| GSPE_STOK BOX PANEL MORATELProduct + InstalasiDeadline: Aug 13, 20250/8 aktivitas selesai | Site Survey Overdue0/39moPlan: Sep 26–Sep 30 | Menerima SOP/MOPOverdue0/39moPlan: Sep 29–Oct 1 | Installation (L2)Overdue0/39moPlan: Sep 30–Oct 1 | ATP/Testcom (L3)Overdue0/39moPlan: Sep 30–Oct 2 | Functional Testing (L4)Overdue0/39moPlan: Oct 1–Oct 3 | Integrated System Testing (L5)Overdue0/39moPlan: Oct 2–Oct 3 | MaintenanceOverdue0/39moPlan: Oct 2–Oct 6 | TroubleshootOverdue0/39moPlan: Oct 3–Oct 6 | 9mo |
| Forecast_Stock Panel Hitachi IP42 & IP54Product + InstalasiDeadline: Oct 10, 20250/8 aktivitas selesai | Site Survey Overdue0/38moPlan: Oct 30–Nov 3 | Menerima SOP/MOPOverdue0/38moPlan: Oct 31–Nov 4 | Installation (L2)Overdue0/38moPlan: Nov 3–Nov 5 | ATP/Testcom (L3)Overdue0/38moPlan: Nov 3–Nov 6 | Functional Testing (L4)Overdue0/38moPlan: Nov 4–Nov 7 | Integrated System Testing (L5)Overdue0/38moPlan: Nov 5–Nov 7 | MaintenanceOverdue0/18moPlan: Nov 5–Nov 6 | TroubleshootOverdue0/18moPlan: Nov 6–Nov 6 | 8mo |
| PTT - Module MPTT DPC 3000 HE (25 unit)Product + InstalasiDeadline: Dec 19, 20250/8 aktivitas selesai | Site Survey Overdue0/16moPlan: Jan 23–Jan 23 | Menerima SOP/MOPOverdue0/25moPlan: Jan 23–Jan 26 | Installation (L2)Overdue0/15moPlan: Jan 26–Jan 27 | ATP/Testcom (L3)Overdue0/15moPlan: Jan 27–Jan 27 | Functional Testing (L4)Overdue0/15moPlan: Jan 27–Jan 28 | Integrated System Testing (L5)Overdue0/15moPlan: Jan 28–Jan 29 | MaintenanceOverdue0/15moPlan: Jan 29–Jan 29 | TroubleshootOverdue0/15moPlan: Jan 29–Jan 30 | 6mo |
| Internal - Micro Data Centre EatonProduct + InstalasiDeadline: Jan 23, 20260/8 aktivitas selesai | Site Survey Overdue0/15moPlan: Jan 26–Jan 26 | Menerima SOP/MOPOverdue0/15moPlan: Jan 26–Jan 27 | Installation (L2)Overdue0/15moPlan: Jan 27–Jan 28 | ATP/Testcom (L3)Overdue0/15moPlan: Jan 28–Jan 28 | Functional Testing (L4)Overdue0/15moPlan: Jan 28–Jan 29 | Integrated System Testing (L5)Overdue0/15moPlan: Jan 29–Jan 30 | MaintenanceOverdue0/15moPlan: Jan 30–Jan 30 | TroubleshootOverdue0/15moPlan: Jan 30–Feb 2 | 5mo |
| Internal - Stock Rack Server Moratel & DCPDUProduct + InstalasiDeadline: Jan 30, 20260/8 aktivitas selesai | Site Survey Overdue0/16moPlan: Jan 20–Jan 20 | Menerima SOP/MOPOverdue0/16moPlan: Jan 20–Jan 23 | Installation (L2)Overdue0/16moPlan: Jan 23–Jan 24 | ATP/Testcom (L3)Overdue0/15moPlan: Jan 24–Jan 25 | Functional Testing (L4)Overdue0/45moPlan: Jan 25–Jan 26 | Integrated System Testing (L5)Overdue0/45moPlan: Jan 25–Jan 26 | MaintenanceOverdue0/35moPlan: Jan 25–Jan 26 | TroubleshootOverdue0/35moPlan: Jan 25–Jan 26 | 6mo |
| BDX - CGK1_RACK SERVER & rPDUProduct + InstalasiDeadline: Feb 6, 20260/8 aktivitas selesai | Site Survey Overdue2/35moPlan: Dec 24–Feb 6Actual: Jan 16 | Menerima SOP/MOPOverdue1/35moPlan: Jan 12–Feb 9Actual: Jan 16 | Installation (L2)Overdue0/45moPlan: Jan 19–Feb 9 | ATP/Testcom (L3)Overdue0/35moPlan: Jan 22–Feb 10 | Functional Testing (L4)Overdue0/35moPlan: Jan 22–Feb 11 | Integrated System Testing (L5)Overdue0/35moPlan: Jan 23–Feb 11 | MaintenanceOverdue0/35moPlan: Jan 24–Feb 12 | TroubleshootOverdue0/35moPlan: Jan 24–Feb 12 | 5mo |
| Internal - Layout Penambahan Unit Mesin HSGProduct + InstalasiDeadline: Feb 6, 20260/8 aktivitas selesai | Site Survey Overdue0/14moPlan: Mar 9–Mar 9 | Menerima SOP/MOPOverdue0/14moPlan: Mar 9–Mar 10 | Installation (L2)Overdue0/14moPlan: Mar 10–Mar 11 | ATP/Testcom (L3)Overdue0/14moPlan: Mar 11–Mar 11 | Functional Testing (L4)Overdue0/14moPlan: Mar 11–Mar 12 | Integrated System Testing (L5)Overdue0/14moPlan: Mar 12–Mar 13 | MaintenanceOverdue0/14moPlan: Mar 13–Mar 13 | TroubleshootOverdue0/14moPlan: Mar 13–Mar 16 | 4mo |
| PT Telin - Instalasi CLS PluitProduct + InstalasiDeadline: Feb 26, 20260/8 aktivitas selesai | Site Survey Overdue0/14moPlan: Mar 23–Mar 24 | Menerima SOP/MOPOverdue0/14moPlan: Mar 24–Mar 25 | Installation (L2)Overdue0/14moPlan: Mar 25–Mar 25 | ATP/Testcom (L3)Overdue0/13moPlan: Mar 25–Mar 26 | Functional Testing (L4)Overdue0/13moPlan: Mar 26–Mar 27 | Integrated System Testing (L5)Overdue0/13moPlan: Mar 27–Mar 27 | MaintenanceOverdue0/13moPlan: Mar 27–Mar 30 | TroubleshootOverdue0/13moPlan: Mar 30–Mar 30 | 4mo |
