| Internal - Stock Rack Server Moratel & DCPDUProduct + InstalasiDeadline: Jan 30, 20260/12 aktivitas selesai | Approved RR Overdue0/17moPlan: Dec 1–Dec 2 | Menerima Barang (RR) Overdue0/17moPlan: Nov 27–Nov 28 | Packing BarangOverdue0/16moPlan: Dec 30–Dec 30 | Packing BarangOverdue0/16moPlan: Jan 16–Jan 16 | Terima HO FG dr QAOverdue0/16moPlan: Dec 29–Dec 30 | PackingOverdue0/17moPlan: Nov 28–Dec 1 | Pickup BarangOverdue0/36moPlan: Jan 17–Jan 18 | Preapare MR&Cut StockOverdue0/17moPlan: Dec 2–Dec 2 | Preapare Barang yg siap kirimOverdue0/17moPlan: Dec 1–Dec 1 | Preapare Base On DO & Cut Stock Overdue0/17moPlan: Dec 2–Dec 3 | HO Loading UnloadingOverdue0/17moPlan: Dec 3–Dec 3 | Terima Balikan dr SiteOverdue0/16moPlan: Dec 31–Dec 31 | 7mo |
| Hitachi - ACP25035 - GI Satui 150kVProduct + InstalasiDeadline: Jun 19, 20260/12 aktivitas selesai | Approved RR Overdue0/17moPlan: Dec 17–Dec 18 | Menerima Barang (RR) Overdue0/17moPlan: Dec 15–Dec 16 | Packing BarangOverdue0/16moPlan: Jan 15–Jan 15 | Packing BarangOverdue0/13wPlan: Jun 18–Jun 18 | Terima HO FG dr QAOverdue0/16moPlan: Jan 14–Jan 15 | PackingOverdue0/17moPlan: Dec 16–Dec 17 | Pickup BarangOverdue0/13wPlan: Jun 19–Jun 19 | Preapare MR&Cut StockOverdue0/17moPlan: Dec 18–Dec 18 | Preapare Barang yg siap kirimOverdue0/17moPlan: Dec 17–Dec 17 | Preapare Base On DO & Cut Stock Overdue0/17moPlan: Dec 18–Dec 19 | HO Loading UnloadingOverdue0/17moPlan: Dec 19–Dec 19 | Terima Balikan dr SiteOverdue0/26moPlan: Jan 15–Jan 16 | 7mo |
| Kelinci Mas - DSS TallolamaProduct OnlyDeadline: Aug 7, 20260/12 aktivitas selesai | Approved RR Overdue0/18moPlan: Nov 20–Nov 21 | Menerima Barang (RR) Overdue0/18moPlan: Nov 16–Nov 19 | Packing BarangOverdue0/17moPlan: Dec 12–Dec 12 | Packing BarangOverdue0/13moPlan: Apr 10–Apr 15 | Terima HO FG dr QAOverdue0/17moPlan: Dec 11–Dec 12 | PackingOverdue0/18moPlan: Nov 19–Nov 20 | Pickup BarangOverdue0/13moPlan: Apr 16–Apr 16 | Preapare MR&Cut StockOverdue0/18moPlan: Nov 21–Nov 21 | Preapare Barang yg siap kirimOverdue0/18moPlan: Nov 20–Nov 20 | Preapare Base On DO & Cut Stock Overdue0/18moPlan: Nov 21–Nov 22 | HO Loading UnloadingOverdue0/18moPlan: Nov 22–Nov 22 | Terima Balikan dr SiteOverdue0/17moPlan: Dec 13–Dec 13 | 8mo |
| Shimizu - Loadbank IRISProduct + InstalasiDeadline: Feb 22, 20260/11 aktivitas selesai | Approved RR Overdue0/17moPlan: Nov 27–Nov 27 | Menerima Barang (RR) Overdue0/18moPlan: Nov 25–Nov 25 | Packing BarangOverdue0/16moPlan: Dec 28–Dec 29 | Packing BarangOverdue0/16moPlan: Dec 29–Dec 29 | Terima HO FG dr QAOverdue0/16moPlan: Dec 28–Dec 28 | PackingOverdue0/17moPlan: Nov 25–Nov 26 | Preapare MR&Cut StockOverdue0/17moPlan: Nov 27–Nov 30 | Preapare Barang yg siap kirimOverdue0/17moPlan: Nov 26–Nov 27 | Preapare Base On DO & Cut Stock Overdue0/17moPlan: Nov 30–Nov 30 | HO Loading UnloadingOverdue0/17moPlan: Nov 30–Dec 1 | Terima Balikan dr SiteOverdue0/26moPlan: Dec 29–Dec 30 | - | 8mo |
