline: Feb 6, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/35moPlan: Feb 2–Feb 2 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 10–Feb 10 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 5–Feb 5 | Membuat BomlistOverdue0/15moPlan: Feb 2–Feb 3 | Membuat BomlistOverdue0/15moPlan: Feb 5–Feb 6 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 10–Feb 11 | Membuat BomlistOverdue0/15moPlan: Feb 11–Feb 11 | Membuat SchematicOverdue0/25moPlan: Feb 6–Feb 6 | Technical DrawingOverdue0/15moPlan: Feb 3–Feb 3 | Melakukan Design ReviewOverdue0/15moPlan: Feb 3–Feb 4 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 6–Feb 6 | Membuat MOP/WIOverdue0/15moPlan: Feb 11–Feb 12 | Membuat MOP/WIOverdue0/15moPlan: Feb 6–Feb 9 | Membuat SOPOverdue0/15moPlan: Feb 12–Feb 12 | Permintaan Customer VisitOverdue0/15moPlan: Feb 4–Feb 4 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 12–Feb 12 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 9–Feb 9 | Membuat MOP/WIOverdue0/15moPlan: Feb 4–Feb 5 | Melakukan Design ReviewOverdue0/15moPlan: Feb 9–Feb 9 | Membuat Materi TrainingOverdue0/15moPlan: Feb 5–Feb 5 | Membuat Materi TrainingOverdue0/15moPlan: Feb 12–Feb 13 | Membuat Materi TrainingOverdue0/15moPlan: Feb 9–Feb 10 | Permintaan Customer VisitOverdue0/15moPlan: Feb 13–Feb 13 | Permintaan Customer VisitOverdue0/15moPlan: Feb 10–Feb 10 | - | - | - | - | 5mo |
| Job LeaderProduct + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/18moPlan: Nov 19–Nov 20 | Membuat Approval Drawing GA-SLDOverdue0/17moPlan: Nov 27–Nov 28 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/18moPlan: Nov 24–Nov 25 | Membuat BomlistOverdue0/26moPlan: Nov 25–Dec 31 | Membuat BomlistOverdue1/26moPlan: Nov 20–Jan 13Actual: Jan 13 | Membuat Timeline instalasiOverdue0/17moPlan: Nov 28–Nov 28 | Membuat BomlistOverdue0/17moPlan: Nov 28–Dec 1 | Membuat SchematicOverdue0/26moPlan: Nov 25–Jan 9 | Technical DrawingOverdue0/18moPlan: Nov 20–Nov 21 | Melakukan Design ReviewOverdue0/26moPlan: Nov 19–Jan 12 | Membuat Dxf Cutout / nameplateOverdue0/17moPlan: Nov 25–Nov 26 | Membuat MOP/WIOverdue0/17moPlan: Dec 1–Dec 1 | Membuat MOP/WIOverdue0/17moPlan: Nov 26–Nov 26 | Membuat SOPOverdue0/17moPlan: Dec 1–Dec 1 | Permintaan Customer VisitOverdue0/18moPlan: Nov 21–Nov 24 | Membuat Form FAT, ATP, SATOverdue0/17moPlan: Dec 1–Dec 2 | Membuat Form FAT, Onsite, SATOverdue0/17moPlan: Nov 26–Nov 26 | Membuat MOP/WIOverdue0/18moPlan: Nov 24–Nov 24 | Melakukan Design ReviewOverdue0/26moPlan: Nov 26–Jan 12 | Membuat Materi TrainingOverdue0/18moPlan: Nov 24–Nov 24 | Membuat Materi TrainingOverdue0/17moPlan: Dec 2–Dec 2 | Membuat Materi TrainingOverdue0/17moPlan: Nov 27–Nov 27 | Permintaan Customer VisitOverdue0/17moPlan: Dec 2–Dec 2 | Permintaan Customer VisitOverdue0/17moPlan: Nov 27–Nov 27 | - | - | - | - | 8mo |
| Internal - Project ISO_27001Product + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/35moPlan: Jan 30–Jan 30 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 9 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 4 | Membuat BomlistOverdue0/15moPlan: Jan 30–Feb 2 | Membuat BomlistOverdue0/25moPlan: Feb 4–Feb 5 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 9–Feb 10 | Membuat BomlistOverdue0/25moPlan: Feb 10–Feb 10 | Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5 | Technical DrawingOverdue0/15moPlan: Feb 2–Feb 2 | Melakukan Design ReviewOverdue0/15moPlan: Feb 2–Feb 3 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 5 | Membuat MOP/WIOverdue0/15moPlan: Feb 10–Feb 11 | Membuat MOP/WIOverdue0/15moPlan: Feb 5–Feb 6 | Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11 | Permintaan Customer VisitOverdue0/25moPlan: Feb 3–Feb 3 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 11 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6 | Membuat MOP/WIOverdue0/15moPlan: Feb 3–Feb 4 | Melakukan Design ReviewOverdue0/35moPlan: Feb 6–Feb 6 | Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4 | Membuat Materi TrainingOverdue0/15moPlan: Feb 11–Feb 12 | Membuat Materi TrainingOverdue0/15moPlan: Feb 6–Feb 9 | Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12 | Permintaan Customer VisitOverdue0/15moPlan: Feb 9–Feb 9 | - | - | - | - | 5mo |
| Internal - Program Estimator (Containment, Container, Smart Rack)Product + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Jan 30–Feb 2 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 10 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 5 | Membuat BomlistOverdue0/15moPlan: Feb 2–Feb 2 | Membuat BomlistOverdue0/15moPlan: Feb 5–Feb 5 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 10–Feb 10 | Membuat BomlistOverdue0/15moPlan: Feb 10–Feb 11 | Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5 | Technical DrawingOverdue0/15moPlan: Feb 2–Feb 3 | Melakukan Design ReviewOverdue0/15moPlan: Feb 3–Feb 3 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 6 | Membuat MOP/WIOverdue0/15moPlan: Feb 11–Feb 11 | Membuat MOP/WIOverdue0/15moPlan: Feb 6–Feb 6 | Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11 | Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 4 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 12 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6 | Membuat MOP/WIOverdue0/15moPlan: Feb 4–Feb 4 | Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 9 | Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4 | Membuat Materi TrainingOverdue0/15moPlan: Feb 12–Feb 12 | Membuat Materi TrainingOverdue0/15moPlan: Feb 9–Feb 9 | Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12 | Permintaan Customer VisitOverdue0/15moPlan: Feb 9–Feb 9 | - | - | - | - | 5mo |
| Internal - Automation Program CRM Section 1-4Product + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Jan 30–Feb 2 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 10 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 5 | Membuat BomlistOverdue0/15moPlan: Feb 2–Feb 2 | Membuat BomlistOverdue0/15moPlan: Feb 5–Feb 5 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 10–Feb 10 | Membuat BomlistOverdue0/15moPlan: Feb 10–Feb 11 | Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5 | Technical DrawingOverdue0/15moPlan: Feb 2–Feb 3 | Melakukan Design ReviewOverdue0/15moPlan: Feb 3–Feb 3 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 6 | Membuat MOP/WIOverdue0/15moPlan: Feb 11–Feb 11 | Membuat MOP/WIOverdue0/15moPlan: Feb 6–Feb 6 | Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11 | Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 4 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 12 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6 | Membuat MOP/WIOverdue0/15moPlan: Feb 4–Feb 4 | Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 9 | Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4 | Membuat Materi TrainingOverdue0/15moPlan: Feb 12–Feb 12 | Membuat Materi TrainingOverdue0/15moPlan: Feb 9–Feb 9 | Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12 | Permintaan Customer VisitOverdue0/15moPlan: Feb 9–Feb 9 | - | - | - | - | 5mo |
| Internal - Perbaikan Loading/Unloading Area Pintu BelakangProduct + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/25moPlan: Jan 30–Jan 30 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 9 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 4 | Membuat BomlistOverdue0/15moPlan: Jan 30–Feb 2 | Membuat BomlistOverdue0/25moPlan: Feb 4–Feb 5 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 9–Feb 10 | Membuat BomlistOverdue0/15moPlan: Feb 10–Feb 10 | Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5 | Technical DrawingOverdue0/25moPlan: Feb 2–Feb 2 | Melakukan Design ReviewOverdue0/25moPlan: Feb 2–Feb 3 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 5 | Membuat MOP/WIOverdue0/15moPlan: Feb 10–Feb 11 | Membuat MOP/WIOverdue0/25moPlan: Feb 5–Feb 6 | Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11 | Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 3 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 11 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6 | Membuat MOP/WIOverdue0/15moPlan: Feb 3–Feb 4 | Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 6 | Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4 | Membuat Materi TrainingOverdue0/15moPlan: Feb 11–Feb 12 | Membuat Materi TrainingOverdue0/25moPlan: Feb 6–Feb 9 | Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12 | Permintaan Customer VisitOverdue0/25moPlan: Feb 9–Feb 9 | - | - | - | - | 5mo |
| Review Product Presentation - Marketing UpdateProduct + InstalasiDeadline: Feb 27, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Jan 30–Jan 30 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 9–Feb 9 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 4–Feb 4 | Membuat BomlistOverdue0/15moPlan: Jan 30–Feb 2 | Membuat BomlistOverdue0/15moPlan: Feb 4–Feb 5 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 9–Feb 10 | Membuat BomlistOverdue0/15moPlan: Feb 10–Feb 10 | Membuat SchematicOverdue0/15moPlan: Feb 5–Feb 5 | Technical DrawingOverdue0/15moPlan: Feb 2–Feb 2 | Melakukan Design ReviewOverdue0/15moPlan: Feb 2–Feb 3 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 5–Feb 5 | Membuat MOP/WIOverdue0/15moPlan: Feb 10–Feb 11 | Membuat MOP/WIOverdue0/15moPlan: Feb 5–Feb 6 | Membuat SOPOverdue0/15moPlan: Feb 11–Feb 11 | Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 3 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 11–Feb 11 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 6–Feb 6 | Membuat MOP/WIOverdue0/15moPlan: Feb 3–Feb 4 | Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 6 | Membuat Materi TrainingOverdue0/15moPlan: Feb 4–Feb 4 | Membuat Materi TrainingOverdue0/15moPlan: Feb 11–Feb 12 | Membuat Materi TrainingOverdue0/15moPlan: Feb 6–Feb 9 | Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12 | Permintaan Customer VisitOverdue0/15moPlan: Feb 9–Feb 9 | - | - | - | - | 5mo |
| Mega Akses - POP Tegal Cangkring-Bali (Add Battery)Product + InstalasiDeadline: Mar 13, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Jan 26–Jan 27 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 3–Feb 4 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Jan 29–Jan 30 | Membuat BomlistOverdue0/15moPlan: Jan 27–Jan 27 | Membuat BomlistOverdue0/15moPlan: Jan 30–Jan 30 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 4–Feb 4 | Membuat BomlistOverdue0/15moPlan: Feb 4–Feb 5 | Membuat SchematicOverdue0/15moPlan: Jan 30–Jan 30 | Technical DrawingOverdue0/15moPlan: Jan 27–Jan 28 | Melakukan Design ReviewOverdue0/15moPlan: Jan 28–Jan 28 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Jan 30–Feb 2 | Membuat MOP/WIOverdue0/15moPlan: Feb 5–Feb 5 | Membuat MOP/WIOverdue0/15moPlan: Feb 2–Feb 2 | Membuat SOPOverdue0/15moPlan: Feb 5–Feb 5 | Permintaan Customer VisitOverdue0/15moPlan: Jan 28–Jan 29 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 5–Feb 6 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 2–Feb 2 | Membuat MOP/WIOverdue0/15moPlan: Jan 29–Jan 29 | Melakukan Design ReviewOverdue0/15moPlan: Feb 2–Feb 3 | Membuat Materi TrainingOverdue0/15moPlan: Jan 29–Jan 29 | Membuat Materi TrainingOverdue0/15moPlan: Feb 6–Feb 6 | Membuat Materi TrainingOverdue0/15moPlan: Feb 3–Feb 3 | Permintaan Customer VisitOverdue0/15moPlan: Feb 6–Feb 6 | Permintaan Customer VisitOverdue0/15moPlan: Feb 3–Feb 3 | - | - | - | - | 5mo |