| Job LeaderProduct + InstalasiDeadline: Feb 27, 20260/8 aktivitas selesai | Site Survey Overdue0/16moPlan: Dec 26–Dec 29 | Menerima SOP/MOPOverdue0/16moPlan: Dec 29–Dec 30 | Installation (L2)Overdue0/16moPlan: Dec 30–Dec 30 | ATP/Testcom (L3)Overdue0/16moPlan: Dec 30–Dec 31 | Functional Testing (L4)Overdue0/16moPlan: Dec 31–Jan 1 | Integrated System Testing (L5)Overdue0/16moPlan: Jan 1–Jan 1 | MaintenanceOverdue0/16moPlan: Jan 1–Jan 2 | TroubleshootOverdue0/16moPlan: Jan 2–Jan 2 | 6mo |
| Internal - Project ISO_27001Product + InstalasiDeadline: Feb 27, 20260/8 aktivitas selesai | Site Survey Overdue0/14moPlan: Mar 9–Mar 9 | Menerima SOP/MOPOverdue0/24moPlan: Mar 9–Mar 10 | Installation (L2)Overdue0/14moPlan: Mar 10–Mar 11 | ATP/Testcom (L3)Overdue0/24moPlan: Mar 11–Mar 11 | Functional Testing (L4)Overdue0/14moPlan: Mar 11–Mar 12 | Integrated System Testing (L5)Overdue0/14moPlan: Mar 12–Mar 13 | MaintenanceOverdue0/14moPlan: Mar 13–Mar 13 | TroubleshootOverdue0/24moPlan: Mar 13–Mar 16 | 4mo |
| Internal - Program Estimator (Containment, Container, Smart Rack)Product + InstalasiDeadline: Feb 27, 20260/8 aktivitas selesai | Site Survey Overdue0/14moPlan: Mar 9–Mar 10 | Menerima SOP/MOPOverdue0/14moPlan: Mar 10–Mar 11 | Installation (L2)Overdue0/14moPlan: Mar 11–Mar 11 | ATP/Testcom (L3)Overdue0/14moPlan: Mar 11–Mar 12 | Functional Testing (L4)Overdue0/14moPlan: Mar 12–Mar 13 | Integrated System Testing (L5)Overdue0/14moPlan: Mar 13–Mar 13 | MaintenanceOverdue0/14moPlan: Mar 13–Mar 16 | TroubleshootOverdue0/14moPlan: Mar 16–Mar 16 | 4mo |
| Internal - Automation Program CRM Section 1-4Product + InstalasiDeadline: Feb 27, 20260/8 aktivitas selesai | Site Survey Overdue0/14moPlan: Mar 9–Mar 10 | Menerima SOP/MOPOverdue0/14moPlan: Mar 10–Mar 11 | Installation (L2)Overdue0/14moPlan: Mar 11–Mar 11 | ATP/Testcom (L3)Overdue0/14moPlan: Mar 11–Mar 12 | Functional Testing (L4)Overdue0/14moPlan: Mar 12–Mar 13 | Integrated System Testing (L5)Overdue0/14moPlan: Mar 13–Mar 13 | MaintenanceOverdue0/14moPlan: Mar 13–Mar 16 | TroubleshootOverdue0/14moPlan: Mar 16–Mar 16 | 4mo |
| Internal - 29 Line AssemblyProduct + InstalasiDeadline: Feb 27, 20260/8 aktivitas selesai | Site Survey Overdue0/16moPlan: Jan 16–Jan 17 | Menerima SOP/MOPOverdue0/16moPlan: Jan 17–Jan 18 | Installation (L2)Overdue0/16moPlan: Jan 18–Jan 21 | ATP/Testcom (L3)Overdue0/16moPlan: Jan 21–Jan 21 | Functional Testing (L4)Overdue0/16moPlan: Jan 21–Jan 22 | Integrated System Testing (L5)Overdue0/16moPlan: Jan 22–Jan 23 | MaintenanceOverdue0/16moPlan: Jan 23–Jan 23 | TroubleshootOverdue0/16moPlan: Jan 23–Jan 24 | 6mo |
| Internal - Perbaikan Loading/Unloading Area Pintu BelakangProduct + InstalasiDeadline: Feb 27, 20260/8 aktivitas selesai | Site Survey Overdue0/13moPlan: Apr 14–Apr 14 | Menerima SOP/MOPOverdue0/13moPlan: Apr 14–Apr 15 | Installation (L2)Overdue0/23moPlan: Apr 15–Apr 16 | ATP/Testcom (L3)Overdue0/13moPlan: Apr 16–Apr 16 | Functional Testing (L4)Overdue0/13moPlan: Apr 16–Apr 17 | Integrated System Testing (L5)Overdue0/13moPlan: Apr 17–Apr 18 | MaintenanceOverdue0/23moPlan: Apr 18–Apr 18 | TroubleshootOverdue0/13moPlan: Apr 18–Apr 21 | 3mo |
| Review Product Presentation - Marketing UpdateProduct + InstalasiDeadline: Feb 27, 20260/8 aktivitas selesai | Site Survey Overdue0/15moPlan: Feb 21–Feb 21 | Menerima SOP/MOPOverdue0/15moPlan: Feb 21–Feb 22 | Installation (L2)Overdue0/15moPlan: Feb 22–Feb 23 | ATP/Testcom (L3)Overdue0/25moPlan: Feb 23–Feb 23 | Functional Testing (L4)Overdue0/24moPlan: Feb 23–Feb 24 | Integrated System Testing (L5)Overdue0/14moPlan: Feb 24–Feb 25 | MaintenanceOverdue0/24moPlan: Feb 25–Feb 25 | TroubleshootOverdue0/14moPlan: Feb 25–Feb 28 | 5mo |