| Hitachi - ACP25026 - BalonganProduct + InstalasiDeadline: Jul 20, 20260/12 aktivitas selesai | Approved RR Overdue0/18moPlan: Nov 11–Nov 12 | Menerima Barang (RR) Overdue0/18moPlan: Nov 7–Nov 10 | Packing BarangOverdue0/17moPlan: Dec 11–Dec 11 | Packing BarangOn Progress0/1Plan: Jul 13–Jul 15 | Terima HO FG dr QAOverdue0/17moPlan: Dec 10–Dec 11 | PackingOverdue0/18moPlan: Nov 10–Nov 11 | Pickup BarangOn Progress0/1Plan: Jul 20–Jul 20 | Preapare MR&Cut StockOverdue0/18moPlan: Nov 12–Nov 12 | Preapare Barang yg siap kirimOverdue0/18moPlan: Nov 11–Nov 11 | Preapare Base On DO & Cut Stock Overdue0/18moPlan: Nov 12–Nov 13 | HO Loading UnloadingOverdue0/18moPlan: Nov 13–Nov 13 | Terima Balikan dr SiteOverdue0/17moPlan: Dec 11–Dec 12 | 8mo |
| Schneider - Panel for PUSRI IIIB Project // E2010-96440Product + InstalasiDeadline: May 26, 20262/12 aktivitas selesai | Approved RR Done1/1Plan: Oct 7–Oct 10Actual: Oct 7 | Menerima Barang (RR) Done1/1Plan: Oct 6–Oct 7Actual: Oct 7 | Packing BarangOverdue0/18moPlan: Nov 8–Nov 8 | Packing BarangOverdue0/12dPlan: Jul 2–Jul 6 | Terima HO FG dr QAOverdue0/18moPlan: Nov 7–Nov 8 | PackingOverdue0/19moPlan: Oct 6–Oct 7 | Pickup BarangOn Progress0/1Plan: Jul 9–Jul 9 | Preapare MR&Cut StockOverdue0/19moPlan: Oct 10–Oct 10 | Preapare Barang yg siap kirimOverdue0/19moPlan: Oct 7–Oct 7 | Preapare Base On DO & Cut Stock Overdue0/19moPlan: Oct 10–Oct 11 | HO Loading UnloadingOverdue0/19moPlan: Oct 11–Oct 11 | Terima Balikan dr SiteOverdue0/18moPlan: Nov 9–Nov 9 | 9mo |
| MECHANICAL PROSESProduct OnlyDeadline: Oct 12, 20220/7 aktivitas selesai | Menerima Barang (RR) Overdue0/1843moPlan: Nov 1–Dec 16 | Packing BarangOverdue0/2842moPlan: Nov 8–Jan 31 | RR Barang masuk Overdue0/2842moPlan: Nov 7–Jan 26 | Terima HO FG dr QAOverdue0/2842moPlan: Nov 8–Jan 30 | Entry HO FG dr QCOverdue0/1843moPlan: Nov 2–Dec 19 | PackingOverdue0/1843moPlan: Nov 3–Dec 20 | DeliveryOverdue0/1144moPlan: Nov 8–Nov 21 | - | - | - | - | - | 44mo |
| Forecast - Open Rack, Subrack, BB45UProduct OnlyDeadline: Sep 20, 20240/7 aktivitas selesai | Menerima Barang (RR) Overdue0/122moPlan: Sep 5–Sep 6 | Packing BarangOverdue0/121moPlan: Oct 2–Oct 3 | Packing BarangOverdue0/121moPlan: Oct 3–Oct 3 | RR Barang masuk Overdue0/121moPlan: Oct 1–Oct 2 | Terima HO FG dr QAOverdue0/121moPlan: Oct 2–Oct 2 | Entry HO FG dr QCOverdue0/122moPlan: Sep 6–Sep 9 | PackingOverdue0/122moPlan: Sep 9–Sep 9 | - | - | - | - | - | 22mo |
| PRODUCT & DEVELOPMENTProduct OnlyDeadline: Oct 12, 20220/6 aktivitas selesai | Menerima Barang (RR) Overdue0/344moPlan: Oct 27–Nov 30 | Packing BarangOverdue0/242moPlan: Jan 11–Jan 12 | RR Barang masuk Overdue0/243moPlan: Jan 5–Jan 9 | Terima HO FG dr QAOverdue0/242moPlan: Jan 9–Jan 11 | Entry HO FG dr QCOverdue0/344moPlan: Oct 28–Dec 1 | PackingOverdue0/344moPlan: Oct 31–Dec 2 | - | - | - | - | - | - | 44mo |
| ELEC_ LV_SYSTEMProduct OnlyDeadline: Oct 27, 20220/6 aktivitas selesai | Menerima Barang (RR) Overdue0/144moPlan: Dec 5–Dec 6 | Packing BarangOverdue0/142moPlan: Jan 18–Jan 19 | RR Barang masuk Overdue0/142moPlan: Jan 12–Jan 16 | Terima HO FG dr QAOverdue0/142moPlan: Jan 16–Jan 18 | Entry HO FG dr QCOverdue0/144moPlan: Dec 6–Dec 7 | PackingOverdue0/144moPlan: Dec 7–Dec 8 | - | - | - | - | - | - | 44mo |