| Mega Akses - Req.Battery - JABODETABEKProduct + InstalasiDeadline: Apr 10, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Feb 10–Feb 11 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 18–Feb 19 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 13–Feb 16 | Membuat BomlistOverdue0/15moPlan: Feb 11–Feb 11 | Membuat BomlistOverdue0/15moPlan: Feb 16–Feb 16 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 19–Feb 19 | Membuat BomlistOverdue0/15moPlan: Feb 19–Feb 20 | Membuat SchematicOverdue0/15moPlan: Feb 16–Feb 16 | Technical DrawingOverdue0/15moPlan: Feb 11–Feb 12 | Melakukan Design ReviewOverdue0/15moPlan: Feb 12–Feb 12 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 16–Feb 17 | Membuat MOP/WIOverdue0/15moPlan: Feb 20–Feb 20 | Membuat MOP/WIOverdue0/15moPlan: Feb 17–Feb 17 | Membuat SOPOverdue0/15moPlan: Feb 20–Feb 20 | Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 13 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Feb 20–Feb 23 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 17–Feb 17 | Membuat MOP/WIOverdue0/15moPlan: Feb 13–Feb 13 | Melakukan Design ReviewOverdue0/15moPlan: Feb 17–Feb 18 | Membuat Materi TrainingOverdue0/15moPlan: Feb 13–Feb 13 | Membuat Materi TrainingOverdue0/15moPlan: Feb 23–Feb 23 | Membuat Materi TrainingOverdue0/15moPlan: Feb 18–Feb 18 | Permintaan Customer VisitOverdue0/15moPlan: Feb 23–Feb 23 | Permintaan Customer VisitOverdue0/15moPlan: Feb 18–Feb 18 | - | - | - | - | 5mo |
| INTERNAL | - MDCC Trial Full Schneider Device - ContainerProduct + InstalasiDeadline: Apr 20, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/96moPlan: Dec 22–Jan 1 | Membuat Approval Drawing GA-SLDOverdue0/95moPlan: Dec 30–Feb 5 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/96moPlan: Nov 20–Dec 26 | Membuat BomlistOverdue1/97moPlan: Nov 11–Dec 23Actual: Jan 12 | Membuat BomlistOverdue1/96moPlan: Nov 21–Dec 26Actual: Mar 2 | Membuat Timeline instalasiOverdue0/115moPlan: Dec 31–Feb 6 | Membuat BomlistOverdue0/95moPlan: Dec 31–Feb 6 | Membuat SchematicOverdue0/126moPlan: Nov 21–Dec 26 | Technical DrawingOverdue0/107moPlan: Nov 11–Dec 24 | Melakukan Design ReviewOverdue1/197moPlan: Nov 11–Dec 24Actual: Feb 4 | Membuat Dxf Cutout / nameplateOverdue0/105moPlan: Dec 26–Feb 1 | Membuat MOP/WIOverdue0/115moPlan: Jan 1–Feb 7 | Membuat MOP/WIOverdue0/95moPlan: Dec 29–Feb 4 | Membuat SOPOverdue0/115moPlan: Jan 1–Feb 7 | Permintaan Customer VisitOverdue0/107moPlan: Nov 19–Dec 25 | Membuat Form FAT, ATP, SATOverdue0/95moPlan: Jan 1–Feb 7 | Membuat Form FAT, Onsite, SATOverdue0/95moPlan: Dec 29–Feb 4 | Membuat MOP/WIOverdue0/97moPlan: Nov 19–Dec 25 | Melakukan Design ReviewOverdue0/95moPlan: Dec 29–Feb 4 | Membuat Materi TrainingOverdue0/97moPlan: Nov 20–Dec 25 | Membuat Materi TrainingOverdue0/115moPlan: Jan 2–Feb 8 | Membuat Materi TrainingOverdue0/95moPlan: Dec 30–Feb 5 | Permintaan Customer VisitOverdue0/95moPlan: Jan 2–Feb 8 | Permintaan Customer VisitOverdue0/95moPlan: Dec 30–Feb 5 | - | - | - | - | 7mo |
| Mega Akses - BDF Power Tanah Merah (Add Battery)Product + InstalasiDeadline: Apr 30, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/14moPlan: Feb 23–Feb 24 | Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Mar 3–Mar 4 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/14moPlan: Feb 26–Feb 27 | Membuat BomlistOverdue0/14moPlan: Feb 24–Feb 24 | Membuat BomlistOverdue0/14moPlan: Feb 27–Feb 27 | Membuat Timeline instalasiOverdue0/14moPlan: Mar 4–Mar 4 | Membuat BomlistOverdue0/14moPlan: Mar 4–Mar 5 | Membuat SchematicOverdue0/14moPlan: Feb 27–Feb 27 | Technical DrawingOverdue0/14moPlan: Feb 24–Feb 25 | Melakukan Design ReviewOverdue0/14moPlan: Feb 25–Feb 25 | Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Feb 27–Mar 2 | Membuat MOP/WIOverdue0/14moPlan: Mar 5–Mar 5 | Membuat MOP/WIOverdue0/14moPlan: Mar 2–Mar 2 | Membuat SOPOverdue0/14moPlan: Mar 5–Mar 5 | Permintaan Customer VisitOverdue0/14moPlan: Feb 25–Feb 26 | Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 5–Mar 6 | Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Mar 2–Mar 2 | Membuat MOP/WIOverdue0/14moPlan: Feb 26–Feb 26 | Melakukan Design ReviewOverdue0/14moPlan: Mar 2–Mar 3 | Membuat Materi TrainingOverdue0/14moPlan: Feb 26–Feb 26 | Membuat Materi TrainingOverdue0/14moPlan: Mar 6–Mar 6 | Membuat Materi TrainingOverdue0/14moPlan: Mar 3–Mar 3 | Permintaan Customer VisitOverdue0/14moPlan: Mar 6–Mar 6 | Permintaan Customer VisitOverdue0/14moPlan: Mar 3–Mar 3 | - | - | - | - | 4mo |
| BDX - CGK1_Panel PDUProduct + InstalasiDeadline: May 21, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue1/26moPlan: Oct 30–Jan 1Actual: Dec 17 | Membuat Approval Drawing GA-SLDOverdue0/17moPlan: Nov 4–Dec 14 | Membuat Approval Drawing GA-SLD/cutoutOverdue1/26moPlan: Oct 30–Jan 6Actual: Dec 17 | Membuat BomlistOverdue1/26moPlan: Oct 31–Jan 2Actual: Dec 19 | Membuat BomlistOverdue1/26moPlan: Oct 30–Jan 7Actual: Jan 9 | Membuat Timeline instalasiOverdue0/18moPlan: Oct 30–Nov 2 | Membuat BomlistOverdue0/17moPlan: Dec 2–Dec 2 | Membuat SchematicOverdue1/26moPlan: Oct 30–Jan 7Actual: Dec 17 | Technical DrawingOverdue1/26moPlan: Oct 31–Jan 2Actual: Dec 19 | Melakukan Design ReviewOverdue1/26moPlan: Nov 3–Jan 5Actual: Dec 19 | Membuat Dxf Cutout / nameplateOverdue1/26moPlan: Oct 30–Jan 7Actual: Dec 17 | Membuat MOP/WIOverdue0/17moPlan: Dec 2–Dec 3 | Membuat MOP/WIOverdue1/25moPlan: Jan 7–Jan 28Actual: Jan 28 | Membuat SOPOverdue0/17moPlan: Dec 2–Dec 5 | Permintaan Customer VisitOverdue1/26moPlan: Nov 3–Jan 5Actual: Jan 2 | Membuat Form FAT, ATP, SATOverdue0/17moPlan: Dec 4–Dec 4 | Membuat Form FAT, Onsite, SATOverdue1/26moPlan: Dec 2–Jan 8Actual: Jan 23 | Membuat MOP/WIOverdue1/25moPlan: Jan 5–Jan 28Actual: Jan 28 | Melakukan Design ReviewOverdue1/26moPlan: Dec 2–Jan 8Actual: Dec 19 | Membuat Materi TrainingOverdue0/17moPlan: Dec 4–Dec 5 | Membuat Materi TrainingOverdue0/26moPlan: Dec 2–Jan 6 | Membuat Materi TrainingOverdue0/26moPlan: Dec 2–Jan 9 | Permintaan Customer VisitOverdue0/17moPlan: Dec 5–Dec 5 | Permintaan Customer VisitOverdue1/26moPlan: Nov 4–Jan 9Actual: Jan 22 | - | - | - | - | 8mo |
| Internal - Forecast Rack Server : (42U, 45U, 52U)Product + InstalasiDeadline: May 29, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/36moPlan: Dec 22–Dec 31 | Membuat Approval Drawing GA-SLDOverdue0/34moPlan: Dec 30–Mar 21 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/35moPlan: Dec 25–Feb 1 | Membuat BomlistOverdue0/55moPlan: Dec 22–Jan 30 | Membuat BomlistOverdue0/55moPlan: Dec 25–Feb 2 | Membuat Timeline instalasiOverdue0/34moPlan: Dec 30–Mar 22 | Membuat BomlistOverdue0/44moPlan: Dec 31–Mar 22 | Membuat SchematicOverdue0/35moPlan: Dec 26–Feb 2 | Technical DrawingOverdue0/35moPlan: Dec 23–Jan 30 | Melakukan Design ReviewOverdue0/85moPlan: Dec 23–Jan 31 | Membuat Dxf Cutout / nameplateOverdue0/35moPlan: Dec 26–Feb 2 | Membuat MOP/WIOverdue0/44moPlan: Dec 31–Mar 23 | Membuat MOP/WIOverdue0/45moPlan: Dec 26–Feb 5 | Membuat SOPOverdue0/34moPlan: Jan 1–Mar 23 | Permintaan Customer VisitOverdue0/35moPlan: Dec 24–Jan 31 | Membuat Form FAT, ATP, SATOverdue0/44moPlan: Jan 1–Mar 23 | Membuat Form FAT, Onsite, SATOverdue0/35moPlan: Dec 29–Feb 5 | Membuat MOP/WIOverdue0/35moPlan: Dec 24–Feb 1 | Melakukan Design ReviewOverdue0/34moPlan: Dec 29–Mar 21 | Membuat Materi TrainingOverdue0/35moPlan: Dec 25–Feb 1 | Membuat Materi TrainingOverdue0/34moPlan: Jan 1–Mar 24 | Membuat Materi TrainingOverdue0/34moPlan: Dec 29–Mar 21 | Permintaan Customer VisitOverdue0/44moPlan: Jan 2–Mar 24 | Permintaan Customer VisitOverdue0/44moPlan: Dec 30–Mar 21 | - | - | - | - | 6mo |
| Intan Mufakat Raya - GIS 150 KV Gandul II/PamulangProduct + InstalasiDeadline: Jun 10, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/14moPlan: Mar 4–Mar 5 | Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Mar 12–Mar 13 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/14moPlan: Mar 9–Mar 10 | Membuat BomlistOverdue0/14moPlan: Mar 5–Mar 5 | Membuat BomlistOverdue0/14moPlan: Mar 10–Mar 10 | Membuat Timeline instalasiOverdue0/14moPlan: Mar 13–Mar 13 | Membuat BomlistOverdue0/14moPlan: Mar 13–Mar 16 | Membuat SchematicOverdue0/14moPlan: Mar 10–Mar 10 | Technical DrawingOverdue0/14moPlan: Mar 5–Mar 6 | Melakukan Design ReviewOverdue0/14moPlan: Mar 6–Mar 6 | Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Mar 10–Mar 11 | Membuat MOP/WIOverdue0/14moPlan: Mar 16–Mar 16 | Membuat MOP/WIOverdue0/14moPlan: Mar 11–Mar 11 | Membuat SOPOverdue0/14moPlan: Mar 16–Mar 16 | Permintaan Customer VisitOverdue0/14moPlan: Mar 6–Mar 9 | Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 16–Mar 17 | Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Mar 11–Mar 11 | Membuat MOP/WIOverdue0/14moPlan: Mar 9–Mar 9 | Melakukan Design ReviewOverdue0/14moPlan: Mar 11–Mar 12 | Membuat Materi TrainingOverdue0/14moPlan: Mar 9–Mar 9 | Membuat Materi TrainingOverdue0/14moPlan: Mar 17–Mar 17 | Membuat Materi TrainingOverdue0/14moPlan: Mar 12–Mar 12 | Permintaan Customer VisitOverdue0/14moPlan: Mar 17–Mar 17 | Permintaan Customer VisitOverdue0/14moPlan: Mar 12–Mar 12 | - | - | - | - | 4mo |
| Internal - Pembuatan Bak Treatment, Hoist, Oven dan TrolleyProduct + InstalasiDeadline: Jun 30, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/76moPlan: Nov 24–Jan 5 | Membuat Approval Drawing GA-SLDOverdue0/46moPlan: Dec 2–Jan 13 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/66moPlan: Nov 27–Jan 8 | Membuat BomlistOverdue0/56moPlan: Nov 24–Jan 14 | Membuat BomlistOverdue1/55moPlan: Nov 27–Jan 26Actual: Jan 26 | Membuat Timeline instalasiOverdue0/46moPlan: Dec 2–Jan 14 | Membuat BomlistOverdue0/46moPlan: Dec 3–Jan 14 | Membuat SchematicOverdue0/55moPlan: Nov 28–Jan 30 | Technical DrawingOverdue0/66moPlan: Nov 25–Jan 6 | Melakukan Design ReviewOverdue1/56moPlan: Nov 25–Jan 15Actual: Jan 15 | Membuat Dxf Cutout / nameplateOverdue0/46moPlan: Nov 28–Jan 9 | Membuat MOP/WIOverdue0/56moPlan: Dec 3–Jan 15 | Membuat MOP/WIOverdue0/56moPlan: Nov 28–Jan 12 | Membuat SOPOverdue0/66moPlan: Dec 4–Jan 15 | Permintaan Customer VisitOverdue0/56moPlan: Nov 26–Jan 7 | Membuat Form FAT, ATP, SATOverdue0/46moPlan: Dec 4–Jan 15 | Membuat Form FAT, Onsite, SATOverdue0/56moPlan: Dec 1–Jan 12 | Membuat MOP/WIOverdue0/56moPlan: Nov 26–Jan 8 | Melakukan Design ReviewOverdue0/86moPlan: Dec 1–Jan 13 | Membuat Materi TrainingOverdue0/46moPlan: Nov 27–Jan 8 | Membuat Materi TrainingOverdue0/56moPlan: Dec 4–Jan 16 | Membuat Materi TrainingOverdue0/56moPlan: Dec 1–Jan 13 | Permintaan Customer VisitOverdue0/46moPlan: Dec 5–Jan 16 | Permintaan Customer VisitOverdue0/56moPlan: Dec 2–Jan 13 | - | - | - | - | 6mo |
| ATOZ - Dakota Electrical Fitout (Batam)Product + InstalasiDeadline: Jul 24, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/14wPlan: Jun 9–Jun 10 | Membuat Approval Drawing GA-SLDOverdue0/13wPlan: Jun 17–Jun 18 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/13wPlan: Jun 12–Jun 15 | Membuat BomlistOverdue0/14wPlan: Jun 10–Jun 10 | Membuat BomlistOverdue0/13wPlan: Jun 15–Jun 15 | Membuat Timeline instalasiOverdue0/13wPlan: Jun 18–Jun 18 | Membuat BomlistOverdue0/13wPlan: Jun 18–Jun 19 | Membuat SchematicOverdue0/13wPlan: Jun 15–Jun 15 | Technical DrawingOverdue0/14wPlan: Jun 10–Jun 11 | Melakukan Design ReviewOverdue0/14wPlan: Jun 11–Jun 11 | Membuat Dxf Cutout / nameplateOverdue0/13wPlan: Jun 15–Jun 16 | Membuat MOP/WIOverdue0/13wPlan: Jun 19–Jun 19 | Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16 | Membuat SOPOverdue0/13wPlan: Jun 19–Jun 19 | Permintaan Customer VisitOverdue0/14wPlan: Jun 11–Jun 12 | Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 19–Jun 22 | Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 16–Jun 16 | Membuat MOP/WIOverdue0/14wPlan: Jun 12–Jun 12 | Melakukan Design ReviewOverdue0/13wPlan: Jun 16–Jun 17 | Membuat Materi TrainingOverdue0/14wPlan: Jun 12–Jun 12 | Membuat Materi TrainingOverdue0/12wPlan: Jun 22–Jun 22 | Membuat Materi TrainingOverdue0/13wPlan: Jun 17–Jun 17 | Permintaan Customer VisitOverdue0/12wPlan: Jun 22–Jun 22 | Permintaan Customer VisitOverdue0/13wPlan: Jun 17–Jun 17 | - | - | - | - | 4w |