| Mega Akses - POP Tegal Cangkring-Bali (Add Battery)Product + InstalasiDeadline: Mar 13, 20260/8 aktivitas selesai | Site Survey Overdue0/14moPlan: Mar 2–Mar 3 | Menerima SOP/MOPOverdue0/14moPlan: Mar 3–Mar 4 | Installation (L2)Overdue0/14moPlan: Mar 4–Mar 4 | ATP/Testcom (L3)Overdue0/14moPlan: Mar 4–Mar 5 | Functional Testing (L4)Overdue0/14moPlan: Mar 5–Mar 6 | Integrated System Testing (L5)Overdue0/14moPlan: Mar 6–Mar 6 | MaintenanceOverdue0/14moPlan: Mar 6–Mar 9 | TroubleshootOverdue0/14moPlan: Mar 9–Mar 9 | 4mo |
| Internal - Mini Data Center Rack (MDCR) from ScheneiderProduct + InstalasiDeadline: Mar 27, 20260/8 aktivitas selesai | Site Survey Overdue0/14moPlan: Mar 12–Mar 12 | Menerima SOP/MOPOverdue0/14moPlan: Mar 12–Mar 13 | Installation (L2)Overdue0/14moPlan: Mar 13–Mar 14 | ATP/Testcom (L3)Overdue0/14moPlan: Mar 14–Mar 14 | Functional Testing (L4)Overdue0/14moPlan: Mar 14–Mar 15 | Integrated System Testing (L5)Overdue0/14moPlan: Mar 15–Mar 16 | MaintenanceOverdue0/14moPlan: Mar 16–Mar 16 | TroubleshootOverdue0/14moPlan: Mar 16–Mar 19 | 4mo |
| Mock Up - PT. Enerkomp Persada Raya Panel Soft Starter 250KWProduct + InstalasiDeadline: Mar 31, 20260/8 aktivitas selesai | Site Survey Overdue0/16moPlan: Jan 24–Jan 24 | Menerima SOP/MOPOverdue0/25moPlan: Jan 24–Jan 25 | Installation (L2)Overdue0/15moPlan: Jan 25–Jan 26 | ATP/Testcom (L3)Overdue0/15moPlan: Jan 26–Jan 27 | Functional Testing (L4)Overdue0/15moPlan: Jan 27–Jan 30 | Integrated System Testing (L5)Overdue0/15moPlan: Jan 30–Jan 31 | MaintenanceOverdue0/15moPlan: Jan 30–Jan 31 | TroubleshootOverdue0/15moPlan: Jan 30–Jan 31 | 6mo |
| GSPE_Smart Rack (Micro Data Center)Product + InstalasiDeadline: Apr 6, 20260/8 aktivitas selesai | Site Survey Overdue0/15moPlan: Feb 5–Feb 5 | Menerima SOP/MOPOverdue0/15moPlan: Feb 5–Feb 8 | Installation (L2)Overdue0/15moPlan: Feb 8–Feb 9 | ATP/Testcom (L3)Overdue0/15moPlan: Feb 9–Feb 10 | Functional Testing (L4)Overdue0/15moPlan: Feb 10–Feb 11 | Integrated System Testing (L5)Overdue0/15moPlan: Feb 11–Feb 12 | MaintenanceOverdue0/25moPlan: Feb 12–Feb 12 | TroubleshootOverdue0/15moPlan: Feb 12–Feb 12 | 5mo |
| Mega Akses - Req.Battery - JABODETABEKProduct + InstalasiDeadline: Apr 10, 20260/8 aktivitas selesai | Site Survey Overdue0/14moPlan: Mar 19–Mar 20 | Menerima SOP/MOPOverdue0/14moPlan: Mar 20–Mar 23 | Installation (L2)Overdue0/14moPlan: Mar 23–Mar 23 | ATP/Testcom (L3)Overdue0/14moPlan: Mar 23–Mar 24 | Functional Testing (L4)Overdue0/14moPlan: Mar 24–Mar 25 | Integrated System Testing (L5)Overdue0/14moPlan: Mar 25–Mar 25 | MaintenanceOverdue0/13moPlan: Mar 25–Mar 26 | TroubleshootOverdue0/13moPlan: Mar 26–Mar 26 | 4mo |
| INTERNAL | - MDCC Trial Full Schneider Device - ContainerProduct + InstalasiDeadline: Apr 20, 20260/8 aktivitas selesai | Site Survey Overdue0/104moPlan: Jan 26–Mar 13 | Menerima SOP/MOPOverdue0/94moPlan: Jan 27–Mar 14 | Installation (L2)Overdue0/104moPlan: Jan 28–Mar 15 | ATP/Testcom (L3)Overdue0/104moPlan: Jan 28–Mar 15 | Functional Testing (L4)Overdue0/94moPlan: Jan 29–Mar 16 | Integrated System Testing (L5)Overdue0/144moPlan: Jan 30–Mar 17 | MaintenanceOverdue0/114moPlan: Jan 30–Mar 17 | TroubleshootOverdue0/114moPlan: Feb 2–Mar 20 | 4mo |
| Internal - Smart rPDUProduct + InstalasiDeadline: Apr 30, 20260/8 aktivitas selesai | Site Survey Overdue0/15moPlan: Feb 13–Feb 13 | Menerima SOP/MOPOverdue0/15moPlan: Feb 13–Feb 14 | Installation (L2)Overdue0/15moPlan: Feb 14–Feb 15 | ATP/Testcom (L3)Overdue0/25moPlan: Feb 15–Feb 15 | Functional Testing (L4)Overdue0/15moPlan: Feb 15–Feb 16 | Integrated System Testing (L5)Overdue0/25moPlan: Feb 16–Feb 17 | MaintenanceOverdue0/15moPlan: Feb 17–Feb 17 | TroubleshootOverdue0/15moPlan: Feb 17–Feb 20 | 5mo |
| Mega Akses - BDF Power Tanah Merah (Add Battery)Product + InstalasiDeadline: Apr 30, 20260/8 aktivitas selesai | Site Survey Overdue0/13moPlan: Mar 30–Mar 31 | Menerima SOP/MOPOverdue0/13moPlan: Mar 31–Apr 1 | Installation (L2)Overdue0/13moPlan: Apr 1–Apr 1 | ATP/Testcom (L3)Overdue0/13moPlan: Apr 1–Apr 2 | Functional Testing (L4)Overdue0/13moPlan: Apr 2–Apr 3 | Integrated System Testing (L5)Overdue0/13moPlan: Apr 3–Apr 3 | MaintenanceOverdue0/13moPlan: Apr 3–Apr 6 | TroubleshootOverdue0/13moPlan: Apr 6–Apr 6 | 3mo |