| ENGINEERING OPRASIONAL 2022Product OnlyDeadline: Jun 9, 20220/4 aktivitas selesai | Packing BarangOverdue0/749moPlan: Jul 12–Jul 12 | RR Barang masuk Overdue0/749moPlan: Jul 11–Jul 12 | Terima HO FG dr QAOverdue0/749moPlan: Jul 12–Jul 12 | DeliveryOverdue0/749moPlan: Jul 12–Jul 12 | - | - | - | - | - | - | - | - | 49mo |
| ELEC_ HV_SYSTEMProduct OnlyDeadline: Oct 12, 20220/3 aktivitas selesai | Packing BarangOverdue0/245moPlan: Oct 17–Oct 18 | RR Barang masuk Overdue0/245moPlan: Oct 12–Oct 14 | Terima HO FG dr QAOverdue0/245moPlan: Oct 14–Oct 17 | - | - | - | - | - | - | - | - | - | 45mo |
| GSPE_STOK BOX PANEL MORATELProduct + InstalasiDeadline: Aug 13, 20250/2 aktivitas selesai | Packing BarangOverdue0/310moPlan: Sep 22–Sep 24 | Pickup BarangOverdue0/310moPlan: Sep 23–Sep 25 | - | - | - | - | - | - | - | - | - | - | 10mo |
| Forecast_Stock Panel Hitachi IP42 & IP54Product + InstalasiDeadline: Oct 10, 20250/2 aktivitas selesai | Packing BarangOverdue0/38moPlan: Oct 24–Oct 28 | Pickup BarangOverdue0/38moPlan: Oct 27–Oct 29 | - | - | - | - | - | - | - | - | - | - | 8mo |
| Internal - Micro Data Centre EatonProduct + InstalasiDeadline: Jan 23, 20260/2 aktivitas selesai | Packing BarangOverdue0/16moPlan: Jan 20–Jan 20 | Pickup BarangOverdue0/16moPlan: Jan 20–Jan 21 | - | - | - | - | - | - | - | - | - | - | 6mo |
| BDX - CGK1_RACK SERVER & rPDUProduct + InstalasiDeadline: Feb 6, 20260/2 aktivitas selesai | Packing BarangOverdue2/44moPlan: Jan 21–Mar 14Actual: Mar 15 | Pickup BarangOverdue2/45moPlan: Jan 21–Feb 15Actual: Mar 15 | - | - | - | - | - | - | - | - | - | - | 5mo |
| Internal - Layout Penambahan Unit Mesin HSGProduct + InstalasiDeadline: Feb 6, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 3–Mar 3 | Pickup BarangOverdue0/14moPlan: Mar 3–Mar 4 | - | - | - | - | - | - | - | - | - | - | 4mo |
| PT Telin - Instalasi CLS PluitProduct + InstalasiDeadline: Feb 26, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 17–Mar 18 | Pickup BarangOverdue0/14moPlan: Mar 18–Mar 19 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Job LeaderProduct + InstalasiDeadline: Feb 27, 20260/2 aktivitas selesai | Packing BarangOverdue0/17moPlan: Dec 22–Dec 23 | Pickup BarangOverdue0/17moPlan: Dec 23–Dec 24 | - | - | - | - | - | - | - | - | - | - | 7mo |
| Internal - Project ISO_27001Product + InstalasiDeadline: Feb 27, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 3–Mar 3 | Pickup BarangOverdue0/14moPlan: Mar 3–Mar 4 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Internal - Program Estimator (Containment, Container, Smart Rack)Product + InstalasiDeadline: Feb 27, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 3–Mar 4 | Pickup BarangOverdue0/14moPlan: Mar 4–Mar 5 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Internal - Automation Program CRM Section 1-4Product + InstalasiDeadline: Feb 27, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 3–Mar 4 | Pickup BarangOverdue0/14moPlan: Mar 4–Mar 5 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Internal - 29 Line AssemblyProduct + InstalasiDeadline: Feb 27, 20260/2 aktivitas selesai | Packing BarangOverdue0/26moPlan: Jan 15–Jan 15 | Pickup BarangOverdue0/16moPlan: Jan 15–Jan 16 | - | - | - | - | - | - | - | - | - | - | 6mo |