| BDX CGK3 - Electrical MaterialProduct + InstalasiDeadline: Jul 24, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/14wPlan: Jun 11–Jun 12 | Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/13wPlan: Jun 16–Jun 17 | Membuat BomlistOverdue0/14wPlan: Jun 12–Jun 12 | Membuat BomlistOverdue0/13wPlan: Jun 17–Jun 17 | Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22 | Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23 | Membuat SchematicOverdue0/13wPlan: Jun 17–Jun 17 | Technical DrawingOverdue0/13wPlan: Jun 12–Jun 15 | Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15 | Membuat Dxf Cutout / nameplateOverdue0/13wPlan: Jun 17–Jun 18 | Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23 | Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18 | Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23 | Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16 | Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24 | Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18 | Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16 | Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19 | Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16 | Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24 | Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19 | Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24 | Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19 | - | - | - | - | 4w |
| Mega Akes - HUB Majalengka (Add Battery)Product + InstalasiDeadline: Jul 31, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Feb 20–Feb 23 | Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Mar 2–Mar 3 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/14moPlan: Feb 25–Feb 26 | Membuat BomlistOverdue0/15moPlan: Feb 23–Feb 23 | Membuat BomlistOverdue0/14moPlan: Feb 26–Feb 26 | Membuat Timeline instalasiOverdue0/14moPlan: Mar 3–Mar 3 | Membuat BomlistOverdue0/14moPlan: Mar 3–Mar 4 | Membuat SchematicOverdue0/14moPlan: Feb 26–Feb 26 | Technical DrawingOverdue0/14moPlan: Feb 23–Feb 24 | Melakukan Design ReviewOverdue0/14moPlan: Feb 24–Feb 24 | Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Feb 26–Feb 27 | Membuat MOP/WIOverdue0/14moPlan: Mar 4–Mar 4 | Membuat MOP/WIOverdue0/14moPlan: Feb 27–Feb 27 | Membuat SOPOverdue0/14moPlan: Mar 4–Mar 4 | Permintaan Customer VisitOverdue0/14moPlan: Feb 24–Feb 25 | Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 4–Mar 5 | Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Feb 27–Feb 27 | Membuat MOP/WIOverdue0/14moPlan: Feb 25–Feb 25 | Melakukan Design ReviewOverdue0/14moPlan: Feb 27–Mar 2 | Membuat Materi TrainingOverdue0/14moPlan: Feb 25–Feb 25 | Membuat Materi TrainingOverdue0/14moPlan: Mar 5–Mar 5 | Membuat Materi TrainingOverdue0/14moPlan: Mar 2–Mar 2 | Permintaan Customer VisitOverdue0/14moPlan: Mar 5–Mar 5 | Permintaan Customer VisitOverdue0/14moPlan: Mar 2–Mar 2 | - | - | - | - | 5mo |
| Hitachi - ACP25105 - Seko IndokomasProduct + InstalasiDeadline: Aug 12, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/14wPlan: Jun 11–Jun 12 | Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/13wPlan: Jun 16–Jun 17 | Membuat BomlistOverdue0/14wPlan: Jun 12–Jun 12 | Membuat BomlistOverdue0/13wPlan: Jun 17–Jun 17 | Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22 | Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23 | Membuat SchematicOverdue0/13wPlan: Jun 17–Jun 17 | Technical DrawingOverdue0/13wPlan: Jun 12–Jun 15 | Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15 | Membuat Dxf Cutout / nameplateOverdue0/13wPlan: Jun 17–Jun 18 | Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23 | Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18 | Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23 | Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16 | Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24 | Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18 | Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16 | Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19 | Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16 | Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24 | Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19 | Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24 | Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19 | - | - | - | - | 4w |
| Demo/Mockup Panel Typetest Cubic, Eaton MV, Eaton LVProduct + InstalasiDeadline: Aug 31, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/45moPlan: Jan 30–Feb 2 | Membuat Approval Drawing GA-SLDOverdue0/55moPlan: Feb 9–Feb 10 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/54moPlan: Feb 4–Feb 25 | Membuat BomlistOverdue0/75moPlan: Jan 30–Feb 2 | Membuat BomlistOverdue1/74moPlan: Feb 4–Mar 2Actual: Feb 5 | Membuat Timeline instalasiOverdue0/35moPlan: Feb 9–Feb 10 | Membuat BomlistOverdue0/55moPlan: Feb 10–Feb 11 | Membuat SchematicOverdue0/64moPlan: Feb 5–Feb 26 | Technical DrawingOverdue0/44moPlan: Jan 19–Feb 25 | Melakukan Design ReviewOverdue0/55moPlan: Feb 2–Feb 3 | Membuat Dxf Cutout / nameplateOverdue0/25moPlan: Feb 5–Feb 5 | Membuat MOP/WIOverdue0/35moPlan: Feb 10–Feb 11 | Membuat MOP/WIOverdue0/35moPlan: Feb 5–Feb 6 | Membuat SOPOverdue0/45moPlan: Feb 11–Feb 11 | Permintaan Customer VisitOverdue0/25moPlan: Feb 3–Feb 3 | Membuat Form FAT, ATP, SATOverdue0/35moPlan: Feb 11–Feb 11 | Membuat Form FAT, Onsite, SATOverdue0/25moPlan: Feb 6–Feb 6 | Membuat MOP/WIOverdue0/25moPlan: Feb 3–Feb 4 | Melakukan Design ReviewOverdue0/25moPlan: Feb 6–Feb 9 | Membuat Materi TrainingOverdue0/25moPlan: Feb 4–Feb 4 | Membuat Materi TrainingOverdue0/45moPlan: Feb 11–Feb 12 | Membuat Materi TrainingOverdue0/25moPlan: Feb 6–Feb 9 | Permintaan Customer VisitOverdue0/35moPlan: Feb 12–Feb 12 | Permintaan Customer VisitOverdue0/25moPlan: Feb 9–Feb 9 | - | - | - | - | 5mo |
| PANEL MCC FIXEDProduct OnlyDeadline: Sep 13, 20220/23 aktivitas selesai | Aproval DrawOverdue0/846moPlan: Sep 16–Sep 21 | BOQOverdue0/846moPlan: Sep 14–Sep 20 | GAOverdue0/546moPlan: Sep 13–Sep 15 | FEPOverdue0/846moPlan: Sep 14–Sep 19 | SLDOverdue0/246moPlan: Sep 13–Sep 14 | TD PKBOverdue0/846moPlan: Sep 14–Sep 20 | PROGRAMOverdue2/846moPlan: Sep 14–Sep 19Actual: Sep 19 | SchematicsOverdue1/546moPlan: Sep 14–Sep 15Actual: Oct 13 | TD WeldOverdue0/846moPlan: Sep 15–Sep 20 | BOQ LIst Elec_LVOverdue1/546moPlan: Sep 14–Sep 15Actual: Oct 13 | TD AssyOverdue0/846moPlan: Sep 15–Sep 20 | WiringList x TubingOverdue0/346moPlan: Sep 15–Sep 15 | (aktivitas)Overdue0/146moPlan: Sep 15–Sep 15 | 3D BusbarOverdue0/846moPlan: Sep 15–Sep 21 | Bom List ElectricalOverdue1/546moPlan: Sep 15–Sep 16Actual: Oct 17 | CUT OUTOverdue0/346moPlan: Sep 15–Sep 15 | 3D AssyOverdue0/846moPlan: Sep 16–Sep 21 | Preare DOc Operation (ATP,MOP,EOP;etc)Overdue1/546moPlan: Sep 13–Sep 16Actual: Oct 19 | Design ReviewOverdue1/546moPlan: Sep 15–Sep 16Actual: Oct 17 | OthersOverdue0/346moPlan: Sep 16–Sep 16 | TD VLispOverdue0/846moPlan: Sep 13–Sep 21 | OthersOverdue0/846moPlan: Sep 15–Sep 21 | (aktivitas)Overdue0/646moPlan: Sep 16–Sep 21 | - | - | - | - | - | 46mo |
| Shimizu - Loadbank IRISProduct + InstalasiDeadline: Feb 22, 20261/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Feb 22–Feb 22 | Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 20–Nov 20 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/18moPlan: Nov 17–Nov 17 | Membuat BomlistOverdue0/18moPlan: Nov 12–Nov 13 | Membuat BomlistOverdue0/18moPlan: Nov 17–Nov 18 | Membuat Timeline instalasiOverdue0/38moPlan: Nov 13–Nov 16 | Membuat BomlistDone1/1Plan: Nov 16–Nov 17Actual: Nov 13 | Membuat SchematicOverdue0/18moPlan: Nov 18–Nov 18 | Technical DrawingOverdue0/18moPlan: Nov 16–Nov 16 | Vlisp Technical Drawing Overdue0/18moPlan: Nov 13–Nov 13 | Melakukan Design ReviewOverdue0/18moPlan: Nov 16–Nov 17 | Membuat Dxf Cutout / nameplateOverdue0/18moPlan: Nov 18–Nov 19 | Membuat MOP/WIOverdue0/18moPlan: Nov 17–Nov 17 | TD BusbarOverdue0/18moPlan: Nov 13–Nov 13 | 3D design Overdue0/18moPlan: Nov 13–Nov 16 | Membuat MOP/WIOverdue0/18moPlan: Nov 19–Nov 19 | Membuat SOPOverdue0/18moPlan: Nov 17–Nov 18 | Permintaan Customer VisitOverdue0/18moPlan: Nov 17–Nov 17 | Membuat Form FAT, ATP, SATOverdue0/18moPlan: Nov 18–Nov 18 | Membuat Form FAT, Onsite, SATOverdue0/38moPlan: Nov 19–Nov 19 | Melakukan Design ReviewOverdue0/18moPlan: Nov 19–Nov 20 | Membuat Materi TrainingOverdue0/18moPlan: Nov 18–Nov 18 | TD BusbarOverdue0/18moPlan: Nov 16–Nov 16 | Membuat Materi TrainingOverdue0/18moPlan: Nov 20–Nov 20 | - | - | - | - | 8mo |
| PT Telin - Instalasi CLS PluitProduct + InstalasiDeadline: Feb 26, 20261/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Feb 16–Feb 17 | Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Feb 24–Feb 25 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 19–Feb 20 | Membuat BomlistOverdue0/15moPlan: Feb 20–Feb 20 | Membuat BomlistDone1/1Plan: Feb 17–Feb 17Actual: Feb 11 | Membuat Timeline instalasiOverdue0/14moPlan: Feb 25–Feb 25 | Membuat BomlistOverdue0/14moPlan: Feb 25–Feb 26 | Membuat SchematicOverdue0/15moPlan: Feb 20–Feb 20 | Technical DrawingOverdue0/15moPlan: Feb 17–Feb 18 | Melakukan Design ReviewOverdue0/15moPlan: Feb 18–Feb 18 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 20–Feb 23 | Membuat MOP/WIOverdue0/14moPlan: Feb 26–Feb 26 | Membuat MOP/WIOverdue0/15moPlan: Feb 23–Feb 23 | Membuat SOPOverdue0/14moPlan: Feb 26–Feb 26 | Permintaan Customer VisitOverdue0/15moPlan: Feb 18–Feb 19 | Membuat Form FAT, ATP, SATOverdue0/14moPlan: Feb 26–Feb 27 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 23–Feb 23 | Membuat MOP/WIOverdue0/15moPlan: Feb 19–Feb 19 | Melakukan Design ReviewOverdue0/14moPlan: Feb 23–Feb 24 | Membuat Materi TrainingOverdue0/15moPlan: Feb 19–Feb 19 | Membuat Materi TrainingOverdue0/14moPlan: Feb 27–Feb 27 | Membuat Materi TrainingOverdue0/14moPlan: Feb 24–Feb 24 | Permintaan Customer VisitOverdue0/14moPlan: Feb 27–Feb 27 | Permintaan Customer VisitOverdue0/14moPlan: Feb 24–Feb 24 | - | - | - | - | 5mo |
| Internal - Micro Data Centre EatonProduct + InstalasiDeadline: Jan 23, 20262/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/16moPlan: Dec 29–Dec 29 | Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Jan 8–Jan 8 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/16moPlan: Jan 3–Jan 3 | Membuat BomlistOverdue0/16moPlan: Dec 29–Jan 1 | Membuat BomlistDone1/11dPlan: Jan 4–Jan 4Actual: Jan 5 | Membuat Timeline instalasiOverdue0/16moPlan: Jan 8–Jan 9 | Membuat BomlistOverdue0/26moPlan: Jan 9–Jan 9 | Membuat SchematicDone1/11dPlan: Jan 4–Jan 4Actual: Jan 5 | Technical DrawingOverdue0/26moPlan: Jan 1–Jan 1 | Melakukan Design ReviewOverdue0/16moPlan: Jan 1–Jan 2 | Membuat Dxf Cutout / nameplateOverdue0/16moPlan: Jan 4–Jan 4 | Membuat MOP/WIOverdue0/16moPlan: Jan 9–Jan 10 | Membuat MOP/WIOverdue0/16moPlan: Jan 4–Jan 5 | Membuat SOPOverdue0/16moPlan: Jan 10–Jan 10 | Permintaan Customer VisitOverdue0/16moPlan: Jan 2–Jan 2 | Membuat Form FAT, ATP, SATOverdue0/16moPlan: Jan 10–Jan 10 | Membuat Form FAT, Onsite, SATOverdue0/16moPlan: Jan 5–Jan 5 | Membuat MOP/WIOverdue0/16moPlan: Jan 2–Jan 3 | Melakukan Design ReviewOverdue0/16moPlan: Jan 5–Jan 5 | Membuat Materi TrainingOverdue0/16moPlan: Jan 3–Jan 3 | Membuat Materi TrainingOverdue0/26moPlan: Jan 10–Jan 11 | Membuat Materi TrainingOverdue0/16moPlan: Jan 5–Jan 8 | Permintaan Customer VisitOverdue0/16moPlan: Jan 11–Jan 11 | Permintaan Customer VisitOverdue0/16moPlan: Jan 8–Jan 8 | - | - | - | - | 6mo |