| Schneider Electric - LNGPPProduct + InstalasiDeadline: Apr 30, 20260/8 aktivitas selesai | Site Survey Overdue0/23moPlan: Apr 16–Apr 16 | Menerima SOP/MOPOverdue0/13moPlan: Apr 16–Apr 17 | Installation (L2)Overdue0/13moPlan: Apr 17–Apr 20 | ATP/Testcom (L3)Overdue0/13moPlan: Apr 20–Apr 20 | Functional Testing (L4)Overdue0/13moPlan: Apr 20–Apr 21 | Integrated System Testing (L5)Overdue0/13moPlan: Apr 21–Apr 22 | MaintenanceOverdue0/13moPlan: Apr 22–Apr 22 | TroubleshootOverdue0/13moPlan: Apr 22–Apr 23 | 3mo |
| BDX - CGK1_Panel PDUProduct + InstalasiDeadline: May 21, 20260/8 aktivitas selesai | Site Survey Overdue1/21moPlan: Feb 2–Jun 5Actual: Dec 10 | Menerima SOP/MOPOverdue1/25moPlan: Feb 2–Feb 14Actual: Dec 21 | Installation (L2)Overdue1/23moPlan: Feb 3–Apr 11Actual: Mar 5 | ATP/Testcom (L3)Overdue0/22moPlan: Feb 4–May 9 | Functional Testing (L4)Overdue0/23moPlan: Feb 4–Apr 24 | Integrated System Testing (L5)Overdue0/21moPlan: Feb 5–Jun 4 | MaintenanceOverdue0/41moPlan: Feb 6–Jun 8 | TroubleshootOverdue0/24wPlan: Feb 6–Jun 9 | 5mo |
| Schneider - Panel for PUSRI IIIB Project // E2010-96440Product + InstalasiDeadline: May 26, 20260/8 aktivitas selesai | Site Survey Overdue0/17moPlan: Dec 6–Dec 6 | Menerima SOP/MOPOverdue0/17moPlan: Dec 6–Dec 9 | Installation (L2)Overdue0/27moPlan: Dec 9–Dec 10 | ATP/Testcom (L3)Overdue0/17moPlan: Dec 10–Dec 11 | Functional Testing (L4)Overdue0/17moPlan: Dec 11–Dec 12 | Integrated System Testing (L5)Overdue0/17moPlan: Dec 11–Dec 12 | MaintenanceOverdue0/17moPlan: Dec 11–Dec 12 | TroubleshootOverdue0/17moPlan: Dec 11–Dec 12 | 7mo |
| Internal - Forecast Rack Server : (42U, 45U, 52U)Product + InstalasiDeadline: May 29, 20260/8 aktivitas selesai | Site Survey Overdue0/32moPlan: Apr 2–May 8 | Menerima SOP/MOPOverdue0/42moPlan: Apr 2–May 9 | Installation (L2)Overdue0/32moPlan: Apr 3–May 10 | ATP/Testcom (L3)Overdue0/32moPlan: Apr 4–May 10 | Functional Testing (L4)Overdue0/32moPlan: Apr 4–May 11 | Integrated System Testing (L5)Overdue0/32moPlan: Apr 5–May 12 | MaintenanceOverdue0/32moPlan: Apr 6–May 12 | TroubleshootOverdue0/32moPlan: Apr 6–May 15 | 2mo |
| Siemens - UCC BP TangguhProduct + InstalasiDeadline: May 29, 20260/8 aktivitas selesai | Site Survey Overdue0/13moPlan: Mar 26–Mar 27 | Menerima SOP/MOPOverdue0/13moPlan: Mar 27–Mar 30 | Installation (L2)Overdue0/13moPlan: Mar 30–Mar 30 | ATP/Testcom (L3)Overdue0/13moPlan: Mar 30–Mar 31 | Functional Testing (L4)Overdue0/13moPlan: Mar 31–Apr 1 | Integrated System Testing (L5)Overdue0/13moPlan: Apr 1–Apr 1 | MaintenanceOverdue0/13moPlan: Apr 1–Apr 2 | TroubleshootOverdue0/13moPlan: Apr 2–Apr 2 | 3mo |
| Kelinci Mas Unggul - Panel MK Single PhiProduct + InstalasiDeadline: Jun 10, 20260/8 aktivitas selesai | Site Survey Overdue0/14wPlan: Jun 8–Jun 9 | Menerima SOP/MOPOverdue0/14wPlan: Jun 9–Jun 10 | Installation (L2)Overdue0/14wPlan: Jun 10–Jun 10 | ATP/Testcom (L3)Overdue0/14wPlan: Jun 10–Jun 11 | Functional Testing (L4)Overdue0/14wPlan: Jun 11–Jun 12 | Integrated System Testing (L5)Overdue0/14wPlan: Jun 12–Jun 12 | MaintenanceOverdue0/13wPlan: Jun 12–Jun 15 | TroubleshootOverdue0/13wPlan: Jun 15–Jun 15 | 4w |
| Hitachi - ACP25035 - GI Satui 150kVProduct + InstalasiDeadline: Jun 19, 20260/8 aktivitas selesai | Site Survey Overdue0/15moPlan: Feb 17–Feb 17 | Menerima SOP/MOPOverdue0/15moPlan: Feb 17–Feb 19 | Installation (L2)Overdue0/15moPlan: Feb 19–Feb 20 | ATP/Testcom (L3)Overdue0/15moPlan: Feb 20–Feb 23 | Functional Testing (L4)Overdue0/14moPlan: Feb 23–Feb 24 | Integrated System Testing (L5)Overdue0/14moPlan: Feb 23–Feb 24 | MaintenanceOverdue0/14moPlan: Feb 23–Feb 24 | TroubleshootOverdue0/24moPlan: Feb 23–Feb 24 | 5mo |