| Internal - Perbaikan Loading/Unloading Area Pintu BelakangProduct + InstalasiDeadline: Feb 27, 20260/2 aktivitas selesai | Packing BarangOverdue0/13moPlan: Apr 8–Apr 8 | Pickup BarangOverdue0/13moPlan: Apr 8–Apr 9 | - | - | - | - | - | - | - | - | - | - | 3mo |
| Review Product Presentation - Marketing UpdateProduct + InstalasiDeadline: Feb 27, 20260/2 aktivitas selesai | Packing BarangOverdue0/15moPlan: Feb 15–Feb 15 | Pickup BarangOverdue0/15moPlan: Feb 15–Feb 16 | - | - | - | - | - | - | - | - | - | - | 5mo |
| Mega Akses - POP Tegal Cangkring-Bali (Add Battery)Product + InstalasiDeadline: Mar 13, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Feb 24–Feb 25 | Pickup BarangOverdue0/14moPlan: Feb 25–Feb 26 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Internal - Mini Data Center Rack (MDCR) from ScheneiderProduct + InstalasiDeadline: Mar 27, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 6–Mar 6 | Pickup BarangOverdue0/14moPlan: Mar 6–Mar 7 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Mock Up - PT. Enerkomp Persada Raya Panel Soft Starter 250KWProduct + InstalasiDeadline: Mar 31, 20260/2 aktivitas selesai | Packing BarangOverdue0/16moPlan: Jan 18–Jan 18 | Pickup BarangOverdue0/16moPlan: Jan 18–Jan 19 | - | - | - | - | - | - | - | - | - | - | 6mo |
| GSPE_Smart Rack (Micro Data Center)Product + InstalasiDeadline: Apr 6, 20260/2 aktivitas selesai | Packing BarangOverdue0/15moPlan: Feb 1–Feb 1 | Pickup BarangOverdue0/15moPlan: Feb 1–Feb 2 | - | - | - | - | - | - | - | - | - | - | 5mo |
| Mega Akses - Req.Battery - JABODETABEKProduct + InstalasiDeadline: Apr 10, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 13–Mar 16 | Pickup BarangOverdue0/14moPlan: Mar 16–Mar 17 | - | - | - | - | - | - | - | - | - | - | 4mo |
| INTERNAL | - MDCC Trial Full Schneider Device - ContainerProduct + InstalasiDeadline: Apr 20, 20260/2 aktivitas selesai | Packing BarangOverdue0/94moPlan: Jan 20–Mar 7 | Pickup BarangOverdue0/104moPlan: Jan 21–Mar 8 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Internal - Smart rPDUProduct + InstalasiDeadline: Apr 30, 20260/2 aktivitas selesai | Packing BarangOverdue0/15moPlan: Feb 7–Feb 7 | Pickup BarangOverdue0/35moPlan: Feb 7–Feb 8 | - | - | - | - | - | - | - | - | - | - | 5mo |
| Mega Akses - BDF Power Tanah Merah (Add Battery)Product + InstalasiDeadline: Apr 30, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 24–Mar 25 | Pickup BarangOverdue0/13moPlan: Mar 25–Mar 26 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Schneider Electric - LNGPPProduct + InstalasiDeadline: Apr 30, 20260/2 aktivitas selesai | Packing BarangOverdue0/13moPlan: Apr 10–Apr 13 | Pickup BarangOverdue0/13moPlan: Apr 13–Apr 14 | - | - | - | - | - | - | - | - | - | - | 3mo |
| BDX - CGK1_Panel PDUProduct + InstalasiDeadline: May 21, 20260/2 aktivitas selesai | Packing BarangOverdue1/25moPlan: Jan 27–Jan 31Actual: Jan 31 | Pickup BarangOverdue1/25moPlan: Jan 27–Jan 31Actual: Jan 31 | - | - | - | - | - | - | - | - | - | - | 5mo |
| Internal - Forecast Rack Server : (42U, 45U, 52U)Product + InstalasiDeadline: May 29, 20260/2 aktivitas selesai | Packing BarangOverdue0/32moPlan: Mar 27–May 2 | Pickup BarangOverdue0/42moPlan: Mar 27–May 3 | - | - | - | - | - | - | - | - | - | - | 2mo |