| Internal - Mini Data Center Rack (MDCR) from ScheneiderProduct + InstalasiDeadline: Mar 27, 20262/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/15moPlan: Feb 2–Feb 5 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Feb 12–Feb 12 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 7–Feb 8 | Membuat BomlistDone1/12moPlan: Feb 5–Feb 5Actual: Apr 17 | Membuat BomlistDone1/11moPlan: Feb 8–Feb 8Actual: Mar 16 | Membuat Timeline instalasiOverdue0/15moPlan: Feb 12–Feb 13 | Membuat BomlistOverdue0/15moPlan: Feb 13–Feb 13 | Membuat SchematicOverdue0/15moPlan: Feb 8–Feb 8 | Technical DrawingOverdue0/15moPlan: Feb 5–Feb 6 | Melakukan Design ReviewOverdue0/15moPlan: Feb 6–Feb 6 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Feb 8–Feb 8 | Membuat MOP/WIOverdue0/15moPlan: Feb 13–Feb 14 | Membuat MOP/WIOverdue0/15moPlan: Feb 8–Feb 9 | Membuat SOPOverdue0/15moPlan: Feb 14–Feb 14 | Permintaan Customer VisitOverdue0/15moPlan: Feb 6–Feb 6 | Membuat Form FAT, ATP, SATOverdue0/25moPlan: Feb 14–Feb 14 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Feb 9–Feb 9 | Membuat MOP/WIOverdue0/15moPlan: Feb 6–Feb 7 | Melakukan Design ReviewOverdue0/15moPlan: Feb 9–Feb 12 | Membuat Materi TrainingOverdue0/15moPlan: Feb 7–Feb 7 | Membuat Materi TrainingOverdue0/15moPlan: Feb 14–Feb 15 | Membuat Materi TrainingOverdue0/15moPlan: Feb 9–Feb 12 | Permintaan Customer VisitOverdue0/15moPlan: Feb 15–Feb 15 | Permintaan Customer VisitOverdue0/15moPlan: Feb 12–Feb 12 | - | - | - | - | 5mo |
| Mock Up - PT. Enerkomp Persada Raya Panel Soft Starter 250KWProduct + InstalasiDeadline: Mar 31, 20262/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/17moPlan: Dec 16–Dec 16 | Membuat Approval Drawing GA-SLDOverdue0/27moPlan: Dec 24–Dec 24 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/17moPlan: Dec 19–Dec 19 | Membuat BomlistDone1/1Plan: Dec 17–Dec 17Actual: Dec 4 | Membuat BomlistDone1/1Plan: Dec 22–Dec 22Actual: Dec 4 | Membuat Timeline instalasiOverdue0/17moPlan: Dec 24–Dec 25 | Membuat BomlistOverdue0/27moPlan: Dec 25–Dec 25 | Membuat SchematicOverdue1/37moPlan: Dec 22–Dec 23Actual: Dec 4 | Technical DrawingOverdue0/17moPlan: Dec 17–Dec 17 | Melakukan Design ReviewOverdue1/37moPlan: Dec 17–Dec 18Actual: Dec 16 | Membuat Dxf Cutout / nameplateOverdue0/17moPlan: Dec 22–Dec 23 | Membuat MOP/WIOverdue0/16moPlan: Dec 25–Dec 26 | Membuat MOP/WIOverdue0/17moPlan: Dec 23–Dec 23 | Membuat SOPOverdue0/16moPlan: Dec 26–Dec 26 | Permintaan Customer VisitOverdue0/17moPlan: Dec 18–Dec 18 | Membuat Form FAT, ATP, SATOverdue0/26moPlan: Dec 26–Dec 29 | Membuat Form FAT, Onsite, SATOverdue0/17moPlan: Dec 23–Dec 23 | Membuat MOP/WIOverdue0/17moPlan: Dec 18–Dec 19 | Melakukan Design ReviewOverdue0/27moPlan: Dec 23–Dec 24 | Membuat Materi TrainingOverdue0/17moPlan: Dec 19–Dec 19 | Membuat Materi TrainingOverdue0/16moPlan: Dec 29–Dec 29 | Membuat Materi TrainingOverdue0/17moPlan: Dec 24–Dec 24 | Permintaan Customer VisitOverdue0/16moPlan: Dec 29–Dec 29 | Permintaan Customer VisitOverdue0/27moPlan: Dec 24–Dec 24 | - | - | - | - | 7mo |
| Internal - Smart rPDUProduct + InstalasiDeadline: Apr 30, 20262/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/25moPlan: Jan 16–Jan 26 | Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Jan 23–Jan 23 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/16moPlan: Jan 21–Jan 21 | Membuat BomlistOverdue0/25moPlan: Jan 16–Jan 28 | Membuat BomlistDone1/1Plan: Jan 28–Jan 29Actual: Jan 29 | Membuat Timeline instalasiOverdue0/16moPlan: Jan 23–Jan 24 | Membuat BomlistOverdue0/16moPlan: Jan 24–Jan 24 | Membuat SchematicDone1/1Plan: Jan 26–Jan 28Actual: Jan 28 | Technical DrawingOverdue0/16moPlan: Jan 19–Jan 19 | Melakukan Design ReviewOverdue0/25moPlan: Jan 19–Jan 26 | Membuat Dxf Cutout / nameplateOverdue0/16moPlan: Jan 19–Jan 19 | Membuat MOP/WIOverdue0/15moPlan: Jan 24–Jan 25 | Membuat MOP/WIOverdue0/16moPlan: Jan 19–Jan 20 | Membuat SOPOverdue0/15moPlan: Jan 25–Jan 25 | Permintaan Customer VisitOverdue0/16moPlan: Jan 20–Jan 20 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Jan 25–Jan 25 | Membuat Form FAT, Onsite, SATOverdue0/26moPlan: Jan 20–Jan 20 | Membuat MOP/WIOverdue0/36moPlan: Jan 20–Jan 21 | Melakukan Design ReviewOverdue0/26moPlan: Jan 20–Jan 20 | Membuat Materi TrainingOverdue0/16moPlan: Jan 21–Jan 21 | Membuat Materi TrainingOverdue0/15moPlan: Jan 25–Jan 26 | Membuat Materi TrainingOverdue0/16moPlan: Jan 20–Jan 23 | Permintaan Customer VisitOverdue0/15moPlan: Jan 26–Jan 26 | Permintaan Customer VisitOverdue0/16moPlan: Jan 23–Jan 23 | - | - | - | - | 6mo |
| Pembuatan Robot AGVProduct + InstalasiDeadline: Jul 24, 20262/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/16moPlan: Jan 20–Jan 20 | Membuat Approval Drawing GA-SLDOverdue0/15moPlan: Jan 28–Jan 28 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/16moPlan: Jan 23–Jan 23 | Membuat BomlistDone1/1Plan: Jan 21–Jan 21Actual: Jan 21 | Membuat BomlistDone1/12wPlan: Jan 26–Jan 26Actual: Feb 12 | Membuat Timeline instalasiOverdue0/15moPlan: Jan 28–Jan 29 | Membuat BomlistOverdue0/15moPlan: Jan 29–Jan 29 | Membuat SchematicOverdue0/15moPlan: Jan 26–Jan 26 | Technical DrawingOverdue0/16moPlan: Jan 21–Jan 21 | Melakukan Design ReviewOverdue0/16moPlan: Jan 21–Jan 22 | Membuat Dxf Cutout / nameplateOverdue0/15moPlan: Jan 26–Jan 26 | Membuat MOP/WIOverdue0/15moPlan: Jan 29–Jan 30 | Membuat MOP/WIOverdue0/15moPlan: Jan 26–Jan 27 | Membuat SOPOverdue0/15moPlan: Jan 30–Jan 30 | Permintaan Customer VisitOverdue0/16moPlan: Jan 22–Jan 22 | Membuat Form FAT, ATP, SATOverdue0/15moPlan: Jan 30–Jan 30 | Membuat Form FAT, Onsite, SATOverdue0/15moPlan: Jan 27–Jan 27 | Membuat MOP/WIOverdue0/16moPlan: Jan 22–Jan 23 | Melakukan Design ReviewOverdue0/15moPlan: Jan 27–Jan 27 | Membuat Materi TrainingOverdue0/16moPlan: Jan 23–Jan 23 | Membuat Materi TrainingOverdue0/15moPlan: Jan 30–Feb 2 | Membuat Materi TrainingOverdue0/15moPlan: Jan 27–Jan 28 | Permintaan Customer VisitOverdue0/25moPlan: Feb 2–Feb 2 | Permintaan Customer VisitOverdue0/25moPlan: Jan 28–Jan 28 | - | - | - | - | 6mo |
| DNA Teknologi Indonesia - Caging System DHIProduct + InstalasiDeadline: Jul 28, 20262/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/13wPlan: Jun 16–Jun 17 | Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 24–Jun 25 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/12wPlan: Jun 19–Jun 22 | Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 22 | Membuat BomlistDone1/16dPlan: Jun 17–Jun 17Actual: Jun 23 | Membuat Timeline instalasiOverdue0/12wPlan: Jun 25–Jun 25 | Membuat BomlistOverdue0/12wPlan: Jun 25–Jun 26 | Membuat SchematicOverdue0/12wPlan: Jun 22–Jun 22 | Technical DrawingDone1/15dPlan: Jun 17–Jun 18Actual: Jun 23 | Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 18 | Membuat Dxf Cutout / nameplateOverdue0/12wPlan: Jun 22–Jun 23 | Membuat MOP/WIOverdue0/12wPlan: Jun 26–Jun 26 | Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23 | Membuat SOPOverdue0/12wPlan: Jun 26–Jun 26 | Permintaan Customer VisitOverdue0/13wPlan: Jun 18–Jun 19 | Membuat Form FAT, ATP, SATOverdue0/11wPlan: Jun 26–Jun 29 | Membuat Form FAT, Onsite, SATOverdue0/12wPlan: Jun 23–Jun 23 | Membuat MOP/WIOverdue0/13wPlan: Jun 19–Jun 19 | Melakukan Design ReviewOverdue0/12wPlan: Jun 23–Jun 24 | Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19 | Membuat Materi TrainingOverdue0/11wPlan: Jun 29–Jun 29 | Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24 | Permintaan Customer VisitOverdue0/11wPlan: Jun 29–Jun 29 | Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24 | - | - | - | - | 3w |
| ENGINEERING OPRASIONAL 2022Product OnlyDeadline: Jun 9, 20220/21 aktivitas selesai | Aproval DrawOverdue0/749moPlan: Jun 17–Jun 17 | BOQOverdue0/749moPlan: Jun 15–Jun 15 | GAOverdue1/750moPlan: Jun 10–Jun 10Actual: Jun 13 | FEPOverdue0/749moPlan: Jun 15–Jun 15 | TD PKBOverdue0/749moPlan: Jun 15–Jun 16 | PROGRAMOverdue0/749moPlan: Jun 15–Jun 15 | SchematicsOverdue0/650moPlan: Jun 10–Jun 10 | TD WeldOverdue0/749moPlan: Jun 16–Jun 16 | BOQ LIst Elec_LVOverdue2/850moPlan: Jun 9–Jun 10Actual: Jun 13 | TD AssyOverdue0/749moPlan: Jun 16–Jun 16 | WiringList x TubingOverdue0/650moPlan: Jun 13–Jun 13 | 3D BusbarOverdue0/749moPlan: Jun 16–Jun 17 | Bom List ElectricalOverdue0/650moPlan: Jun 10–Jun 13 | CUT OUTOverdue0/650moPlan: Jun 13–Jun 13 | 3D AssyOverdue0/749moPlan: Jun 17–Jun 17 | Preare DOc Operation (ATP,MOP,EOP;etc)Overdue1/750moPlan: Jun 14–Jun 14Actual: Jun 13 | Design ReviewOverdue1/750moPlan: Jun 13–Jun 14Actual: Jun 13 | OthersOverdue1/750moPlan: Jun 14–Jun 14Actual: Jun 13 | TD VLispOverdue0/749moPlan: Jun 14–Jun 15 | OthersOverdue0/749moPlan: Jun 16–Jun 16 | (aktivitas)Overdue0/749moPlan: Jun 17–Jun 17 | - | - | - | - | - | - | - | 50mo |
| Siemens - UCC BP TangguhProduct + InstalasiDeadline: May 29, 20263/24 aktivitas selesai | Membuat Approval Drawing GADone1/11moPlan: Feb 17–Feb 18Actual: Apr 3 | Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Feb 25–Feb 26 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/15moPlan: Feb 20–Feb 23 | Membuat BomlistOverdue0/15moPlan: Feb 23–Feb 23 | Membuat BomlistDone1/12moPlan: Feb 18–Feb 18Actual: Apr 8 | Membuat Timeline instalasiOverdue0/14moPlan: Feb 26–Feb 26 | Membuat BomlistOverdue0/14moPlan: Feb 26–Feb 27 | Membuat SchematicOverdue0/15moPlan: Feb 23–Feb 23 | Technical DrawingDone1/13wPlan: Feb 18–Feb 19Actual: Mar 9 | Melakukan Design ReviewOverdue0/15moPlan: Feb 19–Feb 19 | Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Feb 23–Feb 24 | Membuat MOP/WIOverdue0/14moPlan: Feb 27–Feb 27 | Membuat MOP/WIOverdue0/14moPlan: Feb 24–Feb 24 | Membuat SOPOverdue0/14moPlan: Feb 27–Feb 27 | Permintaan Customer VisitOverdue0/15moPlan: Feb 19–Feb 20 | Membuat Form FAT, ATP, SATOverdue0/14moPlan: Feb 27–Mar 2 | Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Feb 24–Feb 24 | Membuat MOP/WIOverdue0/15moPlan: Feb 20–Feb 20 | Melakukan Design ReviewOverdue0/14moPlan: Feb 24–Feb 25 | Membuat Materi TrainingOverdue0/15moPlan: Feb 20–Feb 20 | Membuat Materi TrainingOverdue0/14moPlan: Mar 2–Mar 2 | Membuat Materi TrainingOverdue0/14moPlan: Feb 25–Feb 25 | Permintaan Customer VisitOverdue0/14moPlan: Mar 2–Mar 2 | Permintaan Customer VisitOverdue0/14moPlan: Feb 25–Feb 25 | - | - | - | - | 5mo |
| Hitachi - ACP25035 - GI Satui 150kVProduct + InstalasiDeadline: Jun 19, 20267/28 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Dec 23–Dec 24Actual: Nov 18 | Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Dec 31–Dec 31 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Dec 26–Dec 29Actual: Nov 17 | Membuat BomlistDone1/1Plan: Dec 24–Dec 24Actual: Dec 3 | Membuat BomlistDone1/1Plan: Dec 29–Dec 29Actual: Dec 4 | Membuat Timeline instalasiOverdue0/16moPlan: Dec 31–Jan 1 | Membuat BomlistOverdue0/16moPlan: Jan 1–Jan 1 | Membuat SchematicDone1/1Plan: Dec 29–Dec 30Actual: Dec 11 | Technical DrawingDone1/1Plan: Dec 25–Dec 25Actual: Dec 3 | Vlisp Technical Drawing Overdue0/17moPlan: Nov 26–Nov 26 | Melakukan Design ReviewOverdue0/17moPlan: Dec 25–Dec 25 | Membuat Dxf Cutout / nameplateDone1/1Plan: Dec 30–Dec 30Actual: Nov 17 | Membuat MOP/WIOverdue0/16moPlan: Jan 1–Jan 2 | TD BusbarOverdue0/17moPlan: Nov 26–Nov 27 | 3D design Overdue0/17moPlan: Nov 27–Nov 27 | Membuat MOP/WIOverdue0/16moPlan: Dec 30–Dec 30 | Membuat SOPOverdue0/16moPlan: Jan 2–Jan 2 | Permintaan Customer VisitOverdue0/26moPlan: Dec 26–Dec 26 | Membuat Form FAT, ATP, SATOverdue0/16moPlan: Jan 2–Jan 5 | Membuat Form FAT, Onsite, SATOverdue0/16moPlan: Dec 30–Dec 30 | Membuat MOP/WIOverdue0/16moPlan: Dec 26–Dec 26 | Melakukan Design ReviewOverdue0/26moPlan: Dec 30–Dec 31 | Membuat Materi TrainingOverdue0/16moPlan: Dec 26–Dec 26 | Membuat Materi TrainingOverdue0/16moPlan: Jan 5–Jan 5 | TD BusbarOverdue0/17moPlan: Nov 27–Nov 27 | Membuat Materi TrainingOverdue0/16moPlan: Dec 31–Dec 31 | Permintaan Customer VisitOverdue0/16moPlan: Jan 5–Jan 5 | Permintaan Customer VisitOverdue0/26moPlan: Dec 31–Dec 31 | 7mo |