| Internal - MDCC 20 Feet POD Phase 2/IP65Product + InstalasiDeadline: Jun 30, 20260/8 aktivitas selesai | Site Survey Overdue0/12moPlan: May 15–May 15 | Menerima SOP/MOPOverdue0/12moPlan: May 15–May 18 | Installation (L2)Overdue0/12moPlan: May 18–May 19 | ATP/Testcom (L3)Overdue0/12moPlan: May 19–May 20 | Functional Testing (L4)Overdue0/12moPlan: May 20–May 21 | Integrated System Testing (L5)Overdue0/12moPlan: May 21–May 22 | MaintenanceOverdue0/12moPlan: May 22–May 22 | TroubleshootOverdue0/12moPlan: May 22–May 22 | 2mo |
| Internal - Contaiment 50 UnitProduct + InstalasiDeadline: Jun 30, 20260/8 aktivitas selesai | Site Survey Overdue0/13moPlan: Mar 28–Mar 28 | Menerima SOP/MOPOverdue0/13moPlan: Mar 28–Mar 31 | Installation (L2)Overdue0/13moPlan: Mar 31–Apr 1 | ATP/Testcom (L3)Overdue0/13moPlan: Apr 1–Apr 2 | Functional Testing (L4)Overdue0/13moPlan: Apr 2–Apr 3 | Integrated System Testing (L5)Overdue0/13moPlan: Apr 3–Apr 4 | MaintenanceOverdue0/13moPlan: Apr 4–Apr 4 | TroubleshootOverdue0/13moPlan: Apr 4–Apr 4 | 3mo |
| Internal - Pembuatan Bak Treatment, Hoist, Oven dan TrolleyProduct + InstalasiDeadline: Jun 30, 20260/8 aktivitas selesai | Site Survey Overdue0/34moPlan: Feb 23–Mar 12 | Menerima SOP/MOPOverdue0/34moPlan: Feb 23–Mar 13 | Installation (L2)Overdue0/34moPlan: Feb 24–Mar 14 | ATP/Testcom (L3)Overdue0/44moPlan: Feb 25–Mar 15 | Functional Testing (L4)Overdue0/54moPlan: Feb 26–Mar 16 | Integrated System Testing (L5)Overdue0/64moPlan: Feb 27–Mar 19 | MaintenanceOverdue0/44moPlan: Jan 5–Mar 19 | TroubleshootOverdue0/44moPlan: Jan 5–Mar 19 | 4mo |
| Wholesale - Panel DB - Dermaga BiakProduct + InstalasiDeadline: Jun 30, 20260/8 aktivitas selesai | Site Survey Overdue0/11wPlan: Jun 29–Jun 30 | Menerima SOP/MOPOverdue0/11wPlan: Jun 30–Jul 1 | Installation (L2)Overdue0/11wPlan: Jul 1–Jul 1 | ATP/Testcom (L3)Overdue0/16dPlan: Jul 1–Jul 2 | Functional Testing (L4)Overdue0/15dPlan: Jul 2–Jul 3 | Integrated System Testing (L5)Overdue0/15dPlan: Jul 3–Jul 3 | MaintenanceOverdue0/12dPlan: Jul 3–Jul 6 | TroubleshootOverdue0/12dPlan: Jul 6–Jul 6 | 1w |
| PT. NexWave_Panel TXDP & SDP AC_PO25090188Product + InstalasiDeadline: Jul 3, 20260/8 aktivitas selesai | Site Survey Overdue0/13wPlan: Jun 17–Jun 17 | Menerima SOP/MOPOverdue0/13wPlan: Jun 17–Jun 18 | Installation (L2)Overdue0/23wPlan: Jun 18–Jun 19 | ATP/Testcom (L3)Overdue0/13wPlan: Jun 19–Jun 19 | Functional Testing (L4)Overdue0/13wPlan: Jun 19–Jun 20 | Integrated System Testing (L5)Overdue0/22wPlan: Jun 20–Jun 21 | MaintenanceOverdue0/12wPlan: Jun 21–Jun 21 | TroubleshootOverdue0/12wPlan: Jun 21–Jun 24 | 3w |
| Hitachi - ACP25085 - Sebuku PLN NPCProduct + InstalasiDeadline: Jul 6, 20260/8 aktivitas selesai | Site Survey Overdue0/12wPlan: Jun 25–Jun 25 | Menerima SOP/MOPOverdue0/12wPlan: Jun 25–Jun 26 | Installation (L2)Overdue0/11wPlan: Jun 26–Jun 29 | ATP/Testcom (L3)Overdue0/11wPlan: Jun 29–Jun 29 | Functional Testing (L4)Overdue0/11wPlan: Jun 29–Jun 30 | Integrated System Testing (L5)Overdue0/11wPlan: Jun 30–Jul 1 | MaintenanceOverdue0/11wPlan: Jul 1–Jul 1 | TroubleshootOverdue0/16dPlan: Jul 1–Jul 2 | 2w |
| Hitachi - ACP25026 - BalonganProduct + InstalasiDeadline: Jul 20, 20260/8 aktivitas selesai | Site Survey Overdue0/16moPlan: Jan 13–Jan 13 | Menerima SOP/MOPOverdue0/16moPlan: Jan 13–Jan 15 | Installation (L2)Overdue0/16moPlan: Jan 15–Jan 16 | ATP/Testcom (L3)Overdue0/16moPlan: Jan 16–Jan 19 | Functional Testing (L4)Overdue0/16moPlan: Jan 19–Jan 20 | Integrated System Testing (L5)Overdue0/36moPlan: Jan 19–Jan 20 | MaintenanceOverdue0/16moPlan: Jan 19–Jan 20 | TroubleshootOverdue0/16moPlan: Jan 19–Jan 20 | 6mo |
| Inti Bumi Mas - Panel FeederProduct + InstalasiDeadline: Jul 22, 20260/8 aktivitas selesai | Site Survey Overdue0/13moPlan: Apr 13–Apr 14 | Menerima SOP/MOPOverdue0/13moPlan: Apr 14–Apr 15 | Installation (L2)Overdue0/13moPlan: Apr 15–Apr 15 | ATP/Testcom (L3)Overdue0/13moPlan: Apr 15–Apr 16 | Functional Testing (L4)Overdue0/13moPlan: Apr 16–Apr 17 | Integrated System Testing (L5)Overdue0/13moPlan: Apr 17–Apr 17 | MaintenanceOverdue0/13moPlan: Apr 17–Apr 20 | TroubleshootOverdue0/13moPlan: Apr 20–Apr 20 | 3mo |