| Siemens - UCC BP TangguhProduct + InstalasiDeadline: May 29, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 20–Mar 23 | Pickup BarangOverdue0/14moPlan: Mar 23–Mar 24 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Intan Mufakat Raya - GIS 150 KV Gandul II/PamulangProduct + InstalasiDeadline: Jun 10, 20260/2 aktivitas selesai | Packing BarangOverdue0/13moPlan: Apr 3–Apr 6 | Pickup BarangOverdue0/13moPlan: Apr 6–Apr 7 | - | - | - | - | - | - | - | - | - | - | 3mo |
| Kelinci Mas Unggul - Panel MK Single PhiProduct + InstalasiDeadline: Jun 10, 20260/2 aktivitas selesai | Packing BarangOverdue0/11moPlan: Jun 2–Jun 3 | Pickup BarangOverdue0/11moPlan: Jun 3–Jun 4 | - | - | - | - | - | - | - | - | - | - | 1mo |
| Hitachi - ACP25076 - Single Phi BarruProduct + InstalasiDeadline: Jun 16, 20260/2 aktivitas selesai | Packing BarangOverdue0/13wPlan: Jun 15–Jun 15 | Pickup BarangOverdue0/13wPlan: Jun 16–Jun 16 | - | - | - | - | - | - | - | - | - | - | 3w |
| Internal - MDCC 20 Feet POD Phase 2/IP65Product + InstalasiDeadline: Jun 30, 20260/2 aktivitas selesai | Packing BarangOverdue0/12moPlan: May 11–May 11 | Pickup BarangOverdue0/12moPlan: May 11–May 12 | - | - | - | - | - | - | - | - | - | - | 2mo |
| Internal - Contaiment 50 UnitProduct + InstalasiDeadline: Jun 30, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 24–Mar 24 | Pickup BarangOverdue0/14moPlan: Mar 24–Mar 25 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Internal - Pembuatan Bak Treatment, Hoist, Oven dan TrolleyProduct + InstalasiDeadline: Jun 30, 20260/2 aktivitas selesai | Packing BarangOverdue0/34moPlan: Feb 17–Mar 6 | Pickup BarangOverdue0/34moPlan: Feb 17–Mar 7 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Wholesale - Panel DB - Dermaga BiakProduct + InstalasiDeadline: Jun 30, 20260/2 aktivitas selesai | Packing BarangOverdue0/12wPlan: Jun 23–Jun 24 | Pickup BarangOverdue0/12wPlan: Jun 24–Jun 25 | - | - | - | - | - | - | - | - | - | - | 2w |
| PT. NexWave_Panel TXDP & SDP AC_PO25090188Product + InstalasiDeadline: Jul 3, 20260/2 aktivitas selesai | Packing BarangOverdue0/13wPlan: Jun 15–Jun 16 | Pickup BarangOverdue0/13wPlan: Jun 16–Jun 16 | - | - | - | - | - | - | - | - | - | - | 3w |
| Inti Bumi Mas - Panel FeederProduct + InstalasiDeadline: Jul 22, 20260/2 aktivitas selesai | Packing BarangOverdue0/13moPlan: Apr 7–Apr 8 | Pickup BarangOverdue0/13moPlan: Apr 8–Apr 9 | - | - | - | - | - | - | - | - | - | - | 3mo |
| Hitachi - ACP26018 - GI KM17 Borneo IndobaraProduct + InstalasiDeadline: Jul 30, 20260/2 aktivitas selesai | Packing BarangOverdue0/15dPlan: Jul 1–Jul 3 | Pickup BarangOverdue0/12dPlan: Jul 6–Jul 6 | - | - | - | - | - | - | - | - | - | - | 5d |
| Mega Akes - HUB Majalengka (Add Battery)Product + InstalasiDeadline: Jul 31, 20260/2 aktivitas selesai | Packing BarangOverdue0/14moPlan: Mar 24–Mar 25 | Pickup BarangOverdue0/13moPlan: Mar 25–Mar 26 | - | - | - | - | - | - | - | - | - | - | 4mo |