| Hitachi - ACP25026 - BalonganProduct + InstalasiDeadline: Jul 20, 20267/28 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Nov 17–Nov 18Actual: Oct 23 | Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 25–Nov 25 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Nov 20–Nov 21Actual: Oct 15 | Membuat BomlistDone1/12moPlan: Nov 18–Nov 18Actual: Jan 20 | Membuat BomlistDone1/1Plan: Nov 21–Nov 21Actual: Oct 15 | Membuat Timeline instalasiOverdue0/17moPlan: Nov 25–Nov 26 | Membuat BomlistOverdue0/17moPlan: Nov 26–Nov 26 | Membuat SchematicDone1/12moPlan: Nov 21–Nov 24Actual: Jan 19 | Technical DrawingDone1/12moPlan: Nov 19–Nov 19Actual: Jan 20 | Vlisp Technical Drawing Overdue0/19moPlan: Oct 21–Oct 21 | Melakukan Design ReviewOverdue0/18moPlan: Nov 19–Nov 19 | Membuat Dxf Cutout / nameplateDone1/1Plan: Nov 24–Nov 24Actual: Oct 15 | Membuat MOP/WIOverdue0/17moPlan: Nov 26–Nov 27 | TD BusbarOverdue0/19moPlan: Oct 21–Oct 22 | 3D design Overdue0/19moPlan: Oct 22–Oct 22 | Membuat MOP/WIOverdue0/38moPlan: Nov 24–Nov 24 | Membuat SOPOverdue0/27moPlan: Nov 27–Nov 27 | Permintaan Customer VisitOverdue0/18moPlan: Nov 20–Nov 20 | Membuat Form FAT, ATP, SATOverdue0/27moPlan: Nov 27–Nov 28 | Membuat Form FAT, Onsite, SATOverdue0/28moPlan: Nov 24–Nov 24 | Membuat MOP/WIOverdue0/18moPlan: Nov 20–Nov 20 | Melakukan Design ReviewOverdue0/18moPlan: Nov 24–Nov 25 | Membuat Materi TrainingOverdue0/28moPlan: Nov 20–Nov 20 | Membuat Materi TrainingOverdue0/17moPlan: Nov 28–Nov 28 | TD BusbarOverdue0/19moPlan: Oct 22–Oct 23 | Membuat Materi TrainingOverdue0/18moPlan: Nov 25–Nov 25 | Permintaan Customer VisitOverdue0/27moPlan: Nov 28–Nov 28 | Permintaan Customer VisitOverdue0/18moPlan: Nov 25–Nov 25 | 9mo |
| Ekamas Mora Republik - Open Rack 42U & Rack DCPDU 3U_PO# 174372Product + InstalasiDeadline: Aug 7, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/12wPlan: Jun 25–Jun 26 | Membuat Approval Drawing GA-SLDOverdue0/12dPlan: Jul 3–Jul 6 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/11wPlan: Jun 30–Jul 1 | Membuat BomlistOverdue0/12wPlan: Jun 26–Jun 26 | Membuat BomlistOverdue0/11wPlan: Jul 1–Jul 1 | Membuat Timeline instalasiOverdue0/12dPlan: Jul 6–Jul 6 | Membuat BomlistOverdue0/11dPlan: Jul 6–Jul 7 | Membuat SchematicOverdue0/11wPlan: Jul 1–Jul 1 | Technical DrawingOverdue0/11wPlan: Jun 26–Jun 29 | Melakukan Design ReviewOverdue0/11wPlan: Jun 29–Jun 29 | Membuat Dxf Cutout / nameplateOverdue0/16dPlan: Jul 1–Jul 2 | Membuat MOP/WIOverdue0/11dPlan: Jul 7–Jul 7 | Membuat MOP/WIOverdue0/16dPlan: Jul 2–Jul 2 | Membuat SOPOverdue0/11dPlan: Jul 7–Jul 7 | Permintaan Customer VisitOverdue0/11wPlan: Jun 29–Jun 30 | Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 7–Jul 8 | Membuat Form FAT, Onsite, SATOverdue0/16dPlan: Jul 2–Jul 2 | Membuat MOP/WIOverdue0/11wPlan: Jun 30–Jun 30 | Melakukan Design ReviewOverdue0/15dPlan: Jul 2–Jul 3 | Membuat Materi TrainingOverdue0/11wPlan: Jun 30–Jun 30 | Membuat Materi TrainingOn Progress0/1Plan: Jul 8–Jul 8 | Membuat Materi TrainingOverdue0/15dPlan: Jul 3–Jul 3 | Permintaan Customer VisitOn Progress0/1Plan: Jul 8–Jul 8 | Permintaan Customer VisitOverdue0/15dPlan: Jul 3–Jul 3 | - | - | - | - | 2w |
| Internal - MDCC 20 Feet POD Phase 2/IP65Product + InstalasiDeadline: Jun 30, 20264/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/17moPlan: Dec 23–Dec 23 | Membuat Approval Drawing GA-SLDOverdue0/13moPlan: Apr 3–Apr 3 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/13moPlan: Mar 31–Mar 31 | Membuat BomlistDone1/1Plan: Nov 11–Nov 11Actual: Nov 11 | Membuat BomlistDone1/1Plan: Apr 1–Apr 1Actual: Mar 9 | Membuat Timeline instalasiOverdue0/13moPlan: Apr 3–Apr 6 | Membuat BomlistOverdue0/13moPlan: Apr 6–Apr 6 | Membuat SchematicDone1/1Plan: Apr 1–Apr 1Actual: Mar 9 | Technical DrawingOverdue0/28moPlan: Nov 11–Nov 11 | Melakukan Design ReviewDone1/1Plan: Mar 30–Mar 30Actual: Mar 2 | Membuat Dxf Cutout / nameplateOverdue0/13moPlan: Apr 1–Apr 1 | Membuat MOP/WIOverdue0/13moPlan: Apr 6–Apr 7 | Membuat MOP/WIOverdue0/13moPlan: Apr 1–Apr 2 | Membuat SOPOverdue0/13moPlan: Apr 7–Apr 7 | Permintaan Customer VisitOverdue0/23moPlan: Mar 30–Mar 30 | Membuat Form FAT, ATP, SATOverdue0/13moPlan: Apr 7–Apr 7 | Membuat Form FAT, Onsite, SATOverdue0/13moPlan: Apr 2–Apr 2 | Membuat MOP/WIOverdue0/13moPlan: Mar 30–Mar 31 | Melakukan Design ReviewOverdue1/33moPlan: Apr 2–Apr 3Actual: Mar 2 | Membuat Materi TrainingOverdue0/13moPlan: Mar 31–Mar 31 | Membuat Materi TrainingOverdue0/13moPlan: Apr 7–Apr 8 | Membuat Materi TrainingOverdue0/13moPlan: Apr 2–Apr 3 | Permintaan Customer VisitOverdue0/13moPlan: Apr 8–Apr 8 | Permintaan Customer VisitOverdue0/13moPlan: Apr 3–Apr 3 | - | - | - | - | 8mo |
| Wholesale - Panel DB - Dermaga BiakProduct + InstalasiDeadline: Jun 30, 20264/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/11moPlan: May 22–May 25 | Membuat Approval Drawing GA-SLDOverdue0/11moPlan: Jun 1–Jun 2 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: May 27–May 28Actual: May 13 | Membuat BomlistOverdue0/11moPlan: May 25–May 25 | Membuat BomlistDone1/11moPlan: May 28–May 28Actual: Jul 2 | Membuat Timeline instalasiOverdue0/11moPlan: Jun 2–Jun 2 | Membuat BomlistOverdue0/11moPlan: Jun 2–Jun 3 | Membuat SchematicDone1/11moPlan: May 28–May 28Actual: Jul 2 | Technical DrawingOverdue0/11moPlan: May 25–May 26 | Melakukan Design ReviewOverdue0/11moPlan: May 26–May 26 | Membuat Dxf Cutout / nameplateOverdue0/11moPlan: May 28–May 29 | Membuat MOP/WIOverdue0/11moPlan: Jun 3–Jun 3 | Membuat MOP/WIOverdue0/11moPlan: May 29–May 29 | Membuat SOPOverdue0/11moPlan: Jun 3–Jun 3 | Permintaan Customer VisitOverdue0/11moPlan: May 26–May 27 | Membuat Form FAT, ATP, SATOverdue0/11moPlan: Jun 3–Jun 4 | Membuat Form FAT, Onsite, SATDone1/11moPlan: May 29–May 29Actual: Jul 7 | Membuat MOP/WIOverdue0/11moPlan: May 27–May 27 | Melakukan Design ReviewOverdue0/11moPlan: May 29–Jun 1 | Membuat Materi TrainingOverdue0/11moPlan: May 27–May 27 | Membuat Materi TrainingOverdue0/11moPlan: Jun 4–Jun 4 | Membuat Materi TrainingOverdue0/11moPlan: Jun 1–Jun 1 | Permintaan Customer VisitOverdue0/11moPlan: Jun 4–Jun 4 | Permintaan Customer VisitOverdue0/11moPlan: Jun 1–Jun 1 | - | - | - | - | 1mo |
| PT. NexWave_Panel TXDP & SDP AC_PO25090188Product + InstalasiDeadline: Jul 3, 20264/24 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Mar 30–Mar 31Actual: Mar 31 | Membuat Approval Drawing GA-SLDOverdue0/13moPlan: Apr 3–Apr 3 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Mar 31–Apr 1Actual: Mar 31 | Membuat BomlistDone1/1Plan: Apr 1–Apr 1Actual: Apr 1 | Membuat BomlistDone1/1Plan: Apr 1–Apr 1Actual: Apr 1 | Membuat Timeline instalasiOverdue0/13moPlan: Apr 3–Apr 6 | Membuat BomlistOverdue0/23moPlan: Apr 6–Apr 6 | Membuat SchematicOverdue0/23moPlan: Apr 1–Apr 1 | Technical DrawingOverdue0/13moPlan: Apr 1–Apr 1 | Melakukan Design ReviewOverdue1/63moPlan: Apr 1–Apr 9Actual: Apr 9 | Membuat Dxf Cutout / nameplateOverdue0/13moPlan: Apr 1–Apr 1 | Membuat MOP/WIOverdue0/13moPlan: Apr 6–Apr 7 | Membuat MOP/WIOverdue0/13moPlan: Apr 1–Apr 2 | Membuat SOPOverdue0/23moPlan: Apr 7–Apr 7 | Permintaan Customer VisitOverdue0/13moPlan: Apr 9–Apr 9 | Membuat Form FAT, ATP, SATOverdue0/13moPlan: Apr 7–Apr 7 | Membuat Form FAT, Onsite, SATOverdue0/23moPlan: Apr 2–Apr 2 | Membuat MOP/WIOverdue0/13moPlan: Apr 9–Apr 10 | Melakukan Design ReviewOverdue0/13moPlan: Apr 2–Apr 2 | Membuat Materi TrainingOverdue0/13moPlan: Apr 7–Apr 8 | Membuat Materi TrainingOverdue0/13moPlan: Apr 10–Apr 10 | Membuat Materi TrainingOverdue0/13moPlan: Apr 2–Apr 3 | Permintaan Customer VisitOverdue0/23moPlan: Apr 8–Apr 8 | Permintaan Customer VisitOverdue0/63moPlan: Apr 3–Apr 3 | - | - | - | - | 3mo |
| Inti Bumi Mas - Panel FeederProduct + InstalasiDeadline: Jul 22, 20264/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/14moPlan: Mar 4–Mar 4 | Membuat Approval Drawing GA-SLDOverdue0/14moPlan: Mar 13–Mar 16 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/14moPlan: Mar 4–Mar 4 | Membuat BomlistDone1/11moPlan: Mar 6–Mar 6Actual: Apr 7 | Membuat BomlistDone1/12wPlan: Mar 11–Mar 11Actual: Mar 27 | Membuat Timeline instalasiOverdue0/14moPlan: Mar 16–Mar 16 | Membuat BomlistOverdue0/14moPlan: Mar 16–Mar 17 | Membuat SchematicDone1/1Plan: Mar 11–Mar 11Actual: Mar 27 | Technical DrawingDone1/14wPlan: Mar 6–Mar 9Actual: Apr 7 | Melakukan Design ReviewOverdue0/14moPlan: Mar 9–Mar 9 | Membuat Dxf Cutout / nameplateOverdue0/14moPlan: Mar 11–Mar 12 | Membuat MOP/WIOverdue0/14moPlan: Mar 17–Mar 17 | Membuat MOP/WIOverdue0/14moPlan: Mar 12–Mar 12 | Membuat SOPOverdue0/14moPlan: Mar 17–Mar 17 | Permintaan Customer VisitOverdue0/14moPlan: Mar 9–Mar 10 | Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 17–Mar 18 | Membuat Form FAT, Onsite, SATOverdue0/14moPlan: Mar 12–Mar 12 | Membuat MOP/WIOverdue0/14moPlan: Mar 10–Mar 10 | Melakukan Design ReviewOverdue0/14moPlan: Mar 12–Mar 13 | Membuat Materi TrainingOverdue0/14moPlan: Mar 10–Mar 10 | Membuat Materi TrainingOverdue0/14moPlan: Mar 18–Mar 18 | Membuat Materi TrainingOverdue0/14moPlan: Mar 13–Mar 13 | Permintaan Customer VisitOverdue0/14moPlan: Mar 18–Mar 18 | Permintaan Customer VisitOverdue0/14moPlan: Mar 13–Mar 13 | - | - | - | - | 4mo |
| PROGRAM CNC, LASER & LVDProduct OnlyDeadline: Sep 7, 20220/19 aktivitas selesai | Aproval DrawOverdue0/3846moPlan: Sep 7–Sep 15 | BOQOverdue0/3846moPlan: Sep 8–Sep 14 | GAOverdue0/147moPlan: Sep 8–Sep 8 | FEPOverdue0/3846moPlan: Sep 8–Sep 13 | SLDOverdue0/147moPlan: Sep 7–Sep 8 | TD PKBOverdue0/3846moPlan: Sep 8–Sep 14 | PROGRAMOverdue1/3846moPlan: Sep 8–Sep 13Actual: Sep 20 | SchematicsOverdue0/147moPlan: Sep 8–Sep 9 | TD WeldOverdue0/3846moPlan: Sep 9–Sep 14 | BOQ LIst Elec_LVOverdue0/147moPlan: Sep 9–Sep 9 | TD AssyOverdue0/3846moPlan: Sep 9–Sep 14 | 3D BusbarOverdue0/3846moPlan: Sep 9–Sep 15 | Bom List ElectricalOverdue0/147moPlan: Sep 12–Sep 12 | 3D AssyOverdue0/3846moPlan: Sep 12–Sep 15 | Preare DOc Operation (ATP,MOP,EOP;etc)Overdue0/147moPlan: Sep 9–Sep 12 | Design ReviewOverdue0/147moPlan: Sep 12–Sep 12 | TD VLispOverdue0/3846moPlan: Sep 7–Sep 13 | OthersOverdue0/3846moPlan: Sep 9–Sep 15 | (aktivitas)Overdue0/147moPlan: Sep 12–Sep 12 | - | - | - | - | - | - | - | - | - | 47mo |
| GSPE_Smart Rack (Micro Data Center)Product + InstalasiDeadline: Apr 6, 20265/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/28moPlan: Nov 24–Nov 24 | Membuat Approval Drawing GA-SLDOverdue0/16moPlan: Jan 20–Jan 20 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jan 17–Jan 18Actual: Dec 11 | Membuat BomlistDone1/1Plan: Jan 13–Jan 13Actual: Sep 22 | Membuat BomlistDone1/1Plan: Jan 18–Jan 18Actual: Dec 11 | Membuat Timeline instalasiOverdue0/26moPlan: Jan 20–Jan 21 | Membuat BomlistOverdue0/16moPlan: Jan 21–Jan 21 | Membuat SchematicDone1/1Plan: Jan 18–Jan 18Actual: Dec 11 | Technical DrawingOverdue0/16moPlan: Jan 13–Jan 13 | Melakukan Design ReviewDone1/13wPlan: Jan 14–Jan 14Actual: Feb 4 | Membuat Dxf Cutout / nameplateOverdue0/16moPlan: Jan 18–Jan 18 | Membuat MOP/WIOverdue0/16moPlan: Jan 21–Jan 24 | Membuat MOP/WIOverdue0/16moPlan: Jan 18–Jan 19 | Membuat SOPOverdue0/16moPlan: Jan 24–Jan 24 | Permintaan Customer VisitOverdue0/16moPlan: Jan 14–Jan 14 | Membuat Form FAT, ATP, SATOverdue0/16moPlan: Jan 24–Jan 24 | Membuat Form FAT, Onsite, SATOverdue0/16moPlan: Jan 19–Jan 19 | Membuat MOP/WIOverdue0/16moPlan: Jan 14–Jan 17 | Melakukan Design ReviewOverdue0/16moPlan: Jan 19–Jan 19 | Membuat Materi TrainingOverdue0/16moPlan: Jan 17–Jan 17 | Membuat Materi TrainingOverdue0/15moPlan: Jan 24–Jan 25 | Membuat Materi TrainingOverdue0/16moPlan: Jan 19–Jan 20 | Permintaan Customer VisitOverdue0/15moPlan: Jan 25–Jan 25 | Permintaan Customer VisitOverdue0/16moPlan: Jan 20–Jan 20 | - | - | - | - | 8mo |