| Mega Akes - HUB Majalengka (Add Battery)Product + InstalasiDeadline: Jul 31, 20260/8 aktivitas selesai | Site Survey Overdue0/13moPlan: Mar 30–Mar 31 | Menerima SOP/MOPOverdue0/13moPlan: Mar 31–Apr 1 | Installation (L2)Overdue0/13moPlan: Apr 1–Apr 1 | ATP/Testcom (L3)Overdue0/13moPlan: Apr 1–Apr 2 | Functional Testing (L4)Overdue0/13moPlan: Apr 2–Apr 3 | Integrated System Testing (L5)Overdue0/13moPlan: Apr 3–Apr 3 | MaintenanceOverdue0/13moPlan: Apr 3–Apr 6 | TroubleshootOverdue0/13moPlan: Apr 6–Apr 6 | 3mo |
| Mega Akses - Omadata SurabayaProduct + InstalasiDeadline: Jul 31, 20260/8 aktivitas selesai | Site Survey Overdue0/11moPlan: Jun 8–Jun 8 | Menerima SOP/MOPOverdue0/14wPlan: Jun 9–Jun 10 | Installation (L2)Overdue0/14wPlan: Jun 10–Jun 10 | ATP/Testcom (L3)Overdue0/14wPlan: Jun 10–Jun 11 | Functional Testing (L4)Overdue0/14wPlan: Jun 10–Jun 11 | Integrated System Testing (L5)Overdue0/14wPlan: Jun 11–Jun 12 | MaintenanceOverdue0/14wPlan: Jun 12–Jun 12 | TroubleshootOverdue0/13wPlan: Jun 12–Jun 15 | 1mo |
| Demo/Mockup Panel Typetest Cubic, Eaton MV, Eaton LVProduct + InstalasiDeadline: Aug 31, 20260/8 aktivitas selesai | Site Survey Overdue0/44moPlan: Mar 9–Mar 9 | Menerima SOP/MOPOverdue0/34moPlan: Mar 9–Mar 10 | Installation (L2)Overdue0/54moPlan: Mar 10–Mar 11 | ATP/Testcom (L3)Overdue0/34moPlan: Mar 11–Mar 11 | Functional Testing (L4)Overdue0/54moPlan: Mar 11–Mar 12 | Integrated System Testing (L5)Overdue0/34moPlan: Mar 12–Mar 13 | MaintenanceOverdue0/34moPlan: Mar 13–Mar 13 | TroubleshootOverdue0/34moPlan: Mar 13–Mar 16 | 4mo |
| Shimizu - Loadbank IRISProduct + InstalasiDeadline: Feb 22, 20260/4 aktivitas selesai | Site Survey Overdue0/16moPlan: Jan 1–Jan 1 | Menerima SOP/MOPOverdue0/16moPlan: Jan 1–Jan 4 | Installation (L2)Overdue0/16moPlan: Jan 4–Jan 5 | ATP/Testcom (L3)Overdue0/16moPlan: Jan 5–Jan 6 | - | - | - | - | 6mo |
| Kelinci Mas - DSS TallolamaProduct OnlyDeadline: Aug 7, 20260/4 aktivitas selesai | Site Survey Overdue0/17moPlan: Dec 17–Dec 19 | Menerima SOP/MOPOverdue0/17moPlan: Dec 19–Dec 20 | Installation (L2)Overdue0/17moPlan: Dec 20–Dec 23 | ATP/Testcom (L3)Overdue0/17moPlan: Dec 23–Dec 24 | - | - | - | - | 7mo |
| PT. Vivandiere Technology Indonesia - Renovasi Gedung Data Center BNPT - SentulProduct + InstalasiDeadline: Jun 1, 20262/6 aktivitas selesai | Site Survey Done1/1Plan: Apr 16–Apr 17Actual: Apr 9 | Menerima SOP/MOPDone1/12moPlan: Apr 17–Apr 20Actual: Jun 10 | Installation (L2)On Progress0/1Plan: Jun 9–Jul 17 | ATP/Testcom (L3)On Progress0/1Plan: Jul 13–Jul 24 | Functional Testing (L4)On Progress0/1Plan: Jul 29–Aug 7 | Integrated System Testing (L5)On Progress0/1Plan: Aug 12–Aug 14 | - | - | 2mo |
| MIG - PO-26-0171 - Project Alladin Panel S110 & S510 - Panel DistributionProduct + InstalasiDeadline: Jul 8, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Aug 24–Aug 25 | Menerima SOP/MOPOn Progress0/1Plan: Aug 25–Aug 26 | Installation (L2)On Progress0/1Plan: Aug 26–Aug 26 | ATP/Testcom (L3)On Progress0/1Plan: Aug 26–Aug 27 | Functional Testing (L4)On Progress0/1Plan: Aug 27–Aug 28 | Integrated System Testing (L5)On Progress0/1Plan: Aug 28–Aug 28 | MaintenanceOn Progress0/1Plan: Aug 28–Aug 31 | TroubleshootOn Progress0/1Plan: Aug 31–Aug 31 | — |
| Ekamas Mora Republik - POP Villa Beji Bali_ACPDB & DCPDBProduct + InstalasiDeadline: Jul 10, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Aug 10–Aug 11 | Menerima SOP/MOPOn Progress0/1Plan: Aug 11–Aug 12 | Installation (L2)On Progress0/1Plan: Aug 12–Aug 12 | ATP/Testcom (L3)On Progress0/1Plan: Aug 12–Aug 13 | Functional Testing (L4)On Progress0/1Plan: Aug 13–Aug 14 | Integrated System Testing (L5)On Progress0/1Plan: Aug 14–Aug 14 | MaintenanceOn Progress0/1Plan: Aug 14–Aug 17 | TroubleshootOn Progress0/1Plan: Aug 17–Aug 17 | — |
| Hitachi - GI 150kV kruengProduct + InstalasiDeadline: Jul 22, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 20–Jul 21 | Menerima SOP/MOPOn Progress0/1Plan: Jul 21–Jul 22 | Installation (L2)On Progress0/1Plan: Jul 22–Jul 22 | ATP/Testcom (L3)On Progress0/1Plan: Jul 22–Jul 23 | Functional Testing (L4)On Progress0/1Plan: Jul 23–Jul 24 | Integrated System Testing (L5)On Progress0/1Plan: Jul 24–Jul 24 | MaintenanceOn Progress0/1Plan: Jul 24–Jul 27 | TroubleshootOn Progress0/1Plan: Jul 27–Jul 27 | — |