| Demo/Mockup Panel Typetest Cubic, Eaton MV, Eaton LVProduct + InstalasiDeadline: Aug 31, 20260/2 aktivitas selesai | Packing BarangOverdue0/34moPlan: Mar 3–Mar 3 | Pickup BarangOverdue0/34moPlan: Mar 3–Mar 4 | - | - | - | - | - | - | - | - | - | - | 4mo |
| PTT - Module MPTT DPC 3000 HE (25 unit)Product + InstalasiDeadline: Dec 19, 20251/2 aktivitas selesai | Packing BarangDone1/1Plan: Dec 16–Dec 17Actual: Dec 16 | Pickup BarangOverdue0/17moPlan: Dec 16–Dec 17 | - | - | - | - | - | - | - | - | - | - | 7mo |
| PT. Vivandiere Technology Indonesia - Renovasi Gedung Data Center BNPT - SentulProduct + InstalasiDeadline: Jun 1, 20260/1 aktivitas selesai | Packing BarangOverdue0/11moPlan: Jun 4–Jun 5 | - | - | - | - | - | - | - | - | - | - | - | 1mo |
| Mega Akses - Omadata SurabayaProduct + InstalasiDeadline: Jul 31, 20261/2 aktivitas selesai | Packing BarangDone1/1Plan: Jun 2–Jun 3Actual: May 8 | Pickup BarangOverdue0/11moPlan: Jun 2–Jun 3 | - | - | - | - | - | - | - | - | - | - | 1mo |
| PSN - Rack 20U UPS Hybrid + InverterProduct + InstalasiDeadline: Jun 3, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 27–Jul 27 | Pickup BarangOn Progress0/1Plan: Jul 27–Jul 27 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - ACP25053 - DSS Maumere 150kVProduct + InstalasiDeadline: Jul 6, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 8–Jul 9 | Pickup BarangOn Progress0/1Plan: Jul 10–Jul 10 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - ACP25085 - Sebuku PLN NPCProduct + InstalasiDeadline: Jul 6, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 29–Jul 30 | Pickup BarangOn Progress0/1Plan: Jul 31–Jul 31 | - | - | - | - | - | - | - | - | - | - | — |
| MIG - PO-26-0171 - Project Alladin Panel S110 & S510 - Panel DistributionProduct + InstalasiDeadline: Jul 8, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Aug 18–Aug 19 | Pickup BarangOn Progress0/1Plan: Aug 19–Aug 20 | - | - | - | - | - | - | - | - | - | - | — |
| Ekamas Mora Republik - POP Villa Beji Bali_ACPDB & DCPDBProduct + InstalasiDeadline: Jul 10, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Aug 4–Aug 5 | Pickup BarangOn Progress0/1Plan: Aug 5–Aug 6 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - ACP25029 - GI Tolinggula 150kVProduct + InstalasiDeadline: Jul 13, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 10–Jul 10 | Pickup BarangOn Progress0/1Plan: Jul 13–Jul 13 | - | - | - | - | - | - | - | - | - | - | — |
| Inti Bumi Mas - Panel VFD 132KWProduct + InstalasiDeadline: Jul 22, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 20–Jul 21 | Pickup BarangOn Progress0/1Plan: Jul 22–Jul 22 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - GI 150kV kruengProduct + InstalasiDeadline: Jul 22, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 14–Jul 15 | Pickup BarangOn Progress0/1Plan: Jul 15–Jul 16 | - | - | - | - | - | - | - | - | - | - | — |
| PT. LTI_PO 26060314_ODC With Aircond 300W (1 Unit)Product + InstalasiDeadline: Jul 22, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 31–Aug 3 | Pickup BarangOn Progress0/1Plan: Aug 3–Aug 4 | - | - | - | - | - | - | - | - | - | - | — |
| Pembuatan Robot AGVProduct + InstalasiDeadline: Jul 24, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 16–Jul 16 | Pickup BarangOn Progress0/1Plan: Jul 16–Jul 19 | - | - | - | - | - | - | - | - | - | - | — |