| Mega Akses - Omadata SurabayaProduct + InstalasiDeadline: Jul 31, 20265/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/12moPlan: May 4–May 4 | Membuat Approval Drawing GA-SLDDone1/1Plan: May 12–May 13Actual: Apr 23 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/12moPlan: May 7–May 7 | Membuat BomlistOverdue0/12moPlan: May 4–May 5 | Membuat BomlistOverdue0/12moPlan: May 7–May 8 | Membuat Timeline instalasiDone1/1Plan: May 13–May 13Actual: Apr 23 | Membuat BomlistDone1/1Plan: May 13–May 14Actual: Apr 23 | Membuat SchematicOverdue0/12moPlan: May 8–May 8 | Technical DrawingOverdue0/12moPlan: May 5–May 5 | Melakukan Design ReviewOverdue0/12moPlan: May 5–May 6 | Membuat Dxf Cutout / nameplateOverdue0/12moPlan: May 8–May 8 | Membuat MOP/WIDone1/1Plan: May 14–May 14Actual: Apr 23 | Membuat MOP/WIOverdue0/12moPlan: May 8–May 11 | Membuat SOPDone1/1Plan: May 14–May 14Actual: Apr 23 | Permintaan Customer VisitOverdue0/12moPlan: May 6–May 6 | Membuat Form FAT, ATP, SATOverdue0/12moPlan: May 14–May 14 | Membuat Form FAT, Onsite, SATOverdue0/12moPlan: May 11–May 11 | Membuat MOP/WIOverdue0/12moPlan: May 6–May 7 | Melakukan Design ReviewOverdue0/12moPlan: May 11–May 11 | Membuat Materi TrainingOverdue0/12moPlan: May 7–May 7 | Membuat Materi TrainingOverdue0/12moPlan: May 14–May 15 | Membuat Materi TrainingOverdue0/12moPlan: May 11–May 12 | Permintaan Customer VisitOverdue0/12moPlan: May 15–May 15 | Permintaan Customer VisitOverdue0/12moPlan: May 12–May 12 | - | - | - | - | 2mo |
| Mega Akses Persada - BDF Power Papahan KaranganyarProduct + InstalasiDeadline: Aug 28, 20265/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/46dPlan: Jul 2–Jul 2 | Membuat Approval Drawing GA-SLDDone1/1Plan: Jun 27–Jun 30Actual: Jun 24 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/12wPlan: Jun 25–Jun 26 | Membuat BomlistOverdue0/12wPlan: Jun 25–Jun 25 | Membuat BomlistOverdue0/35dPlan: Jul 2–Jul 3 | Membuat Timeline instalasiDone1/1Plan: Jun 30–Jun 30Actual: Jun 24 | Membuat BomlistDone1/1Plan: Jun 30–Jul 1Actual: Jun 24 | Membuat SchematicOverdue0/12wPlan: Jun 25–Jun 25 | Technical DrawingOverdue0/15dPlan: Jul 3–Jul 3 | Melakukan Design ReviewOverdue0/12dPlan: Jul 3–Jul 6 | Membuat Dxf Cutout / nameplateOverdue0/12wPlan: Jun 25–Jun 25 | Membuat MOP/WIDone1/1Plan: Jul 1–Jul 1Actual: Jun 24 | Membuat MOP/WIOverdue0/12wPlan: Jun 26–Jun 26 | Membuat SOPDone1/1Plan: Jul 1–Jul 1Actual: Jun 24 | Permintaan Customer VisitOverdue0/12dPlan: Jul 6–Jul 6 | Membuat Form FAT, ATP, SATOverdue0/16dPlan: Jul 1–Jul 2 | Membuat Form FAT, Onsite, SATOverdue0/12wPlan: Jun 26–Jun 26 | Membuat MOP/WIOverdue0/21dPlan: Jul 6–Jul 7 | Melakukan Design ReviewOverdue0/12wPlan: Jun 26–Jun 26 | Membuat Materi TrainingOverdue0/16dPlan: Jul 2–Jul 2 | Membuat Materi TrainingOverdue0/21dPlan: Jul 7–Jul 7 | Membuat Materi TrainingOverdue0/22wPlan: Jun 26–Jun 27 | Permintaan Customer VisitOverdue0/16dPlan: Jul 2–Jul 2 | Permintaan Customer VisitOverdue0/12wPlan: Jun 27–Jun 27 | - | - | - | - | 2w |
| INQUIRY ESTIMATORProduct OnlyDeadline: Oct 12, 20220/18 aktivitas selesai | Draft Cutout ViewOverdue0/145moPlan: Oct 31–Nov 1 | Approval CutoutOverdue0/145moPlan: Nov 1–Nov 2 | Aproval DrawOverdue0/145moPlan: Oct 12–Oct 13 | BOQOverdue0/145moPlan: Oct 13–Oct 14 | BOM HVOverdue0/145moPlan: Nov 2–Nov 3 | FEPOverdue0/145moPlan: Oct 13–Oct 13 | TD PKBOverdue0/145moPlan: Oct 14–Oct 14 | Cutout listOverdue0/145moPlan: Nov 4–Nov 7 | PROGRAMOverdue0/145moPlan: Oct 13–Oct 13 | TD WeldOverdue0/145moPlan: Oct 14–Oct 14 | Wiring ListOverdue0/145moPlan: Nov 3–Nov 3 | Printout SchematicOverdue0/145moPlan: Nov 7–Nov 7 | TD AssyOverdue0/145moPlan: Oct 14–Oct 14 | Tubing ListOverdue0/145moPlan: Nov 3–Nov 4 | 3D BusbarOverdue0/145moPlan: Oct 17–Oct 17 | 3D AssyOverdue0/145moPlan: Oct 17–Oct 17 | TD VLispOverdue0/145moPlan: Oct 17–Oct 17 | OthersOverdue0/145moPlan: Oct 14–Oct 17 | - | - | - | - | - | - | - | - | - | - | 45mo |
| Internal - Contaiment 50 UnitProduct + InstalasiDeadline: Jun 30, 20264/22 aktivitas selesai | Membuat Approval Drawing GA-SLDOverdue0/27moPlan: Dec 1–Dec 1 | Membuat BomlistDone1/1Plan: Nov 11–Dec 30Actual: Dec 30 | Membuat BomlistDone1/1Plan: Jan 5–Jan 5Actual: Jan 5 | Membuat Timeline instalasiOverdue0/17moPlan: Dec 1–Dec 2 | Membuat BomlistOverdue0/17moPlan: Dec 2–Dec 2 | Membuat SchematicDone1/1Plan: Dec 30–Jan 5Actual: Jan 5 | Technical DrawingOverdue0/18moPlan: Nov 24–Nov 24 | Melakukan Design ReviewDone1/1Plan: Dec 29–Dec 29Actual: Dec 29 | Membuat Dxf Cutout / nameplateOverdue0/17moPlan: Nov 27–Nov 27 | Membuat MOP/WIOverdue0/17moPlan: Dec 2–Dec 3 | Membuat MOP/WIOverdue0/17moPlan: Nov 27–Nov 28 | Membuat SOPOverdue0/17moPlan: Dec 3–Dec 3 | Permintaan Customer VisitOverdue0/68moPlan: Nov 25–Nov 25 | Membuat Form FAT, ATP, SATOverdue0/17moPlan: Dec 3–Dec 3 | Membuat Form FAT, Onsite, SATOverdue0/17moPlan: Nov 28–Nov 28 | Membuat MOP/WIOverdue0/17moPlan: Nov 25–Nov 26 | Melakukan Design ReviewOverdue0/17moPlan: Nov 28–Nov 28 | Membuat Materi TrainingOverdue0/27moPlan: Nov 26–Nov 26 | Membuat Materi TrainingOverdue0/27moPlan: Dec 3–Dec 4 | Membuat Materi TrainingOverdue0/17moPlan: Nov 28–Dec 1 | Permintaan Customer VisitOverdue0/17moPlan: Dec 4–Dec 4 | Permintaan Customer VisitOverdue0/17moPlan: Dec 1–Dec 1 | - | - | - | - | - | - | 8mo |
| Hitachi - GI 150kV kruengProduct + InstalasiDeadline: Jul 22, 20267/24 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Jun 11–Jun 12Actual: Jun 10 | Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 16–Jun 17Actual: Jun 10 | Membuat BomlistDone1/1Plan: Jun 12–Jun 12Actual: Jun 12 | Membuat BomlistDone1/1Plan: Jun 17–Jun 17Actual: Jun 10 | Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22 | Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23 | Membuat SchematicDone1/1Plan: Jun 17–Jun 17Actual: Jun 15 | Technical DrawingDone1/1Plan: Jun 12–Jun 15Actual: Jun 12 | Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15 | Membuat Dxf Cutout / nameplateDone1/1Plan: Jun 17–Jun 18Actual: Jun 15 | Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23 | Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18 | Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23 | Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16 | Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24 | Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18 | Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16 | Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19 | Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16 | Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24 | Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19 | Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24 | Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19 | - | - | - | - | 3w |
| Hitachi - ACP25099 - GI 150kV TakengonProduct + InstalasiDeadline: Jul 31, 20267/24 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Jun 11–Jun 12Actual: Jun 10 | Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 16–Jun 17Actual: Jun 10 | Membuat BomlistDone1/1Plan: Jun 12–Jun 12Actual: Jun 12 | Membuat BomlistDone1/1Plan: Jun 17–Jun 17Actual: Jun 12 | Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22 | Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23 | Membuat SchematicDone1/1Plan: Jun 17–Jun 17Actual: Jun 15 | Technical DrawingDone1/1Plan: Jun 12–Jun 15Actual: Jun 12 | Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15 | Membuat Dxf Cutout / nameplateDone1/1Plan: Jun 17–Jun 18Actual: Jun 15 | Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23 | Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18 | Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23 | Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16 | Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24 | Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18 | Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16 | Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19 | Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16 | Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24 | Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19 | Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24 | Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19 | - | - | - | - | 3w |
| Hitachi - GI 150kV SribawonoProduct + InstalasiDeadline: Aug 25, 20267/24 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Jun 11–Jun 12Actual: Jun 10 | Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 16–Jun 17Actual: Jun 10 | Membuat BomlistDone1/1Plan: Jun 12–Jun 12Actual: Jun 12 | Membuat BomlistDone1/11dPlan: Jun 17–Jun 17Actual: Jun 18 | Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22 | Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23 | Membuat SchematicDone1/11dPlan: Jun 17–Jun 17Actual: Jun 18 | Technical DrawingDone1/1Plan: Jun 12–Jun 15Actual: Jun 12 | Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15 | Membuat Dxf Cutout / nameplateDone1/1Plan: Jun 17–Jun 18Actual: Jun 18 | Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23 | Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18 | Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23 | Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16 | Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24 | Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18 | Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16 | Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19 | Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16 | Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24 | Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19 | Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24 | Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19 | - | - | - | - | 3w |
| Hitachi - GI 150kV KolakaProduct + InstalasiDeadline: Aug 28, 20267/24 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Jun 11–Jun 12Actual: Jun 10 | Membuat Approval Drawing GA-SLDOverdue0/12wPlan: Jun 19–Jun 22 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 16–Jun 17Actual: Jun 10 | Membuat BomlistDone1/13wPlan: Jun 12–Jun 12Actual: Jul 3 | Membuat BomlistDone1/11dPlan: Jun 17–Jun 17Actual: Jun 18 | Membuat Timeline instalasiOverdue0/12wPlan: Jun 22–Jun 22 | Membuat BomlistOverdue0/12wPlan: Jun 22–Jun 23 | Membuat SchematicDone1/11dPlan: Jun 17–Jun 17Actual: Jun 18 | Technical DrawingDone1/13wPlan: Jun 12–Jun 15Actual: Jul 3 | Melakukan Design ReviewOverdue0/13wPlan: Jun 15–Jun 15 | Membuat Dxf Cutout / nameplateDone1/1Plan: Jun 17–Jun 18Actual: Jun 18 | Membuat MOP/WIOverdue0/12wPlan: Jun 23–Jun 23 | Membuat MOP/WIOverdue0/13wPlan: Jun 18–Jun 18 | Membuat SOPOverdue0/12wPlan: Jun 23–Jun 23 | Permintaan Customer VisitOverdue0/13wPlan: Jun 15–Jun 16 | Membuat Form FAT, ATP, SATOverdue0/12wPlan: Jun 23–Jun 24 | Membuat Form FAT, Onsite, SATOverdue0/13wPlan: Jun 18–Jun 18 | Membuat MOP/WIOverdue0/13wPlan: Jun 16–Jun 16 | Melakukan Design ReviewOverdue0/13wPlan: Jun 18–Jun 19 | Membuat Materi TrainingOverdue0/13wPlan: Jun 16–Jun 16 | Membuat Materi TrainingOverdue0/12wPlan: Jun 24–Jun 24 | Membuat Materi TrainingOverdue0/13wPlan: Jun 19–Jun 19 | Permintaan Customer VisitOverdue0/12wPlan: Jun 24–Jun 24 | Permintaan Customer VisitOverdue0/13wPlan: Jun 19–Jun 19 | - | - | - | - | 3w |