| PT. LTI_PO 26060314_ODC With Aircond 300W (1 Unit)Product + InstalasiDeadline: Jul 22, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Aug 6–Aug 7 | Menerima SOP/MOPOn Progress0/1Plan: Aug 7–Aug 10 | Installation (L2)On Progress0/1Plan: Aug 10–Aug 10 | ATP/Testcom (L3)On Progress0/1Plan: Aug 10–Aug 11 | Functional Testing (L4)On Progress0/1Plan: Aug 11–Aug 12 | Integrated System Testing (L5)On Progress0/1Plan: Aug 12–Aug 12 | MaintenanceOn Progress0/1Plan: Aug 12–Aug 13 | TroubleshootOn Progress0/1Plan: Aug 13–Aug 13 | — |
| Pembuatan Robot AGVProduct + InstalasiDeadline: Jul 24, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 22–Jul 22 | Menerima SOP/MOPOn Progress0/1Plan: Jul 22–Jul 23 | Installation (L2)On Progress0/1Plan: Jul 23–Jul 26 | ATP/Testcom (L3)On Progress0/1Plan: Jul 26–Jul 26 | Functional Testing (L4)On Progress0/1Plan: Jul 26–Jul 27 | Integrated System Testing (L5)On Progress0/1Plan: Jul 27–Jul 28 | MaintenanceOn Progress0/1Plan: Jul 28–Jul 28 | TroubleshootOn Progress0/1Plan: Jul 28–Jul 29 | — |
| ATOZ - Dakota Electrical Fitout (Batam)Product + InstalasiDeadline: Jul 24, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 16–Jul 17 | Menerima SOP/MOPOn Progress0/1Plan: Jul 17–Jul 20 | Installation (L2)On Progress0/1Plan: Jul 20–Jul 20 | ATP/Testcom (L3)On Progress0/1Plan: Jul 20–Jul 21 | Functional Testing (L4)On Progress0/1Plan: Jul 21–Jul 22 | Integrated System Testing (L5)On Progress0/1Plan: Jul 22–Jul 22 | MaintenanceOn Progress0/1Plan: Jul 22–Jul 23 | TroubleshootOn Progress0/1Plan: Jul 23–Jul 23 | — |
| BDX CGK3 - Electrical MaterialProduct + InstalasiDeadline: Jul 24, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 20–Jul 21 | Menerima SOP/MOPOn Progress0/1Plan: Jul 21–Jul 22 | Installation (L2)On Progress0/1Plan: Jul 22–Jul 22 | ATP/Testcom (L3)On Progress0/1Plan: Jul 22–Jul 23 | Functional Testing (L4)On Progress0/1Plan: Jul 23–Jul 24 | Integrated System Testing (L5)On Progress0/1Plan: Jul 24–Jul 24 | MaintenanceOn Progress0/1Plan: Jul 24–Jul 27 | TroubleshootOn Progress0/1Plan: Jul 27–Jul 27 | — |
| DNA Teknologi Indonesia - Caging System DHIProduct + InstalasiDeadline: Jul 28, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 23–Jul 24 | Menerima SOP/MOPOn Progress0/1Plan: Jul 24–Jul 27 | Installation (L2)On Progress0/1Plan: Jul 27–Jul 27 | ATP/Testcom (L3)On Progress0/1Plan: Jul 27–Jul 28 | Functional Testing (L4)On Progress0/1Plan: Jul 28–Jul 29 | Integrated System Testing (L5)On Progress0/1Plan: Jul 29–Jul 29 | MaintenanceOn Progress0/1Plan: Jul 29–Jul 30 | TroubleshootOn Progress0/1Plan: Jul 30–Jul 30 | — |
| Hitachi - ACP25099 - GI 150kV TakengonProduct + InstalasiDeadline: Jul 31, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 20–Jul 21 | Menerima SOP/MOPOn Progress0/1Plan: Jul 21–Jul 22 | Installation (L2)On Progress0/1Plan: Jul 22–Jul 22 | ATP/Testcom (L3)On Progress0/1Plan: Jul 22–Jul 23 | Functional Testing (L4)On Progress0/1Plan: Jul 23–Jul 24 | Integrated System Testing (L5)On Progress0/1Plan: Jul 24–Jul 24 | MaintenanceOn Progress0/1Plan: Jul 24–Jul 27 | TroubleshootOn Progress0/1Plan: Jul 27–Jul 27 | — |
| Ekamas Mora Republik - Open Rack 42U & Rack DCPDU 3U_PO# 174372Product + InstalasiDeadline: Aug 7, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Aug 3–Aug 4 | Menerima SOP/MOPOn Progress0/1Plan: Aug 4–Aug 5 | Installation (L2)On Progress0/1Plan: Aug 5–Aug 5 | ATP/Testcom (L3)On Progress0/1Plan: Aug 5–Aug 6 | Functional Testing (L4)On Progress0/1Plan: Aug 6–Aug 7 | Integrated System Testing (L5)On Progress0/1Plan: Aug 7–Aug 7 | MaintenanceOn Progress0/1Plan: Aug 7–Aug 10 | TroubleshootOn Progress0/1Plan: Aug 10–Aug 10 | — |