| ATOZ - Dakota Electrical Fitout (Batam)Product + InstalasiDeadline: Jul 24, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 10–Jul 13 | Pickup BarangOn Progress0/1Plan: Jul 13–Jul 14 | - | - | - | - | - | - | - | - | - | - | — |
| BDX CGK3 - Electrical MaterialProduct + InstalasiDeadline: Jul 24, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 14–Jul 15 | Pickup BarangOn Progress0/1Plan: Jul 15–Jul 16 | - | - | - | - | - | - | - | - | - | - | — |
| DNA Teknologi Indonesia - Caging System DHIProduct + InstalasiDeadline: Jul 28, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 17–Jul 20 | Pickup BarangOn Progress0/1Plan: Jul 20–Jul 21 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - ACP25099 - GI 150kV TakengonProduct + InstalasiDeadline: Jul 31, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 14–Jul 15 | Pickup BarangOn Progress0/1Plan: Jul 15–Jul 16 | - | - | - | - | - | - | - | - | - | - | — |
| Ekamas Mora Republik - Open Rack 42U & Rack DCPDU 3U_PO# 174372Product + InstalasiDeadline: Aug 7, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 28–Jul 29 | Pickup BarangOn Progress0/1Plan: Jul 29–Jul 30 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - ACP25105 - Seko IndokomasProduct + InstalasiDeadline: Aug 12, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 14–Jul 15 | Pickup BarangOn Progress0/1Plan: Jul 15–Jul 16 | - | - | - | - | - | - | - | - | - | - | — |
| PT Roka Lane Asia - Rack Server 52U DWDM MMRProduct + InstalasiDeadline: Aug 21, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 31–Aug 3 | Pickup BarangOn Progress0/1Plan: Aug 3–Aug 4 | - | - | - | - | - | - | - | - | - | - | — |
| ERCS DCAM - Loadbank PanelProduct + InstalasiDeadline: Aug 24, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 23–Jul 23 | Pickup BarangOn Progress0/1Plan: Jul 24–Jul 24 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - GI 150kV SribawonoProduct + InstalasiDeadline: Aug 25, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 14–Jul 15 | Pickup BarangOn Progress0/1Plan: Jul 15–Jul 16 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - GI 150kV KolakaProduct + InstalasiDeadline: Aug 28, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 14–Jul 15 | Pickup BarangOn Progress0/1Plan: Jul 15–Jul 16 | - | - | - | - | - | - | - | - | - | - | — |
| Mega Akses Persada - BDF Power Papahan KaranganyarProduct + InstalasiDeadline: Aug 28, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Jul 23–Jul 24 | Pickup BarangOn Progress0/1Plan: Jul 24–Jul 25 | - | - | - | - | - | - | - | - | - | - | — |
| Rumah Data Kita CGK11 - Rack Server 45UProduct + InstalasiDeadline: Sep 11, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Aug 14–Aug 17 | Pickup BarangOn Progress0/1Plan: Aug 17–Aug 18 | - | - | - | - | - | - | - | - | - | - | — |
| Hitachi - ACP25111 - Muara Laboh Stage 2Product + InstalasiDeadline: Oct 23, 20260/2 aktivitas selesai | Packing BarangOn Progress0/1Plan: Aug 14–Aug 17 | Pickup BarangOn Progress0/1Plan: Aug 17–Aug 18 | - | - | - | - | - | - | - | - | - | - | — |