| Schneider - Panel for PUSRI IIIB Project // E2010-96440Product + InstalasiDeadline: May 26, 202612/28 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Nov 9–Nov 10Actual: Sep 10 | Membuat Approval Drawing GA-SLDOverdue0/18moPlan: Nov 17–Nov 17 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Nov 14–Nov 15Actual: Sep 10 | Membuat BomlistDone1/1Plan: Nov 10–Nov 10Actual: Sep 17 | Membuat BomlistDone1/1Plan: Nov 15–Nov 15Actual: Sep 19 | Membuat Timeline instalasiOverdue0/18moPlan: Nov 17–Nov 20 | Membuat BomlistOverdue0/18moPlan: Nov 20–Nov 20 | Membuat SchematicDone1/1Plan: Nov 15–Nov 16Actual: Oct 10 | Technical DrawingDone1/1Plan: Nov 13–Nov 13Actual: Sep 17 | Vlisp Technical Drawing Done1/1Plan: Oct 10–Oct 10Actual: Sep 17 | Melakukan Design ReviewDone1/1Plan: Nov 14–Nov 14Actual: Sep 22 | Membuat Dxf Cutout / nameplateDone1/1Plan: Nov 16–Nov 16Actual: Sep 11 | Membuat MOP/WIOverdue0/18moPlan: Nov 20–Nov 21 | TD BusbarDone1/1Plan: Oct 10–Oct 13Actual: Sep 17 | 3D design Done1/1Plan: Oct 13–Oct 13Actual: Sep 17 | Membuat MOP/WIOverdue0/18moPlan: Nov 16–Nov 16 | Membuat SOPOverdue0/18moPlan: Nov 21–Nov 21 | Permintaan Customer VisitOverdue0/18moPlan: Nov 14–Nov 14 | Membuat Form FAT, ATP, SATOverdue0/18moPlan: Nov 21–Nov 22 | Membuat Form FAT, Onsite, SATOverdue0/18moPlan: Nov 16–Nov 16 | Membuat MOP/WIOverdue0/18moPlan: Nov 14–Nov 14 | Melakukan Design ReviewOverdue0/18moPlan: Nov 16–Nov 17 | Membuat Materi TrainingOverdue0/18moPlan: Nov 14–Nov 14 | Membuat Materi TrainingOverdue0/18moPlan: Nov 22–Nov 22 | TD BusbarDone1/1Plan: Oct 13–Oct 14Actual: Sep 17 | Membuat Materi TrainingOverdue0/28moPlan: Nov 17–Nov 17 | Permintaan Customer VisitOverdue0/18moPlan: Nov 22–Nov 22 | Permintaan Customer VisitOverdue0/18moPlan: Nov 17–Nov 17 | 8mo |
| Kelinci Mas Unggul - Panel MK Single PhiProduct + InstalasiDeadline: Jun 10, 20268/24 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Apr 30–May 1Actual: Mar 2 | Membuat Approval Drawing GA-SLDOverdue0/12moPlan: May 8–May 11 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: May 5–May 6Actual: Mar 2 | Membuat BomlistDone1/1Plan: May 1–May 1Actual: Mar 4 | Membuat BomlistDone1/1Plan: May 6–May 6Actual: Mar 10 | Membuat Timeline instalasiOverdue0/12moPlan: May 11–May 11 | Membuat BomlistOverdue0/12moPlan: May 11–May 12 | Membuat SchematicDone1/1Plan: May 6–May 6Actual: Mar 9 | Technical DrawingDone1/1Plan: May 1–May 4Actual: Mar 4 | Melakukan Design ReviewDone1/1Plan: May 4–May 4Actual: Mar 2 | Membuat Dxf Cutout / nameplateDone1/1Plan: May 6–May 7Actual: Mar 10 | Membuat MOP/WIOverdue0/12moPlan: May 12–May 12 | Membuat MOP/WIOverdue0/12moPlan: May 7–May 7 | Membuat SOPOverdue0/12moPlan: May 12–May 12 | Permintaan Customer VisitOverdue0/12moPlan: May 4–May 5 | Membuat Form FAT, ATP, SATOverdue0/12moPlan: May 12–May 13 | Membuat Form FAT, Onsite, SATOverdue0/12moPlan: May 7–May 7 | Membuat MOP/WIOverdue0/12moPlan: May 5–May 5 | Melakukan Design ReviewOverdue0/12moPlan: May 7–May 8 | Membuat Materi TrainingOverdue0/12moPlan: May 5–May 5 | Membuat Materi TrainingOverdue0/12moPlan: May 13–May 13 | Membuat Materi TrainingOverdue0/12moPlan: May 8–May 8 | Permintaan Customer VisitOverdue0/12moPlan: May 13–May 13 | Permintaan Customer VisitOverdue0/12moPlan: May 8–May 8 | - | - | - | - | 2mo |
| Hitachi - ACP25085 - Sebuku PLN NPCProduct + InstalasiDeadline: Jul 6, 20268/24 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: May 12–May 12Actual: May 12 | Membuat Approval Drawing GA-SLDOverdue0/11moPlan: May 27–May 27 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: May 6–May 6Actual: May 6 | Membuat BomlistDone1/1Plan: May 18–May 18Actual: May 15 | Membuat BomlistDone1/14dPlan: May 18–May 18Actual: May 22 | Membuat Timeline instalasiOverdue0/11moPlan: May 27–May 28 | Membuat BomlistOverdue0/31moPlan: May 28–May 28 | Membuat SchematicDone1/15dPlan: May 20–May 20Actual: May 25 | Technical DrawingDone1/1Plan: May 18–May 18Actual: May 15 | Melakukan Design ReviewDone1/1Plan: May 18–May 18Actual: May 12 | Membuat Dxf Cutout / nameplateDone1/1Plan: May 18–May 18Actual: May 6 | Membuat MOP/WIOverdue0/11moPlan: May 28–May 29 | Membuat MOP/WIOverdue0/11moPlan: May 25–May 26 | Membuat SOPOverdue0/11moPlan: May 29–May 29 | Permintaan Customer VisitOverdue0/12moPlan: May 21–May 21 | Membuat Form FAT, ATP, SATOverdue0/11moPlan: May 29–May 29 | Membuat Form FAT, Onsite, SATOverdue0/11moPlan: May 26–May 26 | Membuat MOP/WIOverdue0/12moPlan: May 21–May 22 | Melakukan Design ReviewOverdue0/11moPlan: May 26–May 26 | Membuat Materi TrainingOverdue0/12moPlan: May 22–May 22 | Membuat Materi TrainingOverdue0/11moPlan: May 29–Jun 1 | Membuat Materi TrainingOverdue0/11moPlan: May 26–May 27 | Permintaan Customer VisitOverdue0/21moPlan: Jun 1–Jun 1 | Permintaan Customer VisitOverdue0/11moPlan: May 27–May 27 | - | - | - | - | 2mo |
| PT. LTI_PO 26060314_ODC With Aircond 300W (1 Unit)Product + InstalasiDeadline: Jul 22, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/11wPlan: Jun 30–Jul 1 | Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 8–Jul 9 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/12dPlan: Jul 3–Jul 6 | Membuat BomlistOverdue0/11wPlan: Jul 1–Jul 1 | Membuat BomlistOverdue0/12dPlan: Jul 6–Jul 6 | Membuat Timeline instalasiOn Progress0/1Plan: Jul 9–Jul 9 | Membuat BomlistOn Progress0/1Plan: Jul 9–Jul 10 | Membuat SchematicOverdue0/12dPlan: Jul 6–Jul 6 | Technical DrawingOverdue0/16dPlan: Jul 1–Jul 2 | Melakukan Design ReviewOverdue0/16dPlan: Jul 2–Jul 2 | Membuat Dxf Cutout / nameplateOverdue0/11dPlan: Jul 6–Jul 7 | Membuat MOP/WIOn Progress0/1Plan: Jul 10–Jul 10 | Membuat MOP/WIOverdue0/11dPlan: Jul 7–Jul 7 | Membuat SOPOn Progress0/1Plan: Jul 10–Jul 10 | Permintaan Customer VisitOverdue0/15dPlan: Jul 2–Jul 3 | Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 10–Jul 13 | Membuat Form FAT, Onsite, SATOverdue0/11dPlan: Jul 7–Jul 7 | Membuat MOP/WIOverdue0/15dPlan: Jul 3–Jul 3 | Melakukan Design ReviewOn Progress0/1Plan: Jul 7–Jul 8 | Membuat Materi TrainingOverdue0/15dPlan: Jul 3–Jul 3 | Membuat Materi TrainingOn Progress0/1Plan: Jul 13–Jul 13 | Membuat Materi TrainingOn Progress0/1Plan: Jul 8–Jul 8 | Permintaan Customer VisitOn Progress0/1Plan: Jul 13–Jul 13 | Permintaan Customer VisitOn Progress0/1Plan: Jul 8–Jul 8 | - | - | - | - | 1w |
| PROGRAM PUNCHING, LVD, LASERProduct OnlyDeadline: Oct 11, 20220/12 aktivitas selesai | Customer VisitOverdue0/345moPlan: Oct 24–Oct 25 | Aproval DrawOverdue0/1545moPlan: Oct 11–Oct 25 | BOQOverdue0/1545moPlan: Oct 12–Oct 26 | FEPOverdue0/1545moPlan: Oct 12–Oct 25 | TD PKBOverdue0/1545moPlan: Oct 13–Oct 26 | PROGRAMOverdue3/1645moPlan: Oct 12–Oct 26Actual: Oct 24 | TD WeldOverdue0/1545moPlan: Oct 13–Oct 26 | TD AssyOverdue0/1545moPlan: Oct 13–Oct 26 | 3D BusbarOverdue0/1545moPlan: Oct 14–Oct 27 | 3D AssyOverdue0/1545moPlan: Oct 14–Oct 27 | TD VLispOverdue0/1545moPlan: Oct 14–Oct 27 | OthersOverdue0/1545moPlan: Oct 13–Oct 27 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 45mo |
| INTERNAL_DUMMYLOAD BANK 10KVAProduct OnlyDeadline: Oct 14, 20220/12 aktivitas selesai | Aproval DrawOverdue0/246moPlan: Oct 11–Oct 11 | BOQOverdue0/246moPlan: Oct 7–Oct 7 | FEPOverdue0/246moPlan: Oct 7–Oct 7 | TD PKBOverdue0/246moPlan: Oct 7–Oct 10 | PROGRAMOverdue0/246moPlan: Oct 7–Oct 7 | TD WeldOverdue0/246moPlan: Oct 10–Oct 10 | TD AssyOverdue0/246moPlan: Oct 10–Oct 10 | 3D BusbarOverdue0/246moPlan: Oct 10–Oct 11 | 3D AssyOverdue0/246moPlan: Oct 11–Oct 11 | TD VLispOverdue0/246moPlan: Oct 6–Oct 7 | OthersOverdue0/246moPlan: Oct 10–Oct 10 | (aktivitas)Overdue0/246moPlan: Oct 11–Oct 11 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 46mo |
| Forecast - Open Rack, Subrack, BB45UProduct OnlyDeadline: Sep 20, 20240/10 aktivitas selesai | Customer VisitOverdue0/123moPlan: Aug 23–Aug 26 | Aproval DrawOverdue0/123moPlan: Aug 26–Aug 26 | BOQOverdue0/123moPlan: Aug 27–Aug 27 | FEPOverdue0/123moPlan: Aug 26–Aug 27 | TD PKBOverdue0/123moPlan: Aug 27–Aug 28 | TD WeldOverdue0/123moPlan: Aug 28–Aug 28 | TD AssyOverdue0/123moPlan: Aug 28–Aug 29 | 3D BusbarOverdue0/123moPlan: Aug 29–Aug 29 | 3D AssyOverdue0/123moPlan: Aug 29–Aug 30 | TD VLispOverdue0/123moPlan: Aug 30–Aug 30 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 23mo |
| PT Roka Lane Asia - Rack Server 52U DWDM MMRProduct + InstalasiDeadline: Aug 21, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/16dPlan: Jul 1–Jul 2 | Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 9–Jul 10 | Membuat Approval Drawing GA-SLD/cutoutOverdue0/11dPlan: Jul 6–Jul 7 | Membuat BomlistOverdue0/16dPlan: Jul 2–Jul 2 | Membuat BomlistOverdue0/11dPlan: Jul 7–Jul 7 | Membuat Timeline instalasiOn Progress0/1Plan: Jul 10–Jul 10 | Membuat BomlistOn Progress0/1Plan: Jul 10–Jul 13 | Membuat SchematicOverdue0/11dPlan: Jul 7–Jul 7 | Technical DrawingOverdue0/15dPlan: Jul 2–Jul 3 | Melakukan Design ReviewOverdue0/15dPlan: Jul 3–Jul 3 | Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 7–Jul 8 | Membuat MOP/WIOn Progress0/1Plan: Jul 13–Jul 13 | Membuat MOP/WIOn Progress0/1Plan: Jul 8–Jul 8 | Membuat SOPOn Progress0/1Plan: Jul 13–Jul 13 | Permintaan Customer VisitOverdue0/12dPlan: Jul 3–Jul 6 | Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 13–Jul 14 | Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 8–Jul 8 | Membuat MOP/WIOverdue0/12dPlan: Jul 6–Jul 6 | Melakukan Design ReviewOn Progress0/1Plan: Jul 8–Jul 9 | Membuat Materi TrainingOverdue0/12dPlan: Jul 6–Jul 6 | Membuat Materi TrainingOn Progress0/1Plan: Jul 14–Jul 14 | Membuat Materi TrainingOn Progress0/1Plan: Jul 9–Jul 9 | Permintaan Customer VisitOn Progress0/1Plan: Jul 14–Jul 14 | Permintaan Customer VisitOn Progress0/1Plan: Jul 9–Jul 9 | - | - | - | - | 6d |
| ELEC_ HV_SYSTEMProduct OnlyDeadline: Oct 12, 20220/7 aktivitas selesai | Draft Cutout ViewOverdue0/3045moPlan: Oct 12–Oct 19 | Approval CutoutOverdue0/3045moPlan: Oct 13–Oct 20 | BOM HVOverdue0/3045moPlan: Oct 14–Oct 21 | Cutout listOverdue0/3045moPlan: Oct 18–Oct 25 | Wiring ListOverdue0/3045moPlan: Oct 17–Oct 21 | Printout SchematicOverdue0/3045moPlan: Oct 19–Oct 25 | Tubing ListOverdue0/3045moPlan: Oct 17–Oct 24 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 45mo |
| Review Drawing RDMPProduct OnlyDeadline: Oct 13, 20221/8 aktivitas selesai | GADone1/1Plan: Oct 13–Oct 14Actual: Oct 13 | SLDOverdue0/145moPlan: Oct 14–Oct 14 | SchematicsOverdue0/145moPlan: Oct 14–Oct 17 | BOQ LIst Elec_LVOverdue0/145moPlan: Oct 17–Oct 17 | (aktivitas)Overdue0/145moPlan: Oct 17–Oct 17 | Bom List ElectricalOverdue0/145moPlan: Oct 17–Oct 18 | Preare DOc Operation (ATP,MOP,EOP;etc)Overdue0/145moPlan: Oct 18–Oct 18 | Design ReviewOverdue0/145moPlan: Oct 18–Oct 18 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 45mo |
| Schneider Electric - LNGPPProduct + InstalasiDeadline: Apr 30, 20260/7 aktivitas selesai | Membuat Timeline instalasiOverdue0/14moPlan: Mar 19–Mar 20 | Membuat BomlistOverdue0/14moPlan: Mar 20–Mar 20 | Membuat MOP/WIOverdue0/14moPlan: Mar 20–Mar 23 | Membuat SOPOverdue0/14moPlan: Mar 23–Mar 23 | Membuat Form FAT, ATP, SATOverdue0/14moPlan: Mar 23–Mar 23 | Membuat Materi TrainingOverdue0/14moPlan: Mar 23–Mar 24 | Permintaan Customer VisitOverdue0/14moPlan: Mar 24–Mar 24 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 4mo |