| Hitachi - ACP25105 - Seko IndokomasProduct + InstalasiDeadline: Aug 12, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 20–Jul 21 | Menerima SOP/MOPOn Progress0/1Plan: Jul 21–Jul 22 | Installation (L2)On Progress0/1Plan: Jul 22–Jul 22 | ATP/Testcom (L3)On Progress0/1Plan: Jul 22–Jul 23 | Functional Testing (L4)On Progress0/1Plan: Jul 23–Jul 24 | Integrated System Testing (L5)On Progress0/1Plan: Jul 24–Jul 24 | MaintenanceOn Progress0/1Plan: Jul 24–Jul 27 | TroubleshootOn Progress0/1Plan: Jul 27–Jul 27 | — |
| PT Roka Lane Asia - Rack Server 52U DWDM MMRProduct + InstalasiDeadline: Aug 21, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Aug 6–Aug 7 | Menerima SOP/MOPOn Progress0/1Plan: Aug 7–Aug 10 | Installation (L2)On Progress0/1Plan: Aug 10–Aug 10 | ATP/Testcom (L3)On Progress0/1Plan: Aug 10–Aug 11 | Functional Testing (L4)On Progress0/1Plan: Aug 11–Aug 12 | Integrated System Testing (L5)On Progress0/1Plan: Aug 12–Aug 12 | MaintenanceOn Progress0/1Plan: Aug 12–Aug 13 | TroubleshootOn Progress0/1Plan: Aug 13–Aug 13 | — |
| ERCS DCAM - Loadbank PanelProduct + InstalasiDeadline: Aug 24, 20260/7 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 6–Jul 10 | Menerima SOP/MOPOn Progress0/1Plan: Jul 1–Jul 10 | Installation (L2)On Progress0/1Plan: Aug 1–Aug 21 | ATP/Testcom (L3)On Progress0/1Plan: Aug 1–Aug 21 | Functional Testing (L4)On Progress0/1Plan: Aug 1–Aug 21 | Integrated System Testing (L5)On Progress0/1Plan: Aug 1–Aug 21 | MaintenanceOn Progress0/1Plan: Aug 28–Aug 28 | - | — |
| Hitachi - GI 150kV SribawonoProduct + InstalasiDeadline: Aug 25, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 20–Jul 21 | Menerima SOP/MOPOn Progress0/1Plan: Jul 21–Jul 22 | Installation (L2)On Progress0/1Plan: Jul 22–Jul 22 | ATP/Testcom (L3)On Progress0/1Plan: Jul 22–Jul 23 | Functional Testing (L4)On Progress0/1Plan: Jul 23–Jul 24 | Integrated System Testing (L5)On Progress0/1Plan: Jul 24–Jul 24 | MaintenanceOn Progress0/1Plan: Jul 24–Jul 27 | TroubleshootOn Progress0/1Plan: Jul 27–Jul 27 | — |
| Hitachi - GI 150kV KolakaProduct + InstalasiDeadline: Aug 28, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 20–Jul 21 | Menerima SOP/MOPOn Progress0/1Plan: Jul 21–Jul 22 | Installation (L2)On Progress0/1Plan: Jul 22–Jul 22 | ATP/Testcom (L3)On Progress0/1Plan: Jul 22–Jul 23 | Functional Testing (L4)On Progress0/1Plan: Jul 23–Jul 24 | Integrated System Testing (L5)On Progress0/1Plan: Jul 24–Jul 24 | MaintenanceOn Progress0/1Plan: Jul 24–Jul 27 | TroubleshootOn Progress0/1Plan: Jul 27–Jul 27 | — |
| Mega Akses Persada - BDF Power Papahan KaranganyarProduct + InstalasiDeadline: Aug 28, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Jul 29–Jul 30 | Menerima SOP/MOPOn Progress0/1Plan: Jul 30–Jul 31 | Installation (L2)On Progress0/1Plan: Jul 31–Jul 31 | ATP/Testcom (L3)On Progress0/1Plan: Jul 31–Aug 1 | Functional Testing (L4)On Progress0/1Plan: Aug 1–Aug 2 | Integrated System Testing (L5)On Progress0/1Plan: Aug 2–Aug 2 | MaintenanceOn Progress0/1Plan: Aug 2–Aug 5 | TroubleshootOn Progress0/1Plan: Aug 5–Aug 5 | — |
| Rumah Data Kita CGK11 - Rack Server 45UProduct + InstalasiDeadline: Sep 11, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Aug 20–Aug 21 | Menerima SOP/MOPOn Progress0/1Plan: Aug 21–Aug 24 | Installation (L2)On Progress0/1Plan: Aug 24–Aug 24 | ATP/Testcom (L3)On Progress0/1Plan: Aug 24–Aug 25 | Functional Testing (L4)On Progress0/1Plan: Aug 25–Aug 26 | Integrated System Testing (L5)On Progress0/1Plan: Aug 26–Aug 26 | MaintenanceOn Progress0/1Plan: Aug 26–Aug 27 | TroubleshootOn Progress0/1Plan: Aug 27–Aug 27 | — |
| Hitachi - ACP25111 - Muara Laboh Stage 2Product + InstalasiDeadline: Oct 23, 20260/8 aktivitas selesai | Site Survey On Progress0/1Plan: Aug 20–Aug 21 | Menerima SOP/MOPOn Progress0/1Plan: Aug 21–Aug 24 | Installation (L2)On Progress0/1Plan: Aug 24–Aug 24 | ATP/Testcom (L3)On Progress0/1Plan: Aug 24–Aug 25 | Functional Testing (L4)On Progress0/1Plan: Aug 25–Aug 26 | Integrated System Testing (L5)On Progress0/1Plan: Aug 26–Aug 26 | MaintenanceOn Progress0/1Plan: Aug 26–Aug 27 | TroubleshootOn Progress0/1Plan: Aug 27–Aug 27 | — |