| ERCS DCAM - Loadbank PanelProduct + InstalasiDeadline: Aug 24, 20267/17 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Jun 1–Jun 2Actual: May 8 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jun 4–Jun 5Actual: May 5 | Membuat BomlistDone1/16dPlan: Jun 2–Jun 2Actual: Jun 8 | Membuat BomlistDone1/1Plan: Jun 5–Jun 5Actual: May 25 | Membuat Timeline instalasiOn Progress0/1Plan: Jul 1–Jul 17 | Membuat BomlistOn Progress0/1Plan: Jul 1–Jul 17 | Membuat SchematicDone1/1Plan: Jun 5–Jun 5Actual: May 29 | Melakukan Design ReviewDone1/1Plan: Jun 3–Jun 3Actual: Jun 3 | Membuat MOP/WIOn Progress0/1Plan: Jul 1–Jul 10 | Membuat MOP/WIOverdue0/12wPlan: Jun 19–Jun 26 | Membuat SOPOn Progress0/1Plan: Jul 1–Jul 10 | Membuat Form FAT, Onsite, SATDone1/1Plan: Jun 8–Jun 12Actual: Jun 8 | Membuat MOP/WIOverdue0/11moPlan: Jun 4–Jun 4 | Melakukan Design ReviewOverdue0/14wPlan: Jun 8–Jun 9 | Membuat Materi TrainingOn Progress0/1Plan: Jul 27–Jul 31 | Permintaan Customer VisitOverdue0/11wPlan: Jun 30–Jun 30 | Permintaan Customer VisitOverdue0/11wPlan: Jun 30–Jun 30 | - | - | - | - | - | - | - | - | - | - | - | 1mo |
| PT. Vivandiere Technology Indonesia - Renovasi Gedung Data Center BNPT - SentulProduct + InstalasiDeadline: Jun 1, 202611/15 aktivitas selesai | Membuat Approval Drawing GA-SLDDone1/14wPlan: Mar 18–Mar 19Actual: Apr 13 | Membuat Approval Drawing GA-SLD/cutoutDone1/14wPlan: Mar 5–Mar 10Actual: Apr 6 | Membuat BomlistDone1/12moPlan: Mar 13–Mar 18Actual: May 4 | Membuat BomlistDone1/1Plan: Mar 13–Mar 18Actual: Apr 17 | Membuat BomlistDone1/1Plan: Mar 19–Mar 20Actual: Mar 20 | Membuat SchematicDone1/11moPlan: Mar 13–Mar 18Actual: Apr 28 | Technical DrawingDone1/12moPlan: Mar 13–Mar 18Actual: May 4 | Melakukan Design ReviewDone1/12moPlan: Mar 25–Mar 25Actual: May 15 | Membuat MOP/WIOverdue0/14moPlan: Mar 16–Mar 18 | Membuat MOP/WIDone1/13moPlan: Mar 9–Mar 18Actual: Jun 10 | Membuat SOPOverdue0/14moPlan: Mar 16–Mar 18 | Membuat Form FAT, Onsite, SATDone1/13moPlan: Mar 5–Mar 18Actual: Jun 10 | Melakukan Design ReviewDone1/12moPlan: Mar 5–Mar 18Actual: May 15 | Membuat Materi TrainingOverdue0/13moPlan: Mar 11–Mar 27 | Membuat Materi TrainingOverdue0/13moPlan: Mar 5–Mar 27 | - | - | - | - | - | - | - | - | - | - | - | - | - | 4mo |
| Ekamas Mora Republik - POP Villa Beji Bali_ACPDB & DCPDBProduct + InstalasiDeadline: Jul 10, 20265/24 aktivitas selesai | Membuat Approval Drawing GAOverdue0/12dPlan: Jul 3–Jul 6 | Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 13–Jul 14 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jul 8–Jul 9Actual: Jun 29 | Membuat BomlistDone1/1Plan: Jul 6–Jul 6Actual: Jun 30 | Membuat BomlistDone1/1Plan: Jul 9–Jul 9Actual: Jun 29 | Membuat Timeline instalasiOn Progress0/1Plan: Jul 14–Jul 14 | Membuat BomlistOn Progress0/1Plan: Jul 14–Jul 15 | Membuat SchematicDone1/1Plan: Jul 9–Jul 9Actual: Jun 29 | Technical DrawingDone1/1Plan: Jul 6–Jul 7Actual: Jun 30 | Melakukan Design ReviewOverdue0/11dPlan: Jul 7–Jul 7 | Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 9–Jul 10 | Membuat MOP/WIOn Progress0/1Plan: Jul 15–Jul 15 | Membuat MOP/WIOn Progress0/1Plan: Jul 10–Jul 10 | Membuat SOPOn Progress0/1Plan: Jul 15–Jul 15 | Permintaan Customer VisitOn Progress0/1Plan: Jul 7–Jul 8 | Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 15–Jul 16 | Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 10–Jul 10 | Membuat MOP/WIOn Progress0/1Plan: Jul 8–Jul 8 | Melakukan Design ReviewOn Progress0/1Plan: Jul 10–Jul 13 | Membuat Materi TrainingOn Progress0/1Plan: Jul 8–Jul 8 | Membuat Materi TrainingOn Progress0/1Plan: Jul 16–Jul 16 | Membuat Materi TrainingOn Progress0/1Plan: Jul 13–Jul 13 | Permintaan Customer VisitOn Progress0/1Plan: Jul 16–Jul 16 | Permintaan Customer VisitOn Progress0/1Plan: Jul 13–Jul 13 | - | - | - | - | 2d |
| Hitachi - ACP25053 - DSS Maumere 150kVProduct + InstalasiDeadline: Jul 6, 20267/8 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Feb 27–Feb 27Actual: Feb 25 | Membuat Approval Drawing GA-SLD/cutoutDone1/13dPlan: Feb 27–Feb 27Actual: Mar 2 | Membuat BomlistDone1/13wPlan: Mar 3–Mar 3Actual: Mar 25 | Membuat BomlistDone1/12wPlan: Mar 4–Mar 4Actual: Mar 18 | Membuat SchematicOverdue0/14moPlan: Mar 3–Mar 3 | Technical DrawingDone1/12wPlan: Mar 9–Mar 11Actual: Mar 25 | Melakukan Design ReviewDone1/11wPlan: Mar 12–Mar 12Actual: Mar 20 | Membuat Dxf Cutout / nameplateDone1/12wPlan: Mar 5–Mar 5Actual: Mar 17 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 4mo |
| Hitachi - ACP25076 - Single Phi BarruProduct + InstalasiDeadline: Jun 16, 20269/9 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Mar 2–Mar 2Actual: Mar 2 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Mar 2–Mar 2Actual: Mar 2 | Membuat BomlistDone1/16dPlan: Mar 4–Mar 4Actual: Mar 10 | Membuat BomlistDone1/1Plan: Mar 10–Mar 10Actual: Mar 4 | Membuat SchematicDone1/1Plan: Mar 9–Mar 9Actual: Mar 9 | Technical DrawingDone1/1Plan: Mar 9–Mar 10Actual: Mar 4 | Melakukan Design ReviewDone1/1Plan: Mar 9–Mar 9Actual: Mar 4 | Membuat Dxf Cutout / nameplateDone1/1Plan: Mar 10–Mar 10Actual: Mar 9 | Melakukan Design ReviewDone1/1Plan: Mar 9–Mar 9Actual: Mar 4 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 6d |
| MIG - PO-26-0171 - Project Alladin Panel S110 & S510 - Panel DistributionProduct + InstalasiDeadline: Jul 8, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOn Progress0/1Plan: Jul 17–Jul 20 | Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 27–Jul 28 | Membuat Approval Drawing GA-SLD/cutoutOn Progress0/1Plan: Jul 22–Jul 23 | Membuat BomlistOn Progress0/1Plan: Jul 20–Jul 20 | Membuat BomlistOn Progress0/1Plan: Jul 23–Jul 23 | Membuat Timeline instalasiOn Progress0/1Plan: Jul 28–Jul 28 | Membuat BomlistOn Progress0/1Plan: Jul 28–Jul 29 | Membuat SchematicOn Progress0/1Plan: Jul 23–Jul 23 | Technical DrawingOn Progress0/1Plan: Jul 20–Jul 21 | Melakukan Design ReviewOn Progress0/1Plan: Jul 21–Jul 21 | Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 23–Jul 24 | Membuat MOP/WIOn Progress0/1Plan: Jul 29–Jul 29 | Membuat MOP/WIOn Progress0/1Plan: Jul 24–Jul 24 | Membuat SOPOn Progress0/1Plan: Jul 29–Jul 29 | Permintaan Customer VisitOn Progress0/1Plan: Jul 21–Jul 22 | Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 29–Jul 30 | Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 24–Jul 24 | Membuat MOP/WIOn Progress0/1Plan: Jul 22–Jul 22 | Melakukan Design ReviewOn Progress0/1Plan: Jul 24–Jul 27 | Membuat Materi TrainingOn Progress0/1Plan: Jul 22–Jul 22 | Membuat Materi TrainingOn Progress0/1Plan: Jul 30–Jul 30 | Membuat Materi TrainingOn Progress0/1Plan: Jul 27–Jul 27 | Permintaan Customer VisitOn Progress0/1Plan: Jul 30–Jul 30 | Permintaan Customer VisitOn Progress0/1Plan: Jul 27–Jul 27 | - | - | - | - | — |
| Hitachi - ACP25029 - GI Tolinggula 150kVProduct + InstalasiDeadline: Jul 13, 20267/7 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Mar 27–Mar 27Actual: Mar 27 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Mar 18–Mar 18Actual: Mar 18 | Membuat BomlistDone1/11dPlan: Apr 1–Apr 1Actual: Apr 2 | Membuat BomlistDone1/11wPlan: Apr 2–Apr 2Actual: Apr 10 | Membuat SchematicDone1/11wPlan: Apr 2–Apr 2Actual: Apr 10 | Technical DrawingDone1/11dPlan: Apr 1–Apr 1Actual: Apr 2 | Membuat Dxf Cutout / nameplateDone1/11wPlan: Apr 3–Apr 3Actual: Apr 10 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1w |
| Inti Bumi Mas - Panel VFD 132KWProduct + InstalasiDeadline: Jul 22, 202610/10 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: Jan 5–Jan 5Actual: Jan 5 | Membuat Approval Drawing GA-SLD/cutoutDone1/1Plan: Jan 5–Jan 5Actual: Jan 5 | Membuat BomlistDone1/12moPlan: Jan 7–Jan 7Actual: Mar 4 | Membuat BomlistDone1/12moPlan: Jan 7–Jan 7Actual: Feb 24 | Membuat SchematicDone1/12moPlan: Jan 5–Jan 5Actual: Feb 24 | Technical DrawingDone1/12moPlan: Jan 7–Jan 8Actual: Mar 4 | Melakukan Design ReviewDone1/1Plan: Jan 12–Jan 8Actual: Jan 8 | Membuat Dxf Cutout / nameplateDone1/11moPlan: Jan 12–Jan 13Actual: Feb 24 | Membuat Form FAT, Onsite, SATDone1/13moPlan: Mar 13–Mar 13Actual: Jun 19 | Melakukan Design ReviewDone1/1Plan: Jan 9–Jan 9Actual: Jan 8 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 3mo |
| Hitachi - ACP26018 - GI KM17 Borneo IndobaraProduct + InstalasiDeadline: Jul 30, 20268/8 aktivitas selesai | Membuat Approval Drawing GADone1/1Plan: May 12–May 12Actual: May 12 | Membuat Approval Drawing GA-SLD/cutoutDone1/11wPlan: May 15–May 15Actual: May 25 | Membuat BomlistDone1/1Plan: May 15–May 15Actual: May 12 | Membuat BomlistDone1/16dPlan: May 19–May 19Actual: May 25 | Membuat SchematicDone1/1Plan: May 19–May 19Actual: May 18 | Technical DrawingDone1/1Plan: May 12–May 15Actual: May 12 | Melakukan Design ReviewDone1/1Plan: May 12–May 12Actual: May 11 | Membuat Dxf Cutout / nameplateDone1/1Plan: May 19–May 19Actual: May 15 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | 1w |
| Rumah Data Kita CGK11 - Rack Server 45UProduct + InstalasiDeadline: Sep 11, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOn Progress0/1Plan: Jul 14–Jul 15 | Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 22–Jul 23 | Membuat Approval Drawing GA-SLD/cutoutOn Progress0/1Plan: Jul 17–Jul 20 | Membuat BomlistOn Progress0/1Plan: Jul 15–Jul 15 | Membuat BomlistOn Progress0/1Plan: Jul 20–Jul 20 | Membuat Timeline instalasiOn Progress0/1Plan: Jul 23–Jul 23 | Membuat BomlistOn Progress0/1Plan: Jul 23–Jul 24 | Membuat SchematicOn Progress0/1Plan: Jul 20–Jul 20 | Technical DrawingOn Progress0/1Plan: Jul 15–Jul 16 | Melakukan Design ReviewOn Progress0/1Plan: Jul 16–Jul 16 | Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 20–Jul 21 | Membuat MOP/WIOn Progress0/1Plan: Jul 24–Jul 24 | Membuat MOP/WIOn Progress0/1Plan: Jul 21–Jul 21 | Membuat SOPOn Progress0/1Plan: Jul 24–Jul 24 | Permintaan Customer VisitOn Progress0/1Plan: Jul 16–Jul 17 | Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 24–Jul 27 | Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 21–Jul 21 | Membuat MOP/WIOn Progress0/1Plan: Jul 17–Jul 17 | Melakukan Design ReviewOn Progress0/1Plan: Jul 21–Jul 22 | Membuat Materi TrainingOn Progress0/1Plan: Jul 17–Jul 17 | Membuat Materi TrainingOn Progress0/1Plan: Jul 27–Jul 27 | Membuat Materi TrainingOn Progress0/1Plan: Jul 22–Jul 22 | Permintaan Customer VisitOn Progress0/1Plan: Jul 27–Jul 27 | Permintaan Customer VisitOn Progress0/1Plan: Jul 22–Jul 22 | - | - | - | - | — |
| Internal - Stock Box Container 40 Feet ( 10 Unit)Product + InstalasiDeadline: Sep 21, 20262/2 aktivitas selesai | Membuat BomlistDone1/1Plan: Nov 10–Nov 13Actual: Nov 13 | Melakukan Design ReviewDone1/1Plan: Dec 19–Dec 31Actual: Jan 13 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - ACP25111 - Muara Laboh Stage 2Product + InstalasiDeadline: Oct 23, 20260/24 aktivitas selesai | Membuat Approval Drawing GAOn Progress0/1Plan: Jul 15–Jul 16 | Membuat Approval Drawing GA-SLDOn Progress0/1Plan: Jul 23–Jul 24 | Membuat Approval Drawing GA-SLD/cutoutOn Progress0/1Plan: Jul 20–Jul 21 | Membuat BomlistOn Progress0/1Plan: Jul 16–Jul 16 | Membuat BomlistOn Progress0/1Plan: Jul 21–Jul 21 | Membuat Timeline instalasiOn Progress0/1Plan: Jul 24–Jul 24 | Membuat BomlistOn Progress0/1Plan: Jul 24–Jul 27 | Membuat SchematicOn Progress0/1Plan: Jul 21–Jul 21 | Technical DrawingOn Progress0/1Plan: Jul 16–Jul 17 | Melakukan Design ReviewOn Progress0/1Plan: Jul 17–Jul 17 | Membuat Dxf Cutout / nameplateOn Progress0/1Plan: Jul 21–Jul 22 | Membuat MOP/WIOn Progress0/1Plan: Jul 27–Jul 27 | Membuat MOP/WIOn Progress0/1Plan: Jul 22–Jul 22 | Membuat SOPOn Progress0/1Plan: Jul 27–Jul 27 | Permintaan Customer VisitOn Progress0/1Plan: Jul 17–Jul 20 | Membuat Form FAT, ATP, SATOn Progress0/1Plan: Jul 27–Jul 28 | Membuat Form FAT, Onsite, SATOn Progress0/1Plan: Jul 22–Jul 22 | Membuat MOP/WIOn Progress0/1Plan: Jul 20–Jul 20 | Melakukan Design ReviewOn Progress0/1Plan: Jul 22–Jul 23 | Membuat Materi TrainingOn Progress0/1Plan: Jul 20–Jul 20 | Membuat Materi TrainingOn Progress0/1Plan: Jul 28–Jul 28 | Membuat Materi TrainingOn Progress0/1Plan: Jul 23–Jul 23 | Permintaan Customer VisitOn Progress0/1Plan: Jul 28–Jul 28 | Permintaan Customer VisitOn Progress0/1Plan: Jul 23–Jul 23 | - | - | - | - | — |